ZP NO. 332, LLC v. HUFFMAN CONTRACTORS, INC., et al.

CourtDistrict Court, E.D. Virginia
DecidedNovember 4, 2025
Docket2:24-cv-00611
StatusUnknown

This text of ZP NO. 332, LLC v. HUFFMAN CONTRACTORS, INC., et al. (ZP NO. 332, LLC v. HUFFMAN CONTRACTORS, INC., et al.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ZP NO. 332, LLC v. HUFFMAN CONTRACTORS, INC., et al., (E.D. Va. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Norfolk Division

ZP NO. 332, LLC, Plaintiff, v. Case No. 2:24-cv-611 HUFFMAN CONTRACTORS, INC., et al., Defendants. OPINION & ORDER Plaintiff ZP No. 332, LLC hired Defendant Huffman Contractors, Inc. as the general contractor on a real estate development project. Huffman allegedly failed to complete the work adequately, and ZP eventually declared a default on the construction contract. That gave the parties’ surety, Travelers Casualty and Surety Company of America, several options under a performance bond. From those options, Travelers chose to take over Huffman’s contract, hire subcontractors, and finish the project. ZP claims Travelers did not fulfill the construction contract adequately after it took over. ZP sued both Huffman and Travelers for breach of contract. All three parties filed motions for partial summary judgment, and each of the defendants filed a motion to exclude one of ZP’s expert witnesses. This opinion addresses both of the defendants’motions for summary judgment(ECF Nos. 220, 230) and Huffman’s Daubert motion regarding Kevin Coyne (ECF No. 224). The Court will: (1) deny summary judgment that liquidated damages are ZP’s exclusive remedy against the defendants; (2) deny Huffman’s Daubert motion regarding Coyne;

(3) grant summary judgment in favor of the defendants on ZP’s lost value claim, because ZP’s proof depends on certain testimony of Robert Jones, which is inadmissible;

(4) deny summary judgment to Travelers regarding attorney fees, because there remains a genuine dispute as to whether the parties provided for attorney fees in the event ZP were to prove Travelers breached the performance bond independent of Huffman’s breach; and

(5) grant summary judgment that ZP’s recovery against Travelers is capped at the amount of the performance bond. The Court finds that such recovery is limited by the amount Travelers already spent to fulfill Huffman’s obligations under the construction contract but not by the amount of Travelers’s legal and expert costs.

I. BACKGROUND The parties do not dispute the following facts:1 1. ZP and Huffman executed a construction contract with a guaranteed maximum price of $31,272,000. ECF No. 52-4 § 5.2. 2. The construction contract contained the following provision regarding delays: In the event [Huffman] fails to complete the Work according to the dates set forth in Exhibit J . . . [Huffman]

1The Court includes only the facts required for its decisions on the motions addressed in this Opinion and Order. agrees that [ZP] shall be entitled to the liquidated damages set forth in Exhibit J (which may be assessed on a cumulative basis). [Huffman] acknowledges and agrees that the liquidated damages set forth in Exhibit J are a reasonable estimate of [ZP’s] damages in the event of a delay in the completion of the Work, and that such damages are difficult to calculate with certainty. ECF No. 52-4 § 4.2 (emphasis removed); see also id. at 129 (liquidated damages schedule). 3. Travelers issued a performance bond in the amount of $31,272,000. ECF No. 52-4 at 2–4 (performance bond). 4. ZP terminated the construction contract for cause and made a demand that Travelers perform under the bond. ECF No. 235 at 11 ¶ 11; ECF No. 261 at 10 ¶ 11. 5. After ZP’s demand, Travelers had several options according to the performance bond. ECF No. 235 at 11 ¶ 12; ECF No. 261 at 10 ¶ 12 (disputing only the number of options available); see ECF No. 62-2 at 3 § 5.1–5.4. 6. Travelers chose to proceed under § 5.2 of the performance bond, taking over Huffman’s duties on the construction contract and hiring a contractor to finish the project in Huffman’s place. ECF No. 235 at 12 ¶ 15; ECF No. 261 at 11 ¶ 15 (not disputing these facts). 7. The performance bond provides: If the Surety elects to act under Section 5.1, 5.2 or 5.3, then the responsibilities of the Surety to the Owner shall not be greater than those of the Contractor under the Construction Contract, and the responsibilities of the Owner to the Surety shall not be greater than those of the Owner under the Construction Contract. Subject to the commitment by the Owner to pay the Balance of the Contract Price, the Surety is obligated, without duplication, for

.12 the responsibilities of the Contractor for correction of defective work and completion of the Construction Contract; .2 additional legal, design professional and delay costs resulting from the Contractor’s Default, and resulting from the actions or failure to act of the Surety under Section 5; and

.3 liquidated damages, or if no liquidated damages are specified in the Construction Contract, actual damages caused by delayed performance or non-performance of the Contractor.

ECF No. 62-2 at 3 § 7. 8. As a result of Travelers’s election to proceed under § 5.2, ZP and Travelers executed a takeover agreement. ECF No. 235 at 12 ¶ 15; ECF No. 261 at 11 ¶ 15 (not disputing this fact); see ECF No. 62-5 (takeover agreement). 9. The takeover agreement provides that $31,272,000 is Travelers’s “single limit of liability.” ECF No. 235 at 13 ¶ 17; ECF No. 261 at 12 ¶ 17 (not disputing this fact); see ECF No. 62-5 §§ 11, 16, 21, 26. 10. The takeover agreement states: From time to time, the Surety agrees to expend or pay such of its own funds as may be necessary to pay for the completion of the Remaining Work, the correction or repair of the Remaining Work or work previously performed under the General

2 The performance bond uses this format—a period before the numeral—to designate subsections of § 7. This Opinion and Order adopts the parties’ format for referencing subsections in line. Contract, pay the Completing Contractor, reimburse or pay the Owner for any and all damages or settlements of any nature or description; provided, however, that the Surety’s obligations and liability under the Performance Bond, the General Contract and/or this Agreement, over and above the amount paid by the Owner and received by the Surety under this Agreement, shall, in no event, exceed, and it is hereby expressly limited to, the expenditure or payment of the penal amount of the Performance Bond ($31,272,000), which amount is the Surety’s single limit of liability for its completion obligations . . . for all three of these contracts . . . , as reduced by all amounts expended or paid by the Surety after the date of the Principal’s default, including, but not limited to, all expenditures or payments made to complete the Remaining Work, to correct or repair the Remaining Work or work previously performed under the General Contract, pay the Completing Contractor, pay third-parties to monitor and/or administer the Contract with the Completing Contractor on the Surety’s behalf, or to return, confirm or mobilize subcontractors, vendors or others to complete or correct or repair the Remaining Work or work previously performed under the General Contract, reimburse or pay the Owner for any and all damages or settlements of any nature or description, including the amount described in Exhibit B- 1 of this Agreement, and/or defend, adjust and satisfy any claims under the Performance Bond, General Contract, and/or this Agreement. For each dollar the Surety so expends or pays pursuant to the Performance Bond, General Contract, and/or this Agreement, the Surety shall receive a corresponding dollar-for-dollar reduction in the amount of its single limit of liability for all three of these contracts . . . , which is the penal amount of the Performance Bond ($31,272,000).

ECF No. 62-5 § 11. 11. Travelers paid subcontractors to complete work after the takeover agreement. ECF No. 235 at 14 ¶ 21; ECF No. 261 at 12 ¶ 21. 12. Among ZP’s claims in this case is lost property value in the amount of $29,209,829.59. ECF No. 235 at 14 ¶ 24; ECF No. 261 at 13 ¶ 24 (not disputing this fact). II. LEGAL STANDARDS A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gunning v. Cooley
281 U.S. 90 (Supreme Court, 1930)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Alyeska Pipeline Service Co. v. Wilderness Society
421 U.S. 240 (Supreme Court, 1975)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Creekmore v. Maryview Hospital
662 F.3d 686 (Fourth Circuit, 2011)
Cave Hill Corp. v. Hiers
570 S.E.2d 790 (Supreme Court of Virginia, 2002)
Tonti v. Akbari
553 S.E.2d 769 (Supreme Court of Virginia, 2001)
Gordonsville Energy, L.P. v. Virginia Electric & Power Co.
512 S.E.2d 811 (Supreme Court of Virginia, 1999)
O'BRIAN v. Langley School
507 S.E.2d 363 (Supreme Court of Virginia, 1998)
Westmoreland-Lg & E Partners v. Va. Elec.
486 S.E.2d 289 (Supreme Court of Virginia, 1997)
Long v. Abbruzzetti
487 S.E.2d 217 (Supreme Court of Virginia, 1997)
Beverly Enterprises-Virginia, Inc. v. Nichols
441 S.E.2d 1 (Supreme Court of Virginia, 1994)
Paul Business Systems, Inc. v. Canon U.S.A., Inc.
397 S.E.2d 804 (Supreme Court of Virginia, 1990)
Seaward International, Inc. v. Price Waterhouse
391 S.E.2d 283 (Supreme Court of Virginia, 1990)
Appalachian Power Co. v. John Stewart Walker, Inc.
201 S.E.2d 758 (Supreme Court of Virginia, 1974)
Hiss v. Friedberg
112 S.E.2d 871 (Supreme Court of Virginia, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
ZP NO. 332, LLC v. HUFFMAN CONTRACTORS, INC., et al., Counsel Stack Legal Research, https://law.counselstack.com/opinion/zp-no-332-llc-v-huffman-contractors-inc-et-al-vaed-2025.