§ 2812.5. — 2812.5. (Added by Stats. 1976, Ch. 915.)
California § 2812.5.
JurisdictionCalifornia
Code PUCPublic Utilities Code - PUC
Div. 1.DIVISION 1. REGULATION OF PUBLIC UTILITIES
Part 2.PART 2. SPECIFIC PUBLIC UTILITIES
Ch. 7.CHAPTER 7. Private Energy Producers
Art. 2.ARTICLE 2. Interconnection of Facilities
This text of California § 2812.5. (2812.5. (Added by Stats. 1976, Ch. 915.)) is published on Counsel Stack Legal Research, covering California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Cal. Public Utilities Code - PUC Code § 2812.5. (2026).
Text
Upon application of a private energy producer, and after notice to any affected public utility and hearing thereon, the commission shall authorize such producer to construct an interconnection for the purpose of transmitting electricity, if the commission finds:
(1)That no uncompensated burden will be placed upon the utility or utilities furnishing the transmission service.
(2)That furnishing the transmission service will not result in any added costs or any other adverse consequences for the customers of the electrical corporation.
(3)That the facilities proposed in the application will be used to transmit power from other than a conventional power source for generating electrical power.
The commission shall prescribe such reasonable terms, conditions, and requirements as it deems appr
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Added by Stats. 1976, Ch. 915.