Zufari v. Architecture Plus

914 S.W.2d 756, 323 Ark. 411, 1996 Ark. LEXIS 88
CourtSupreme Court of Arkansas
DecidedFebruary 12, 1996
Docket95-935
StatusPublished
Cited by20 cases

This text of 914 S.W.2d 756 (Zufari v. Architecture Plus) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zufari v. Architecture Plus, 914 S.W.2d 756, 323 Ark. 411, 1996 Ark. LEXIS 88 (Ark. 1996).

Opinion

Robert L. Brown, Justice.

Appellant Dr. M. Munir Zufari appeals a judgment barring his claim for breach of contract on limitations grounds. Zufari had sued appellee Architecture Plus and those persons who were partners during the time of the events in question — appellees Paul Hill, Michael G. Johnson, and Anthony Leraris. Zufari contends on appeal that the complaint was timely filed because the cause of action did not accrue until the project was substantially completed and, further, that the trial court erred in concluding that his request for arbitration was also barred by time. We disagree, and we affirm the judgment.

On August 3, 1993, Zufari filed his • complaint against Architecture Plus and the other appellees. He alleged that on or about September 1, 1987, he and Architecture Plus entered into a contract where Architecture Plus would design a medical clinic which would contain an ambulatory surgical center. Under the terms of the agreement, Architecture Plus was to design the facility according to Health Department regulations, prepare construction documents, and assist in the administration of the construction contract. The complaint asserted that after substantial completion of the facility, the Health Department refused to certify the project due to design defects. As a result, Zufari was forced to incur the additional expense of hiring another architectural firm to modify the design. The complaint further alleged that Zufari relied on Architecture Plus to make certain that the building complied with Health Department requirements. The complaint also contains a request for the trial court to order arbitration, as provided in the contract. In an amended complaint, Zufari sought damages in the amount of $114,742.38. Architecture Plus filed a counterclaim and alleged that Zufari owed it a balance of $9,874.95 for services rendered.

Architecture Plus and the appellee partners answered, raising the affirmative defense of statute of limitations, and moved to dismiss Zufari’s complaint on the same grounds. A hearing was held on the affirmative defense, and proof was presented. Paul Hill, who was previously a partner in Architecture Plus, testified that his firm was hired by Zufari to construct the medical clinic and that the first design was completed on November 23, 1987, and submitted to the Health Department for approval. In a return letter dated December 4, 1987, the Health Department informed Architecture Plus that in order to license the facility, the design would have to incorporate these changes:

1. Flip-flop O.R. [operating room] and vascular lab.
2. Provide a sterile barrier and a traffic route for surgery personnel to get from street clothes, to a gowning space, and into the surgery corridor.
3. Smooth washable ceiling and walls in the anesthetizing location and in the surgery corridor. Lay-in ceiling is not permitted in the O.R.
4. Provide for dumping a bed pan without traveling through other functional areas.
5. Tell us how and where you will incinerate excised tissue.
6. Label preop and postop space.
7. Make the O.R. 250 square feet in area.
8. Provide a smoke barrier.
When you get your plumbing approval, this office approves construction to begin. Note that this does not constitute city approval. To be licensed and certified as an ambulatory surgery center, you must satisfy our requirements.

Zufari was shown as having been sent a copy of the letter. The court permitted Hill to testify about the contents of the letter over hearsay objections by Zufari.

Hill testified that the absence of a sterile corridor is what prevented the facility from being licensed. He further testified that Zufari was aware of the Department’s rejection of the design in December 1987. Hill continued to communicate with the Health Department during the construction of the building. On December 22, 1987, Hill presented Zufari with a bill from Architecture Plus which showed that the design phase was 100% complete and that the construction documents and working drawings were 100% complete.

Hill also testified that on January 26, 1988, he submitted revised plans of the Zufari clinic to the Health Department in an effort to incorporate the required changes. These were the last plans that Hill prepared on the facility, although he made minor design changes later. Over Zufari’s objection, the trial court admitted a reply letter from Glenn Anderson, a construction engineer with the Division of Health Facility Services of the Health Department. In the letter dated February 4, 1988, Anderson wrote:

We did fail to point out that the type construction required does include steel door frames. Steel door frames with an integral steel stop across the top and down both sides are required.
I have noted on my sheet A2 of eight (8) that Hall-10 (the surgery corridor) is “off limits” to the public and that the gowning alcove is just north of door 21B with scrub sink just south of that door in the surgery corridor.
We must have Dr. Zufari’s written policy on how he will get proper incineration of all infectious, pathological and anatomical waste before we can recommend licensing of his facility. He must also give us a signed agreement with a hospital that will give him back-up service.

A notation at the bottom of this letter showed a copy going to Zufari.

On September 22, 1988, Hill wrote Zufari that the project was substantially completed. The medical clinic had opened for business on September 16, 1988. Hill testified that Zufari had expressed dissatisfaction with his work during a walk-through of the facility in December 1988. On February 15, 1989, Hill left Architecture Plus, and Hill’s work for Zufari ended.

Anthony Leraris, another partner with Architecture Plus, testified that Zufari’s contract was a standard form contract used by the firm and that it contained an arbitration provision. Leraris testified that he never received any request for arbitration from Zufari. On March 15, 1989, Leraris wrote the director of the Health Department, Dr. Joycelyn Elders, and complained that Glenn Anderson had approved the plans for the Zufari medical clinic by letter dated February 4, 1988, but that his successor, Tom Saunders, had later denied them. In the letter, Leraris blamed personnel turnover in the department for the denial of the license. Leraris testified that he did not become aware of any problems until after the medical clinic was substantially complete. As Leraris understood the problem, the addition of steel doors to the substerile surgery corridor would have met the Health Department’s demands. Zufari never consented to the addition of the steel doors, according to Leraris, and Hill never revised the plans to include steel doors.

The Health Department responded in a letter to Zufari dated March 30, 1989, regarding license denial:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C & R Construction Co., Inc. v. David Smith
2020 Ark. App. 105 (Court of Appeals of Arkansas, 2020)
Dye v. Diamante
2017 Ark. 42 (Supreme Court of Arkansas, 2017)
Farris v. Conger
2016 Ark. App. 230 (Court of Appeals of Arkansas, 2016)
Arkansas Realtors Ass'n v. Real Forms, LLC
2014 Ark. 385 (Supreme Court of Arkansas, 2014)
Bank of America, N.A. v. JB Hanna, LLC
766 F.3d 841 (Eighth Circuit, 2014)
Boellner v. Clinical Study Centers, LLC
2011 Ark. 83 (Supreme Court of Arkansas, 2011)
David A. Smith v. Union Carbide Corp.
222 F. App'x 536 (Eighth Circuit, 2007)
Phillips v. Union Pacific Railroad
201 S.W.3d 439 (Court of Appeals of Arkansas, 2005)
Slusser v. FARM SERVICE, INC.
198 S.W.3d 106 (Supreme Court of Arkansas, 2004)
Harness v. Curtis
192 S.W.3d 267 (Court of Appeals of Arkansas, 2004)
Opinion No.
Arkansas Attorney General Reports, 2004
Vereen v. Hargrove
96 S.W.3d 762 (Court of Appeals of Arkansas, 2003)
Entergy Services, Inc. v. Union Pacific Railroad
35 F. Supp. 2d 746 (D. Nebraska, 1999)
Dougan v. State
957 S.W.2d 182 (Supreme Court of Arkansas, 1997)
Weber v. State
933 S.W.2d 370 (Supreme Court of Arkansas, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
914 S.W.2d 756, 323 Ark. 411, 1996 Ark. LEXIS 88, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zufari-v-architecture-plus-ark-1996.