Arizona Statutes
§ 33-1058 — Withholding monies by construction lenders; payment bond
Arizona § 33-1058
This text of Arizona § 33-1058 (Withholding monies by construction lenders; payment bond) is published on Counsel Stack Legal Research, covering Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ariz. Rev. Stat. Ann. § 33-1058 (2026).
Text
A.On receipt of a stop notice pursuant to section 33-1055, the construction lender may and on receipt of a bonded stop notice shall withhold from the borrower or other person to whom it or the owner may be obligated to make payments or advances out of the construction fund sufficient monies to answer the claim and any claim of lien that may be recorded. If a payment bond has previously been recorded in accordance with section 33-1003, the construction lender shall withhold monies pursuant to a bonded stop notice filed by the original contractor and, at its option, may withhold monies pursuant to a stop notice or bonded stop notice given by anyone other than the original contractor.
B.The construction lender may elect not to withhold pursuant to a bonded stop notice if a payment bond has
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 33-1005
Payments made in trust§ 33-1007
Definition of professional services§ 33-1008
Waiver of lien§ 33-101
Petition to establish landmarks§ 33-1021.01
Dry cleaners' and launderers' lien; foreclosure§ 33-1022
Garages; aircraft§ 33-1022.01
Fabrication work; lienCite This Page — Counsel Stack
Bluebook (online)
Arizona § 33-1058, Counsel Stack Legal Research, https://law.counselstack.com/statute/az/33-1058.