ZTE Corporation and ZTE USA, Inc. v. Universal Telephone Exchange, Inc.

CourtCourt of Appeals of Texas
DecidedNovember 19, 2018
Docket05-17-00781-CV
StatusPublished

This text of ZTE Corporation and ZTE USA, Inc. v. Universal Telephone Exchange, Inc. (ZTE Corporation and ZTE USA, Inc. v. Universal Telephone Exchange, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ZTE Corporation and ZTE USA, Inc. v. Universal Telephone Exchange, Inc., (Tex. Ct. App. 2018).

Opinion

REVERSE and RENDER; Opinion Filed November 19, 2018.

In The Court of Appeals Fifth District of Texas at Dallas No. 05-17-00781-CV

ZTE CORPORATION AND ZTE USA, INC., Appellant V. UNIVERSAL TELEPHONE EXCHANGE, INC., Appellee

On Appeal from the 44th Judicial District Court Dallas County, Texas Trial Court Cause No. DC-10-07052

MEMORANDUM OPINION Before Justices Myers, Evans, and Brown Opinion by Justice Evans This is an appeal from the trial court’s order vacating an arbitration award in favor of ZTE

Corporation and ZTE USA, Inc. (collectively ZTE) on claims brought against them by Universal

Telephone Exchange, Inc. (UTE). In five issues, ZTE generally asserts the trial court erred in

vacating the award and instead should have granted ZTE’s motion to confirm. We agree that none

of the grounds raised by UTE support vacation of the arbitration award. Accordingly, we reverse

the trial court’s order and render judgment confirming the arbitrator’s final award.

BACKGROUND

This dispute arises out of UTE’s efforts to obtain a contract to install and integrate a

comprehensive and modern telecommunications system throughout the country of Liberia after

the country’s civil war ended in 2003. The peace agreement ending the war established a transitional government that, among other things, sought to modernize Liberia’s

telecommunication services. The full record of the arbitration proceeding is not before us and it

was not before the trial court. The following facts are largely from the arbitrator’s final award and

undisputed facts in appellant’s brief.1

After the civil war ended, UTE began negotiating with Liberia’s national

telecommunications company, the Liberian Telecommunications Corporation (LTC), with respect

to the project.2 In furtherance of UTE’s efforts, UTE executed a non-disclosure agreement (NDA)

with ZTE USA to explore obtaining equipment and financing from ZTE USA and/or its Chinese

parent company, ZTE. The NDA contained an arbitration clause providing all disputes arising

from or in connection with the agreement “shall be submitted to the American Arbitration

Association in accordance with its rules in force at the time of application for arbitration.”

Although UTE and LTC initially reached an agreement in principle to proceed as a joint

venture, open competitive bids were eventually solicited for the project. Ultimately, UTE’s bid

was ranked first among the five qualified bids and LTC passed a resolution confirming UTE’s

winning bid.3 After conducting its own investigation, however, Liberia’s Contracts and

Monopolies Commission (CMC)4 recommended Liberia’s president not approve the LTC/UTE

contract because, among other things, UTE did not have the financial resources nor the operational

capacity to execute the project. The president rejected the contract and UTE then sought relief

from the Liberian legislature and the Liberian courts in an effort to obtain the necessary approval

1 In its brief, UTE acknowledges that the background facts and history recounted in the arbitration award is basically correct. Moreover, in civil cases, we accept as true the facts stated in appellant’s brief unless another party contradicts them. See TEX. R. APP. P. 38.1(g). 2 According to ZTE, LTC is the main telecommunications service provider in Liberia. 3 ZTE submitted its own competing bid for the project and was ranked fifth out of the five qualified bidders by the LTC. 4 This commission was also established by the peace agreement and was charged with reviewing all large public financial commitments. –2– to finalize its winning bid into a contract. However, UTE never consummated a final contract with

LTC. UTE sued ZTE, first in Liberia, and later in Dallas County district court, alleging ZTE’s

improper actions caused UTE to lose the UTE/LTC contract.

The Dallas lawsuit was filed in June 2010. UTE generally alleged ZTE interfered with its

business relationships in Liberia and had improperly used UTE’s confidential information. The

parties executed a Rule 11 agreement in which they agreed to arbitrate their dispute. Specifically,

the Rule 11 agreement also provided the case would be submitted to the “American Arbitration

Association to be arbitrated in accordance with the terms of the parties’ non-disclosure agreement

. . . and the rules in force at the time of the application for arbitration.”

Upon receipt of the arbitration demand, the AAA referred the matter to its international

division (IDCR) under the applicable International Dispute Resolution Procedures (IDR

Procedures). After an arbitrator was appointed, the matter proceeded and an arbitration hearing

was held. Before the arbitrator issued his final ruling, however, the parties agreed to his removal.

UTE then requested the IDCR appoint a three-arbitrator panel to re-hear the case. ZTE objected

and the IDCR rejected UTE’s request. Raul Gonzalez, former justice of the Texas Supreme Court

and UTE’s first choice for arbitrator, was appointed. After a two-week hearing, the arbitrator

issued his final award denying all of UTE’s claims against ZTE. Among other things, the arbitrator

concluded UTE’s causes of action were barred by limitations, that the project was a high risk

business venture, that UTE’s behavior was not the “but for cause” of UTE losing the LTC contract,

and adverse inferences against ZTE were not warranted because UTE failed to prove ZTE acted

with intent to conceal or intentionally destroyed evidence.

ZTE moved to confirm the award in the trial court, and UTE filed a cross-motion to vacate

the award, or alternatively, conduct additional discovery based on “new revelations” involving

ZTE’s execution of a federal plea agreement nineteen days after the arbitrator issued the final

–3– award in this case. The plea agreement involved charges of obstruction of justice, intentional

destruction and manipulation of evidence, and lying under oath to federal authorities with respect

to investigations of ZTE’s sale of telecommunications and security equipment to Iran and North

Korea in violation of sanctions imposed against those countries. UTE based its motion to vacate

on the following grounds: (1) the AAA impermissibly denied the parties’ agreed arbitrator

selection method; (2) the arbitrator refused to draw an adverse inference from, or refused to

consider, UTE’s evidence that ZTE officers, employees, and witnesses were unavailable,

concealed, or were uncooperative; (3) ZTE’s federal plea agreement established the arbitration

award in this case was obtained by corruption, fraud, or undue means, and (4) the arbitrator

exceeded his jurisdiction in ruling UTE’s claims were barred by limitations. Ultimately, the trial

court denied ZTE’s motion to confirm and granted UTE’s motion without stating a reason,

vacating the arbitration award and remanding the case to the AAA. ZTE filed this appeal.

ANALYSIS

A. Standard of Review

We review a trial court’s ruling confirming or vacating an arbitration award de novo based

on the entire record before us. See Cambridge Legacy Grp., Inc. v. Jain, 407 S.W.3d 443, 447

(Tex. App.—Dallas 2013, pet. denied). An arbitration award has the same force as a judgment of

a court of last resort and is presumed valid and entitled to great deference. Id. Thus, we indulge

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
East Texas Salt Water Disposal Co. v. Werline
307 S.W.3d 267 (Texas Supreme Court, 2010)
Hamm v. Millennium Income Fund, L.L.C.
178 S.W.3d 256 (Court of Appeals of Texas, 2005)
Ancor Holdings, LLC v. Peterson, Goldman & Villani, Inc.
294 S.W.3d 818 (Court of Appeals of Texas, 2009)
Dewayne Rogers Logging, Inc. v. Propac Industries, Ltd.
299 S.W.3d 374 (Court of Appeals of Texas, 2009)
Statewide Remodeling, Inc. v. Williams
244 S.W.3d 564 (Court of Appeals of Texas, 2008)
CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)
LAS PALMAS MEDICAL CENTER v. Moore
349 S.W.3d 57 (Court of Appeals of Texas, 2010)
Roric Gibbs v. Brooke Lomas
755 F.3d 529 (Seventh Circuit, 2014)
Cambridge Legacy Group, Inc. v. Ravi Jain
407 S.W.3d 443 (Court of Appeals of Texas, 2013)
Americo Life, Inc. v. Myer
440 S.W.3d 18 (Texas Supreme Court, 2014)
Hoskins v. Hoskins
497 S.W.3d 490 (Texas Supreme Court, 2016)
Odeon Capital Group LLC v. Ackerman
864 F.3d 191 (Second Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
ZTE Corporation and ZTE USA, Inc. v. Universal Telephone Exchange, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/zte-corporation-and-zte-usa-inc-v-universal-telephone-exchange-inc-texapp-2018.