Zumsteg v. Ætna Casualty & Surety Co.

31 F.2d 65, 1929 U.S. App. LEXIS 3391
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 20, 1929
DocketNo. 8239
StatusPublished
Cited by2 cases

This text of 31 F.2d 65 (Zumsteg v. Ætna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zumsteg v. Ætna Casualty & Surety Co., 31 F.2d 65, 1929 U.S. App. LEXIS 3391 (8th Cir. 1929).

Opinion

KENTON, Circuit Judge.

Appellant brought action against appellee in the District Court of the United States for the District of Colorado, claiming damages for various items hereinafter discussed. The trial court entered judgment on the pleadings in favor of appellee, and dismissed the complaint. The ease, therefore, is to be determined on the pleadings.

This court has said in Walker et al. v. Traylor Engineering & Mfg. Co. (C. C. A.) 12 F.(2d) 382, 385, that these questions are determinable by the laws of the state “regulating the practice and pleadings in the courts of that state.” Under the laws of Colorado, where this ease originated and was tried, the courts hold that the motion for judgment on the pleadings is “allowed only when it affirmatively appears that the party against whom the motion is interposed is without right” (Childers v. Baird et al., 59 Colo. 382, 148 P. 854), and that motion for judgment on the pleadings cannot be entertained where a material issue of fact is tendered (Lamon v. Zamp, 81 Colo. 90, 253 P. 1056; Williams v. Rocky Mountain Fuel Co., 55 Colo. 133, 133 P. 742; Richards et al. v. Stewart, 53 Colo. 205, 124 P. 740). These holdings present substantially the same test laid down by this court, viz., that the judgment rendered on the pleadings to be valid “must be sustained by undisputed facts appearing in the pleadings.” Klink v. Chicago, R. I. & P. Ry. Co. (C. C. A.) 219 F. 457, 461.

Does it affirmatively appear from the pleadings that appellant had no right to recover; that a situation is presented where there is no material question of fact to litigate? The answer to this requires careful examination of the pleadings.

The complaint is a very extended one, and the alleged facts stated therein and gathered from the exhibits attached thereto are substantially as follows:

On July 20,1923, Knowlton & Terry, contractors, made a contract with the government of the United States for the construction of a road known as the Cameron Pass project in Colorado. Bond, upon which appellee was surety, was executed by them for carrying out the contract. They performed some 24 per cent, of this work between August 1,1923, and December 1,1923. Weather conditions made it impossible to proceed further at that time. In the spring of 1924 they had failed to pay approximately $8,009 of construction bills, and appellee was notified by the United States to take over the project and complete it. In pursuance of this, Knowlton & Terry in April, 1924, assigned their contract to appellee; it assuming their obligations to the government.

April 26, 1924, appellee entered into a contract with one Johnson, which contract is made part of the complaint, and under the terms of which Johnson was to complete the contract made by Knowlton & Terry with the government, appellee to collect the moneys due from the United States on proper estimates and to promptly pay the same over to Johnson.

Shortly after this arrangement was made Johnson and appellant entered into an oral agreement, by which appellant agreed to advance moneys to Johnson to be used in the performance of the work, and to have an interest in the contract, to be determined by the amount advanced. Under this arrangement appellant advanced to Johnson $11,136.86. November 1,1924, Johnson executed and delivered to appellant a written assignment of his interest under the April 26, 1924, contract. After April 26, 1924, Johnson prosecuted the work until about September 20, 1924, when work was discontinued on account of weather conditions. During that period the moneys paid by the government to appellee were turned over to Johnson. Work was resumed June 5, 1925, by Johnson, and continued until August 14,1925.

December 20, 1924, appellant and Johnson notified appellee of the oral and written assignments made by Johnson to appellant of his interest under the contract.

December 20, 1924, appellee was served with garnishee summons in a ease pending in the state district court in Colorado, in which the city of Glenwood Springs was plaintiff and Johnson was one of the defendants. Appellee answered this summons, denying any indebtedness to Johnson, and stating that it was advised that Johnson had assigned his interest in the April 26, 1924, contract to appellant. The city of Glenwood Springs traversed said garnishee answer. After the traverse was filed, appellant, as assignee of Johnson’s contract, made advances for construction purposes aggregating some $8,-236.68.

Another garnishment summons was served on appellee May 26, 1925, in the case of the Southern Surety Co. v. Johnson and other defendants, pending in the state district court at Denver. Appellee filed answer denying any indebtedness to Johnson, [67]*67admitting that it had a contract with him relating to the Cameron Pass project and certain property of his in its possession in the nature of collateral security delivered to it by Johnson, and asserted that it was advised that Johnson had assigned his interest, under the contract, to appellant to secure the indebtedness from him to appellant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hays v. Wilkinson
72 F.2d 201 (Tenth Circuit, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
31 F.2d 65, 1929 U.S. App. LEXIS 3391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zumsteg-v-tna-casualty-surety-co-ca8-1929.