§ 22-9-604 — Procedure

Arkansas·Title 22
(a)(1) (A) In the case of a construction contract entered into between a public agency and a contractor who is required to furnish a performance and payment bond, the contractor shall be entitled to payment of ninety-five percent (95%) of the earned progress payments when due, with the public agency retaining five percent (5%) to assure faithful performance of the construction contract.
(B)(i) A public agency may forego withholding retainage of the progress payments if:
(a)The construction contract is fifty-percent (50%) complete;
(b)The contractor has provided the work in a satisfactory manner; and (c) The design professional and public agency agree with and approve of subdivisions (a)(1)(B)(i) (a) and (b) of this section.
(ii)This subdivision (a)(1)(B) does not prohibit a public age

Free access — add to your briefcase to read the full text and ask questions with AI

Arkansas § 22-9-604 (Procedure) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Opinion No.
(Arkansas Attorney General Reports, 1992)

Legislative History

Amended by Act 2015, No. 866,§ 1, eff. 7/22/2015. Acts 1977, No. 235, §§ 2, 3; A.S.A. 1947, §§ 14-653.1, 14-653.2; Acts 2007, No. 471, § 3; 2009, No. 193, § 10.