Zeraschi & Son, Inc. v. R.W. Granger & Sons, Inc.

13 Mass. L. Rptr. 187
CourtMassachusetts Superior Court
DecidedMay 30, 2001
DocketNo. CA000473
StatusPublished

This text of 13 Mass. L. Rptr. 187 (Zeraschi & Son, Inc. v. R.W. Granger & Sons, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zeraschi & Son, Inc. v. R.W. Granger & Sons, Inc., 13 Mass. L. Rptr. 187 (Mass. Ct. App. 2001).

Opinion

Brassard, J.

The plaintiff in this action, a masonry subcontractor, alleges that the defendant, the general contractor of a construction project, breached the terms of the subcontract when it refused to pay for work completed but not included in the contract’s masonry specifications. The plaintiff has moved for summary judgment contending that it is entitled to judgment as a matter of law because other specifications explicitly require roofing subcontractors to perform the work in question, and any ambiguities in the specifications must be resolved against the defendant. The defendant has filed a cross-motion for summary judgment against the third-party defendant, the project owner, seeking indemnification and attorneys fees. The third-party defendant argues that summary judgment must be denied as to both motions because material issues of fact remain in dispute. For the following reasons, the plaintiffs motion for summary judgment is DENIED and the defendant’s cross-motion summary judgment is DENIED.

BACKGROUND

At or around January 1997, the plaintiff, Zeraschi and Son, Inc. ("Zeraschi”), a masonry subcontractor, filed a masonry subbid pursuant to G.L.c. 149, §44F(2) in the construction of the New Chelsea Court House (“Project”). The defendant, R.W. Granger & Sons Inc. (“Granger”),2 was subsequently awarded the general contract for the Project, and entered into a prime contract with the third-party defendant, the Commonwealth of Massachusetts Division of Capital Planning and Operations (“DCPO’).3

On February 26, 1997, after being awarded the masonry subcontract, Zeraschi entered into a subcontract with Granger. The subcontract states in pertinent part,

The Subcontractor agrees to furnish all labor and materials required for the completion of all work specified in Section No. 04101 of the specifications for Masonry and the plans referred to therein and addenda No 1, 2, 3 and 4 for the [Project] as prepared by Schwartz/Silver Architects, Inc. . . .

Part 2 of the Masonry specifications, §04101, entitled “Products,” .states in part:

2.12 EMBEDDED FLASHING MATERIALS:
1. Type 1: Fabricate from 16 oz. (0.0216 inch) copper. Fabricate through-wall metal flashings embedded in masonry with ribs formed in dovetail pattern at 3-inch intervals along length of flashing to provide a three-way integral mortar bond and weep-hole drainage.
1. Fabricate metal expansion joint strips from sheet metal indicated above, formed to shape indicated.
Type 2: Rubberized Asphalt Sheet Flashing: Composite flashing product consisting of 32-mil-thick pliable and highly adhesive rubberized asphalt compound bonded completely and integrally to 8 mil-thick, high-density, cross-laminated polyethylene film to produce an overall thickness of 40 mils.
[188]*1881. Extent: Use flashing type 2 for fully concealed applications to the greatest extent possible, but not where exposed to view or sunlight, not where joint sealant is in contract, not where flashing type 2 must span over an opening or cavity, and not where the self-adhesive properties make the flashing impossible to install. In these instances, use flashing type 1.

When a question arose at a job meeting on April 30, 1998, as to which subcontractor was responsible for completing work known as “lead coated copper flashing,” Granger contacted Schwartz/Silver (“architects”), the architects of the Project. By letter dated May 5, 1998, the architects responded that “flashings are indicated on the drawings without noted indications of subcontract ownership, although materials are sometimes noted.” The letter further explained:

The ownership of the metal flashing is indicated in the contract documents by language in the specification sections. 07601 includes metal flashings and counter flashings, except throughwalls masonry flashings are masonry work in 04101; 04101 includes throughwall flashings in masonry assemblies. “Throughwall masonry flashings” and “throughwall flashings in masonry assemblies" mean flashings that are embedded or sandwiched in masonry construct; that is, the flashing goes through the masonry assembly. In general, this means that the mason owns horizontal head and sill flashings at window and curtainwall openings and other locations where the flashing goes through the masonry; flashing at other locations (such as curtainwall opening heads and jambs) belong to the roofer.

Zeraschi completed all the original masonry subcontract work. Thereafter, Zeraschi was ordered by DCPO, through Granger, to perform work requiring lead coated copper flashing. Zeraschi, who believed that such work was the responsibility of roofers and flashers, did not include the cost to furnish or install lead coated copper flashing in its bid. Consequently, Zeraschi performed this work under protest and made a claim for costs totaling approximately $40,412.10 to Granger.

Granger submitted Zeraschi’s request for additional costs to DCPO, who subsequently denied Zeraschi’s claim. In so doing, DCPO consulted the architects to again clarify whether the masons or roofers and flashers were responsible for lead coated copper flashing. By letter dated January 15, 1999, the architect recommended that Zeraschi’s request be rejected because the disputed lead coated copper flashing work was “part of the contract work.” On February 9, 1999, the architect provided an additional letter in support of its recommendation. In pertinent part, the letter stated,

[T]he relevant distinction is between what is a throughwall flashing, or throughwall masonry flashing (there is no meaningful difference between these two expressions for the details on this set of construction documents) and other metal flashings; the former will belong to Section 04101, and the latter to 07601 . . . The assignment of a detail to 070601 means that it is not a throughwall flashing; the assignment of it to 04101 means that it is throughwall flashing.

On March 19, 1999, the DCPO adopted the architect’s recommendation, rejected Zeraschi’s claim, and directed Zeraschi to “furnish and install lead coated copper flashing by the masonry contractor.” Zeraschi appealed the architect’s decision and was ultimately denied costs for the flashing.

On February 3, 2000, Zeraschi filed the present action alleging breach of contract in violation of G.L.c. 149, §29 (Count I), and quantum meruit (Count II). On March 3, 2000, Granger and Guaranty filed a third-party complaint against the DCPO seeking indemnification (Count I), and attorneys fees (Count II).

DISCUSSION

Summary judgment is appropriate when there are no material facts in dispute and when the moving party is entitled to judgment as a matter of law. Mass.R.Civ.P. 56. The moving party bears the burden of affirmatively demonstrating the absence of a triable factual issue and of showing that it is entitled to judgment as a matter of law. Pederson v. Time Inc., 404 Mass. 14, 16-17 (1989). Once the moving party demonstrates the absence of a triable issue, the party opposing the motion must respond with evidence of specific facts establishing the existence of a material factual dispute. Id. at 17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hardware Specialties, Inc. v. Mishara Construction Co.
311 N.E.2d 564 (Massachusetts Appeals Court, 1974)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
J. A. Sullivan Corp. v. Commonwealth
494 N.E.2d 374 (Massachusetts Supreme Judicial Court, 1986)
John F. Miller Co. v. George Fichera Construction Corp.
388 N.E.2d 1201 (Massachusetts Appeals Court, 1979)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
13 Mass. L. Rptr. 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zeraschi-son-inc-v-rw-granger-sons-inc-masssuperct-2001.