Arkansas Statutes
§ 22-9-604 — Procedure
Arkansas § 22-9-604
JurisdictionArkansas
Title22
This text of Arkansas § 22-9-604 (Procedure) is published on Counsel Stack Legal Research, covering Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ark. Code Ann. § 22-9-604 (2026).
Text
(a)(1) (A) In the case of a construction contract entered into between a public agency and a contractor who is required to furnish a performance and payment bond, the contractor shall be entitled to payment of ninety-five percent (95%) of the earned progress payments when due, with the public agency retaining five percent (5%) to assure faithful performance of the construction contract.
(B)(i) A public agency may forego withholding retainage of the progress payments if:
(a)The construction contract is fifty-percent (50%) complete;
(b)The contractor has provided the work in a satisfactory manner; and (c) The design professional and public agency agree with and approve of subdivisions (a)(1)(B)(i) (a) and (b) of this section.
(ii)This subdivision (a)(1)(B) does not prohibit a public age
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Opinion No.
(Arkansas Attorney General Reports, 1992)
Legislative History
Amended by Act 2015, No. 866,§ 1, eff. 7/22/2015. Acts 1977, No. 235, §§ 2, 3; A.S.A. 1947, §§ 14-653.1, 14-653.2; Acts 2007, No. 471, § 3; 2009, No. 193, § 10.
Nearby Sections
15
§ 22-1-201
Roads and parks§ 22-1-202
Municipal waterworks lands§ 22-1-206
Property of levee districts - Definition§ 22-10-101
Title§ 22-10-102
Legislative findings - Purpose§ 22-10-103
Definitions§ 22-10-104
Construction - Supplemental nature - Intent§ 22-10-105
Application§ 22-10-201
Responsible public entity§ 22-10-203
Requirements for proposalsCite This Page — Counsel Stack
Bluebook (online)
Arkansas § 22-9-604, Counsel Stack Legal Research, https://law.counselstack.com/statute/ar/22-9-604.