This text of Connecticut § 22a-371 (Request for additional information. Notice of completed application. Notice of hearing. Waiver of hearing.) is published on Counsel Stack Legal Research, covering Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Conn. Gen. Stat. § 22a-371 (2026).
Text
(a)Within one hundred eighty days of receipt of an application for a permit, the commissioner shall determine if there is any additional information that he deems necessary to carry out the purposes of sections 22a-365 to 22a-378, inclusive. The applicant shall provide such information to the commissioner upon request.
(b)If the applicant does not furnish the requested information, the commissioner shall publish notice of his tentative determination on the application in accordance with section 22a-6h and shall hold or waive a public hearing in accordance with the provisions of subsection (f) of this section.
(c)If the commissioner finds that an application is complete, he shall notify the applicant by electronic means or certified mail, return receipt requested. The commissioner shall
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
(P.A. 82-402, S. 7, 16; P.A. 84-29, S. 1, 2; 84-546, S. 75, 173; P.A. 85-243, S. 1; P.A. 92-162, S. 10, 25; P.A. 93-381, S. 9, 39; 93-428, S. 6, 39; P.A. 95-94, S. 1; 95-250, S. 1; 95-257, S. 12, 21, 58; P.A. 96-211, S. 1, 5, 6; P.A. 04-151, S. 4; P.A. 10-32, S. 163; P.A. 11-80, S. 70; P.A. 13-209, S. 7.) History: P.A. 84-29 added Subsec. (g) authorizing the commissioner to waive the public hearing requirement for intrabasin transfers; P.A. 84-546 made technical change in Subsec. (e); P.A. 85-243 amended Subsec. (g) to apply public hearing waiver to cases which do not involve water transfers between regional rather than subregional drainage basins; P.A. 92-162 amended Subsec. (c) to revise some language for clarity and to delete requirement that hearings on applications under this section be held within 120 days of notification by the commissioner of a complete application, amended Subsec. (d) to modify the notice requirements for certain officials and to add conservation commissions, wetlands agencies and interested persons as recipients of notice under this section, deleted former Subsecs. (e) and (g), relettering Subsec. (f) accordingly and added new Subsec. (f) re notice and hearing requirements for approval of permits under this section; P.A. 93-381 replaced commissioner of health services with commissioner of public health and addiction services, effective July 1, 1993; P.A. 93-428 amended Subsec. (f) to specify that notice include commissioner's tentative decision in cases where he intends to waive hearing, effective July 1, 1993; P.A. 95-94 amended Subsec. (a) to change from 30 to 120 the number of days the commissioner has to determine if additional information is needed and to give the applicant the option of asking the application to be deemed complete as is rather than submit more information and amended Subsec. (b) to require the commissioner to publish notice and hold or waive a public hearing, eliminating the requirement that he return the application; P.A. 95-250 and P.A. 96-211 replaced Commissioner and Department of Economic Development with Commissioner and Department of Economic and Community Development; P.A. 95-257 replaced Commissioner and Department of Public Health and Addiction Services with Commissioner and Department of Public Health, effective July 1, 1995; P.A. 04-151 amended Subsec. (a) to change determination deadline from 120 days to 180 days and to remove provision re requesting that application be deemed complete and amended Subsec. (f) to change publication and notice requirements from 20 days to 30 days prior to commencement of hearing and to remove provision re publication twice at intervals of not less than 2 days, effective May 21, 2004; P.A. 10-32 made a technical change in Subsec. (d), effective May 10, 2010; P.A. 11-80 amended Subsec. (d) by changing “Public Utilities Control Authority” to “Public Utilities Regulatory Authority”, effective July 1, 2011; P.A. 13-209 amended Subsecs. (c) and (d) by authorizing commissioner to provide notification by electronic means. Cited. 28 CA 674. Because commissioner did not give plaintiff an opportunity to remedy application's deficiencies or to request that application be deemed complete as submitted and have those deficiencies examined in the forum of a public hearing, notice of rejection was a final decision in a contested case and meets requirements for appeal pursuant to Sec. 4-183, despite absence of a public hearing. 71 CA 395.
Nearby Sections
15
§ 22a-1
Policy of the state.§ 22a-10
Payment of refunds.§ 22a-101
Municipal coastal programs.§ 22a-105
Coastal site plan reviews.§ 22a-106a
Civil penalty.§ 22a-108
Violations.§ 22a-109
Coastal site plans. Review.Cite This Page — Counsel Stack
Bluebook (online)
Connecticut § 22a-371, Counsel Stack Legal Research, https://law.counselstack.com/statute/ct/22a-371.