§ 40-360.02 — Plans; filing; failure to comply; classification
Arizona § 40-360.02
JurisdictionArizona
Title 40Arizona Revised Statutes
Ch. 2PUBLIC SERVICE CORPORATIONS GENERALLY
Art. 6.Power Plant and Transmission Line Siting Committee
This text of Arizona § 40-360.02 (Plans; filing; failure to comply; classification) is published on Counsel Stack Legal Research, covering Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ariz. Rev. Stat. Ann. § 40-360.02 (2026).
Text
A.Every person contemplating construction of any transmission line within the state during any ten year period shall file a ten year plan with the commission on or before January 31 of each year.
B.Every person contemplating construction of any plant within the state shall file a plan with the commission ninety days before filing an application for a certificate of environmental compatibility as provided in section 40-360.03.
C.Each plan filed pursuant to subsection A or B of this section shall set forth the following information with respect to the proposed facilities to the extent such information is available:
1.The size and proposed route of any transmission lines or location of each plant proposed to be constructed.
2.The purpose to be served by each proposed transmission lin
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 40-1001
Unclaimed freight or baggage§ 40-1003
Inspection; record of sale§ 40-1004
Proceeds of sale; disposition§ 40-1005
Perishable freight or baggage§ 40-103
Corporation commission seal§ 40-106
Legal services§ 40-110
Consumer services section§ 40-1111
DefinitionsCite This Page — Counsel Stack
Bluebook (online)
Arizona § 40-360.02, Counsel Stack Legal Research, https://law.counselstack.com/statute/az/40-360.02.