This text of Connecticut § 13a-95b (Designation of projects using construction-manager-at-risk or design-build contracts.) is published on Counsel Stack Legal Research, covering Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conn. Gen. Stat. § 13a-95b (2026).

Text

(a)The Commissioner of Transportation may, as an alternative to using a design-bid-build contract, designate specific projects to be completed using a (1) construction-manager-at-risk contract with a guaranteed maximum price, or (2) design-build contract.
(b)If the commissioner designates a project to use a construction-manager-at-risk contract with a guaranteed maximum price, the commissioner may have the project designed by department personnel or enter into a contract with an architect or engineer for the project design, and may also enter into a contract with a construction-manager-at-risk contractor who will provide input during the design process and may be responsible for the construction of the project. The commissioner may permit the contractor to self-perform a portion of the c

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(P.A. 12-70, S. 1; P.A. 13-277, S. 14; June Sp. Sess. P.A. 15-5, S. 159; P.A. 17-230, S. 2.) History: P.A. 12-70 effective June 6, 2012; P.A. 13-277 amended Subsec. (a) to delete “pursuant to this chapter”, effective July 1, 2013; June Sp. Sess. P.A. 15-5 amended Subsec. (b) to allow project to be designed by department personnel, to permit the contractor to self-perform a portion of the work and to allow for bids where a guaranteed maximum price cannot be agreed upon and amended Subsecs. (b) and (c) to allow notice of projects to be posted on Department of Administrative Services State Contracting Portal or through other advertising methods, effective June 30, 2015; P.A. 17-230 amended Subsecs. (b) and (c) by deleting provisions re notice of projects to be advertised in a newspaper.