§ 7108.5. — 7108.5. (Amended by Stats. 2011, Ch. 700, Sec. 1.)

California·Code BPC Business and Professions Code - BPC·Div. 3. DIVISION 3. PROFESSIONS AND VOCATIONS GENERALLY·Ch. 9. CHAPTER 9. Contractors·Art. 7. ARTICLE 7. Disciplinary Proceedings
(a)A prime contractor or subcontractor shall pay to any subcontractor, not later than seven days after receipt of each progress payment, unless otherwise agreed to in writing, the respective amounts allowed the contractor on account of the work performed by the subcontractors, to the extent of each subcontractor’s interest therein. In the event that there is a good faith dispute over all or any portion of the amount due on a progress payment from the prime contractor or subcontractor to a subcontractor, the prime contractor or subcontractor may withhold no more than 150 percent of the disputed amount.
(b)Any violation of this section shall constitute a cause for disciplinary action and shall subject the licensee to a penalty, payable to the subcontractor, of 2 percent of the amount

Free access — add to your briefcase to read the full text and ask questions with AI

California § 7108.5. (7108.5. (Amended by Stats. 2011, Ch. 700, Sec. 1.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Legislative History

Amended by Stats. 2011, Ch. 700, Sec. 1. (SB 293) Effective January 1, 2012.

Nearby Sections

3
View on official source ↗