Zurich American Ins. v. AIU Ins. CA1/2

CourtCalifornia Court of Appeal
DecidedAugust 28, 2013
DocketA133700
StatusUnpublished

This text of Zurich American Ins. v. AIU Ins. CA1/2 (Zurich American Ins. v. AIU Ins. CA1/2) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zurich American Ins. v. AIU Ins. CA1/2, (Cal. Ct. App. 2013).

Opinion

Filed 8/28/13 Zurich American Ins. v. AIU Ins. CA1/2 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION TWO

ZURICH AMERICAN INSURANCE COMPANY, Plaintiff and Appellant, A133700

v. (Alameda County AIU INSURANCE COMPANY, Super. Ct. Nos. RG-07-360089, RG-08-416902 ) Defendant and Respondent, LEXINGTON INSURANCE COMPANY, Defendant and Appellant.

I. INTRODUCTION This appeal arises out of a protracted dispute regarding liability and insurance coverage for property damage to an office building caused by a construction defect. In this round of litigation, Zurich American Insurance Company (Zurich) sought equitable indemnity and subrogation from AIU Insurance Company (AIU) for a $900,000 payment that Zurich made to settle claims against the parties’ mutual insured, Frederick Meiswinkel Co., Inc. (FMI). Zurich also sought equitable contribution from Lexington Insurance Company (Lexington) for a portion of the defense costs it paid in the underlying property damage case against FMI. After a non-jury trial, the superior court found that AIU was not liable for the settlement payment that Zurich paid on behalf of FMI because the claims against FMI in the underlying action were excluded from coverage under an AIU policy exclusion for

1 damages caused by FMI’s work. The court also found, however, that Lexington failed to pay its share of the defense costs of the underlying lawsuit against FMI and that it owed that amount to Zurich. Both Zurich and Lexington filed appeals. We affirm. II. FACTUAL AND PROCEDURAL BACKGROUND A. The Hopyard Project In 1996, C.M. Centerprop commenced plans to develop a commercial office building at 5050 Hopyard Road in Pleasanton. In February 1997, Centerprop executed a prime contract with the general contractor, L.E. Wentz Co. The building plans called for an “exterior insulation finish system” (an EIFS system), which would be a “design build” element of the project. In July 1997, Wentz entered into a subcontract with FMI, pursuant to which FMI agreed to design, furnish and install the EIFS system on the Hopyard building. The EIFS system that FMI designed called for a “bullnose” component, a piece of shaped foam that resembles a bull’s nose. FMI obtained the bullnoses from Bay Foam, Inc. To construct the bullnoses, Bay Foam used its machines to cut foam blocks into the specifically-designed element, applied modified cement to them, embedded fiberglass mesh, reapplied additional acrylic layers, and then delivered them to the jobsite. There was no written agreement between FMI and Bay Foam regarding the fabrication and provision of these bullnoses. Building construction was completed in 1998. That winter, the EIFS system started to crack and leak. In 1999, both FMI and Bay Foam made repair attempts but the EIFS system continued to fail. B. The Chawin Action In 2004, Chawin Property, Inc., Centerprop’s successor in interest, filed an action for damages for breach of contract, breach of warranty and negligence against Wentz, FMI and others. At some point, Chawin named Bay Foam as a defendant and alleged a cause of action against it for negligence. Wentz also filed a cross-complaint for indemnity against FMI.

2 Chawin settled some of its claims relating to damage caused by leaking decks on the Hopyard building. However, the “EIFS-related disputes” were submitted to binding arbitration. Although Bay Foam had not entered into a contract with any other party and had no contractual obligation to arbitrate, it agreed to participate. However, Bay Foam settled with Chawin and was dismissed from the action before the arbitration hearing commenced. In late January 2006, a 10-day arbitration hearing was conducted before Arbitrator Ernest C. Brown. The parties stipulated that the EIFS system had caused significant leaks starting in the winter of 1998. The key issues at the hearing included identifying causes of the leaks, selecting the proper repair method and assessing legal responsibility for the damage. On March 28, 2006, the arbitrator set forth his findings in an interim award, which was subsequently incorporated into a final award that was entered on July 14, 2006. The following month, the arbitrator filed a “Clarification” of the disposition and award. In this opinion, we will refer to these three related orders as the final award. On the issue of causation, the arbitrator’s findings included the following: (1) FMI had “design build” responsibility for the EIFS system. (2) The “principal reason” for the cracking of the EIFS system was “the lack of proper placement of the reinforcing mesh within the cross-sections of the laminate” on the foam shapes supplied by Bay Foam. (3) Bay Foam was primarily responsible for the failure of the EIFS system because it improperly applied the mesh to the foam shapes that it supplied to FMI. (4) The “secondary reasons” for the system failure were design defects attributable to FMI. (5) FMI’s field installation technique was also a contributing factor to the harm. The appropriate repair method was the subject of extensive disagreement among the parties. Ultimately, the arbitrator concluded that the existing EIFS System should be replaced with a new Outsulation System. The arbitrator also found that Chawin’s damages associated with that repair totaled $3,143,500. In assessing the legal liability of the parties, the arbitrator found that Wentz was liable to Chawin, and that FMI was liable to both Wentz and Chawin. FMI was liable to Wentz for breach of the subcontract, breach of warranty and negligence because it failed

3 to adhere to product manufacturer specifications as well as good practices in the EIFS industry, and because, “[a]s the EIFS Design-Build subcontractor, FMI [was] legally responsible for the erroneous mesh embedment in the materials supplied by its supplier, Bay Foam.” FMI was also liable to Chawin for negligence and, therefore, Chawin could recover damages directly from FMI. The final award holds FMI and Wentz jointly and severally liable for Chawin’s damages, although it also gives them an $825,000 credit for the Chawin-Bay Foam settlement. The final award also holds FMI and Wentz jointly and severally liable for Chawin’s attorney fees and costs, although it apportions three quarters of the liability for those amounts to FMI. In October 2006, Chawin, Wentz and FMI settled all of their claims arising out of the Hopyard project pursuant to an agreement which was coordinated with a related partial settlement of an action that FMI had filed against its insurance companies. C. FMI’s Insurance Coverage and Bad Faith Action In May 2006, before the final award was entered by the Chawin arbitrator, FMI filed an action against four insurances companies that had issued policies to FMI during the period when the damage to the Hopyard building could potentially have occurred: Zurich, Lexington, Transcontinental Insurance Company, which was later acquired by CNA, and AIU. During the relevant time period, FMI had obtained successive policies affording primary commercial insurance coverage from Transcontinental Insurance Company/CNA (1998-2000), Zurich (2001) and Lexington (2002-2003). In 1998 and 1999, FMI was also covered under excess insurance policies issued by AIU, a company affiliated with Lexington via their parent, American Insurance Group (AIG). FMI’s complaint against these insurers included causes of action for breach of contract and breach of the implied covenant of good faith and fair dealing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vandenberg v. Superior Court
982 P.2d 229 (California Supreme Court, 1999)
Esgro Central, Inc. v. General Insurance
20 Cal. App. 3d 1054 (California Court of Appeal, 1971)
Hartford Accident & Indemnity Co. v. Sequoia Insurance
211 Cal. App. 3d 1285 (California Court of Appeal, 1989)
State Farm General Insurance v. Mintarsih
175 Cal. App. 4th 274 (California Court of Appeal, 2009)
OneBeacon America Insurance v. Fireman's Fund Insurance
175 Cal. App. 4th 183 (California Court of Appeal, 2009)
People Ex Rel. Sneddon v. Torch Energy Services, Inc.
125 Cal. Rptr. 2d 365 (California Court of Appeal, 2002)
Griffin Dewatering Corp. v. Northern Ins. Co. of New York
176 Cal. App. 4th 172 (California Court of Appeal, 2009)
Executive Risk Indemnity, Inc. v. Jones
171 Cal. App. 4th 319 (California Court of Appeal, 2009)
Hassoldt v. Patrick Media Group, Inc.
100 Cal. Rptr. 2d 662 (California Court of Appeal, 2000)
Prichard v. Liberty Mutual Insurance
101 Cal. Rptr. 2d 298 (California Court of Appeal, 2000)
SFPP, L.P. v. Burlington Northern & Santa Fe Railway
17 Cal. Rptr. 3d 96 (California Court of Appeal, 2004)
Heaps v. Heaps
21 Cal. Rptr. 3d 239 (California Court of Appeal, 2004)
Collett v. Insurance Co. of the West
75 Cal. Rptr. 2d 165 (California Court of Appeal, 1998)
National Union Fire Ins. v. Structural Sys. Tech.
756 F. Supp. 1232 (E.D. Missouri, 1991)
Thibodeau v. Crum
4 Cal. App. 4th 749 (California Court of Appeal, 1992)
Scottsdale Ins. Co. v. MV TRANSP.
115 P.3d 460 (California Supreme Court, 2005)
Kruger v. California Highway Indemnity Exchange
258 P. 602 (California Supreme Court, 1927)
Fireman's Fund Insurance v. Maryland Casualty Co.
65 Cal. App. 4th 1279 (California Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Zurich American Ins. v. AIU Ins. CA1/2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zurich-american-ins-v-aiu-ins-ca12-calctapp-2013.