Connecticut Statutes

§ 16-32n — Cost-benefit analysis concerning resources expended and existing staffing levels during storm events. Minimum staffing levels and acceptable performance standards for electric distribution companies. Penalties.

Connecticut·Title 16 Public Service Companies·Ch. 277 Department of Energy and Environmental Protection. Public Utilities Regulatory Authority. Office of Consumer Counsel. Miscellaneous Provisions
(a)As used in this section, “electric distribution company” has the same meaning as provided in section 16-1.
(b)Not later than January 1, 2021, each electric distribution company shall submit to the joint standing committee of the General Assembly having cognizance of matters relating to energy, in accordance with the provisions of section 11-4a , and the Public Utilities Regulatory Authority the following:
(1)A cost-benefit analysis identifying the resources expended in response to the last five storm events classified as a level three, four or five. Such analysis shall include a review of the number of line crew workers and shall distinguish between line crew workers (A) directly employed by the electric distribution company and working full time within the state, (B) directly employ

Free access — add to your briefcase to read the full text and ask questions with AI

Connecticut § 16-32n (Cost-benefit analysis concerning resources expended and existing staffing levels during storm events. Minimum staffing levels and acceptable performance standards for electric distribution companies. Penalties.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

(Sept. Sp. Sess. P.A. 20-5, S. 12.) History: Sept. Sp. Sess. P.A. 20-5 effective October 2, 2020.