Zubair v. Entech Engineering P.C.

900 F. Supp. 2d 355, 2012 WL 4887738, 2012 U.S. Dist. LEXIS 144607
CourtDistrict Court, S.D. New York
DecidedOctober 1, 2012
DocketNo. 09 Civ. 7927(VM)
StatusPublished
Cited by13 cases

This text of 900 F. Supp. 2d 355 (Zubair v. Entech Engineering P.C.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zubair v. Entech Engineering P.C., 900 F. Supp. 2d 355, 2012 WL 4887738, 2012 U.S. Dist. LEXIS 144607 (S.D.N.Y. 2012).

Opinion

DECISION AND ORDER

VICTOR MARRERO, District Judge.

Plaintiff Ahmed Zubair (“Zubair”) brought this action against defendants En-Tech Engineering P.C. (“EnTech”) and Soudabey Bayat (“Bayat,” together, “Defendants”) alleging violations of the Fair Labor Standards Act, 29 U.S.C. § 201 et seq. (“FLSA”) and New York State Labor Law (“NYSLL”) by failing to pay him for certain overtime hours he worked while employed by EnTech as a chief/senior inspector. Zubair also brought several breach of contract claims that have since been dropped. On August 17, 2011, the Court granted summary judgment in favor of Zubair with respect to his FLSA and NYSLL overtime claims, while granting summary judgment in favor of Defendants with respect to Zubair’s NYSLL “spread of hours” claim. Zubair v. EnTech Eng’g P.C., et al., 808 F.Supp.2d 592 (S.D.N.Y.2011). Based upon the factual record at summary judgment, the Court could not determine, as a matter of law, whether Zubair should also be entitled to (1) liquidated damages with respect to his overtime claims, (2) reasonable attorneys’ fees, and (3) prejudgment interest. On September 6, 2012, the Court held a bench trial to adjudicate these three remaining issues.

The Court now sets forth its findings of fact and conclusions of law pursuant to Rule 52(a) of the Federal Rules of Civil Procedure. As explained below, the Court concludes that Defendants have not met their burden to show that their underpayment of wages, in violation of the FLSA and NYSLL, was in good faith and the result of an objectively reasonable belief that they were in compliance with the law. Therefore, the Court may not exercise its discretion to reduce or deny the liquidated damages Zubair is entitled to under the FLSA. The Court, however, concludes that additional liquidated damages under the NYSLL are not warranted in this case. Moreover, as the prevailing plaintiff in an FLSA and NYSLL suit, Zubair is entitled to reasonable attorneys’ fees and costs with respect to the overtime claims but not for the NYSLL “spread of hours” claim or for the contract claims Zubair dropped before the September 6, 2012 trial. Final[358]*358ly, Zubair’s award of liquidated damages under the FLSA precludes him from receiving prejudgment interest.

I. FINDINGS OF FACT1

Beginning in 2006, Zubair worked for EnTech as an inspector in different capacities on three New York State Department of Transportation (“NYSDOT”) projects: (1) the Robert Moses Causeway Project (“Robert Moses Project”); (2) the Bridge Deck Joint/Replacement Project (“Bridge/ Deck Project”); and (3) the Nassau Expressway and Interim Nassau Expressway Rehabilitation and Resurfacing Project (“Nassau Project”).

Defendant Bayat is the owner and president of Entech. At all relevant times, Bayat had control over the company’s employment practices and was responsible for Entech’s wage and hour practices.

From 2006 to 2007, Zubair worked on the Robert Moses Project as a senior inspector at a rate of pay of $43 per hour. For this project, he received overtime compensation when he worked more than 40 hours in a week. From May 2008 through September 2008, Zubair worked on the Bridge/Deck Project as a senior inspector at a rate of pay of $49 per hour. He did not receive the statutorily required overtime pay to which he was entitled for his work on this project. See Zubair, 808 F.Supp.2d at 600. Finally, from September 2008 through December 2008, Zubair worked on the Nassau Project as a chief inspector. His rate of pay for this project was $49 per hour, which was later reduced to a rate of $46 per hour, but he received no overtime compensation, in violation of the FLSA and NYSLL. See id.

II. CONCLUSIONS OF LAW

A. LIQUIDATED DAMAGES

1. FLSA Liquidated Damages

An employer who violates the FLSA’s minimum wage and overtime requirements is liable for any unpaid minimum wages or overtime compensation “and an additional equal amount as liquidated damages.”2 29 U.S.C. § 216(b). The Court may, in its discretion, reduce or deny liquidated damages “if the employer shows to the satisfaction of the court that the act or omission giving rise to such action was in good faith and that he had reasonable grounds for believing that his act or omission was not a violation of the [FLSA].” 29 U.S.C. § 260.

When seeking a reduction in liquidated damages, “[t]he employer bears the ‘difficult’ burden of establishing, by ‘plain and substantial’ evidence, its subjective good faith and objective reasonableness, as ‘double damages are the norm, single damages the exception.’ ” See Tlacoapa v. Carregal, 386 F.Supp.2d 362, 368 (S.D.N.Y.2005), citing Reich v. Southern New England Telecomms. Corp., 121 F.3d 58, 71 (2d Cir.1997); See also Walton v. United Consumers Club, Inc., 786 F.2d 303, 310 (7th Cir.1986) (Easterbrook, J.) (“Doubling [damages under FLSA] is not some disfavored ‘penalty.’ The [Portal-to-Portal Act] made doubling discretionary rather than mandatory, but it left a strong pre[359]*359sumption in favor of doubling, a presumption overcome only by the employer’s ‘good faith ... and reasonable grounds for believing that [the] act or omission was not a violation.’ ”).

Defendants argue that they acted in good faith and had reasonable grounds to conclude that Zubair was not entitled to an overtime premium for the work he performed on the Nassau Project because Defendants relied on the pay schedule in the NYSDOT Agreement for the Nassau Project (the “NYSDOT Nassau Agreement,” Def. Exh. A, at 43) to determine Zubair’s overtime compensation. Under the NYSDOT Nassau Agreement, a “chief inspector,” such as Zubair, is in overtime category “B,” which calls for straight-time, rather than time-and-a-half for overtime hours.

Defendants, however, do not explain how this contract provision from the Nassau Agreement justifies them failure to pay Zubair an overtime premium on the Bridge/Deck Project, for which Zubair was classified as a “senior inspector” rather than a “chief inspector.” While Defendants did not offer the NYSDOT contract for the Birdge/Deck Project into evidence, Bayat admitted that for that project, she did not pay Zubair according to the NYSDOT pay schedule because of a “special agreement” between her and Zubair. Assuming senior inspectors are in overtime category “C” under the Bridge/Deck NYSDOT contract, as they are under the NYSDOT Nassau Project Agreement, then according to the terms of the Bridge/Deck contract, Zubair should have been paid an overtime premium.

In this case, the Court need not determine whether Defendants’ reliance on a contract approved by a state agency establishes objective reasonableness under the FLSA liquidated damages test. Both parties cite to cases where courts have either accepted or rejected such reliance as reasonable grounds. Here, however, the Defendants’ selective

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
900 F. Supp. 2d 355, 2012 WL 4887738, 2012 U.S. Dist. LEXIS 144607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zubair-v-entech-engineering-pc-nysd-2012.