§ 4a-100 — Prequalification of contractors and substantial subcontractors. Fees. Application. Regulations. Renewal. Revocation. Notice re state contractors or substantial contractors. Appeal. Notice re bond guaranty program.

Connecticut § 4a-100
JurisdictionConnecticut
Title 4aAdministrative Services
Ch. 58aPrequalification and Evaluation of Contractors

This text of Connecticut § 4a-100 (Prequalification of contractors and substantial subcontractors. Fees. Application. Regulations. Renewal. Revocation. Notice re state contractors or substantial contractors. Appeal. Notice re bond guaranty program.) is published on Counsel Stack Legal Research, covering Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conn. Gen. Stat. § 4a-100 (2026).

Text

(a)As used in this section:
(1)“Prequalification” means prequalification issued by the Commissioner of Administrative Services to bid on a contract or perform work pursuant to a contract for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building or any other public work by the state or a municipality, except a public highway or bridge project or any other construction project administered by the Department of Transportation, or to perform work under such a contract as a substantial subcontractor;
(2)“subcontractor” means a person who performs work with a value in excess of twenty-five thousand dollars for a contractor pursuant to a contract for work for the state or a municipality which is estimated to cost more than one million dollars; (3

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(P.A. 03-215, S. 3; 03-278, S. 129; June 30 Sp. Sess. P.A. 03-6, S. 146(g), (h); P.A. 04-141, S. 2; 04-189, S. 1; P.A. 06-134, S. 16, 22; P.A. 07-202, S. 3, 4; Sept. Sp. Sess. P.A. 09-7, S. 159; P.A. 11-51, S. 50; 11-229, S. 6; P.A. 13-140, S. 5; 13-247, S. 204; 13-304, S. 2; P.A. 14-182, S. 6; P.A. 19-126, S. 1; P.A. 21-198, S. 1, 2; P.A. 22-39, S. 3, 4; P.A. 23-204, S. 433.) History: P.A. 03-215 effective July 1, 2004; P.A. 03-278 amended Subsec. (a)(2) by redefining “subcontractor”, effective July 1, 2004; June 30 Sp. Sess. P.A. 03-6 replaced Commissioner and Department of Consumer Protection with Commissioner and Department of Agriculture and Consumer Protection, effective July 1, 2004; P.A. 04-141 added Subsec. (a)(4) and (5) defining “aggregate work capacity rating” and “single project limit”, amended Subsec. (f) to establish October 1, 2005, deadline for adoption of regulations by the commissioner and add provision re single project limits, amended Subsec. (g) to include references to single project limits and add provisions enabling the commissioner to issue prequalification certificates for an effective period not to exceed two years, amended Subsec. (h) to allow for the sending of the commissioner's preliminary determination by electronic mail, and made technical changes in Subsecs. (i) and (k)(2); P.A. 04-189 repealed Sec. 146 of June 30 Sp. Sess. P.A. 03-6, thereby reversing the merger of the Departments of Agriculture and Consumer Protection, effective June 1, 2004; P.A. 06-134 redefined “prequalification” in Subsec. (a) to include any other public work and except public highway or bridge projects, effective January 1, 2007, and further amended Subsec. (a) to redefine “prequalification” to include reference to work performed under such a contract as a substantial subcontractor and to define “substantial subcontractor”, amended Subsec. (c) to delete former Subdiv. (3) re applicant's experience and redesignate existing Subdivs. (4) to (7) as Subdivs. (3) to (6), amended Subsec. (f) to change performance look back period from within the past five years to a period of not less than the past three years and add references to substantial subcontractors, amended Subsec. (g) to provide for fee of not less than one-half of application fee and eliminate minimum fee of $600 in Subdiv. (3) and add references to substantial subcontractors in Subdivs. (1) and (2), amended Subsecs. (i) to (n), inclusive, to include references to substantial subcontractors and make technical changes, and added Subsec. (p) re regulations to establish a schedule of application fees for substantial subcontractors, effective October 1, 2007; P.A. 07-202 redefined “prequalification” in Subsec. (a)(1), defined “contract” in Subsec. (a)(6), amended Subsec. (i) to insert “or renew”, amended Subsec. (j) to enable commissioner to suspend contractor's prequalification certificate if commissioner determines there is probable cause to believe contractor engaged in conduct that significantly undermines contractor's skill, ability or integrity, amended Subsec. (k) to require substantial evidence of fraud, include references to update bid statement, include President of The University of Connecticut in list of persons to receive notice of false statement and require opportunity for a hearing prior to any revocation, amended Subsec. (l) to include reference to President of The University of Connecticut, amended Subsec. (n) to include update bid statement and made technical changes, effective July 10, 2007, and amended Subsec. (f) to delete provision re performance for a period of not less than the past three years, redesignated existing Subsec. (a)(6) as Subsec. (a)(7) and deleted Subsec. (p) re adoption of regulations, effective October 1, 2007; Sept. Sp. Sess. P.A. 09-7 amended Subsec. (j) to add references to substantial subcontractors, amended Subsec. (k) to make a technical change in Subdiv. (1), and replace references to person with references to contractor, substantial contractor, or principal or key personnel of such contractor or substantial contractor, add provision re entering plea of guilty or nolo contendere, or admitting to crime related to procurement or performance of any public or private construction contract, and eliminate provision re 5-year look back period in Subdiv. (2), amended Subsec. (n) to replace reference to bidders with reference to contractors and amended Subsec. (o) to replace reference to applicant with reference to contractor or substantial contractor, effective October 5, 2009; P.A. 11-51 amended Subsecs. (k)(1) and (l) to substitute “Commissioner of Construction Services” for “Commissioner of Public Works, effective July 1, 2011; P.A. 11-229 amended Subsec. (d) to make technical changes, to delete references to “plant and equipment” and “bank and credit references” re statement prepared, to add exception for applicants accepted into a certified community development financial institution bonding program, to replace “maximum” with “letter stating the aggregate work capacity and single project limit” re bonding capacity and to define “certified community development financial institution”; P.A. 13-140 amended Subsec. (c)(5) by deleting former Subpara. (B) re statement concerning whether applicant is on list distributed by Labor Commissioner pursuant to Sec. 31-57a and redesignating existing Subparas. (C) to (H) as Subparas. (B) to (G), effective June 18, 2013; P.A. 13-247 amended Subsecs. (k)(1) and (l) to delete references to Commissioner of Construction Services, effective July 1, 2013; P.A. 13-304 added Subsec. (p) re notice of bond guaranty program; P.A. 14-182 made a technical change in Subsec. (k)(2), effective June 12, 2014; P.A. 19-126 amended Subsec. (c) to delete references to pending investigations in Subdiv. (3), to add new Subdiv. (4) re proceedings relating to nonpayment or underpayment of wages or benefits and to redesignate existing Subdivs. (4) to (6) as Subdivs. (5) to (7); P.A. 21-198 amended Subsecs. (k) and (n) to delete references to update bid statement, effective July 1, 2021; P.A. 22-39 amended Subsec. (c) to add “settled or” in Subdiv. (3), add new Subdiv. (5) re adverse administrative proceedings and redesignate existing Subdivs. (5) to (7) as Subdivs. (6) to (8) and amended Subsec. (k)(2) to add new Subpara. (B) re withholding of information or documentation and redesignate existing Subparas. (B) and (C) as Subparas. (C) and (D); P.A. 23-204 amended Subsec. (a)(2),(6) and (7) to change references to the amount of estimated cost for work from $500,000 to $1,000,000.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Connecticut § 4a-100, Counsel Stack Legal Research, https://law.counselstack.com/statute/ct/4a-100.