Zelvin v. JEM Builders, Inc.

942 A.2d 455, 106 Conn. App. 401, 2008 Conn. App. LEXIS 98
CourtConnecticut Appellate Court
DecidedMarch 18, 2008
DocketAC 26422
StatusPublished
Cited by9 cases

This text of 942 A.2d 455 (Zelvin v. JEM Builders, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zelvin v. JEM Builders, Inc., 942 A.2d 455, 106 Conn. App. 401, 2008 Conn. App. LEXIS 98 (Colo. Ct. App. 2008).

Opinion

Opinion

FLYNN, C. J.

Steven L. Zelvin and Kenneth C. Zelvin appeal from the judgments of the trial court denying their application to vacate or to modify an arbitration award and granting the application to confirm the award filed by JEM Builders, Inc. (JEM Builders). On appeal, the Zelvins claim that the court improperly confirmed the award because the submission to the arbitration panel was restricted and the arbitration panel exceeded the scope of its authority. We affirm the judgments of the trial court.

*403 The following facts and procedural history are relevant to the Zelvins’ appeal. On March 27, 2000, the Zelvins and JEM Builders entered into a contract in which JEM Builders agreed to purchase lot 6, located in the Mystic Shores subdivision of Groton. The contract contained a broad arbitration provision providing in relevant part that “[t]he Buyer and Seller agree any controversy or claim arising from or relating to this Agreement or the breach thereof be settled by binding arbitration administered by the American Arbitration Association (‘AAA’) pursuant to their Rules for the Real Estate Industry. Either Buyer or Seller may initiate a request for such arbitration with the AAA office . . . .”

A dispute later arose, and, as a result, JEM Builders, as the initiating party, filed a demand for arbitration on March 17, 2003, in accordance with the arbitration clause in the contract. 1 In its description of the nature *404 of the dispute, JEM Builders asserted that the Zelvins had breached the contract by failing to convey lot 6. In the demand for arbitration, JEM Builders also sought specific performance, “[d]amages for lost profit on the new home construction customer that was lost,” punitive damages, attorney’s fees and “[a]ny other remedies deemed necessary by the Arbitration Board.” In response, the Zelvins filed an answer, in which they denied that they had breached the contract and stated that JEM Builders was not entitled to any relief. Additionally, the Zelvins filed their own demand, which they styled as a counterclaim, asserting that JEM Builders had defaulted on the contract, and they requested liquidated damages, attorney’s fees and costs, and “[s]uch other relief as the panel deems just and proper.” Thereafter, on May 9, 2003, JEM Builders filed a revised demand, providing more details about the dispute and seeking specific performance, money damages, punitive damages, attorney’s fees and costs and “[s]uch other remedies as the Arbitration panel may deem necessary.” The Zelvins subsequently filed a supplemental answer.

Following several days of hearings in October, 2003, and in January, 2004, a panel of three arbitrators issued an award on April 29, 2004, concluding, inter alia, that the Zelvins had breached the contract regarding lot 6 by “violating the covenant of good faith and fair dealing that is implicit in every contract.” 2 As part of the arbitration award, the panel ordered the following relief: “[JEM Builders] is awarded [$80,000] as damages resulting from [the Zelvins’] breach of the contract. There was evidence sufficient to support a finding of damages relating to the appreciation of value of Lot No. 6 . . . .”

*405 The Zelvins then filed with the court an application to vacate or, in the alternative, to modify the award pursuant to General Statutes §§ 52-418 3 and 52-419. 4 JEM Builders filed an application to confirm the award. See General Statutes § 52-417. 5 The applications were consolidated, and a hearing was held on October 7, 2004. Thereafter, the court denied the Zelvins’ application to vacate or to modify the award and granted JEM Builders’ application to confirm the award. This appeal followed.

*406 On appeal, the Zelvins challenge the court’s conclusions that the submission was unrestricted and that the arbitration panel acted within its authority in awarding JEM Builders damages in the amount of $80,000. Specifically, the Zelvins contend that the panel exceeded its authority by failing to conform the award to the submission and by manifestly disregarding the law.

Before addressing these claims, we set forth the well established principles that guide our analysis. “Judicial review of arbitral decisions is narrowly confined. . . . When the parties agree to arbitration and establish the authority of the arbitrator through the terms of their submission, the extent of our judicial review of the award is delineated by the scope of the parties’ agreement. . . . When the scope of the submission is unrestricted, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission. . . . Because we favor arbitration as a means of settling private disputes, we undertake judicial review of arbitration awards in a manner designed to minimize interference with an efficient and economical system of alternative dispute resolution. . . .

“Where the submission does not otherwise state, the arbitrators are empowered to decide factual and legal questions and an award cannot be vacated on the grounds that . . . the interpretation of the agreement by the arbitrators was erroneous. Courts will not review the evidence nor, where the submission is unrestricted, will they review the arbitrators’ decision of the legal questions involved. ... In other words, [u]nder an unrestricted submission, the arbitrators’ decision is considered final and binding; thus the courts will not review the evidence considered by the arbitrators nor will they review the award for errors of law or fact. . . .

“The significance ... of a determination that an arbitration submission was unrestricted or restricted is *407 not to determine what the arbitrators are obligated to do, but to determine the scope of judicial review of what they have done. Put another way, the submission tells the arbitrators what they are obligated to decide. The determination by a court of whether the submission was restricted or unrestricted tells the court what its scope of review is regarding the arbitrators’ decision.” (Internal quotation marks omitted.) Harty v. Cantor Fitzgerald & Co., 275 Conn. 72, 80-81, 881 A.2d 139 (2005). With these principles in mind, we turn to the Zelvins’ claims on appeal.

I

The Zelvins first claim that the court improperly concluded that the submission was unrestricted. We disagree.

“In determining whether a submission is unrestricted, we look to the authority of the arbitrator.” (Internal quotation marks omitted.) Exley v. Connecticut Yankee Greyhound Racing, Inc., 59 Conn. App. 224, 229, 755 A. 2d 990, cert. denied, 254 Conn. 939, 761 A. 2d 760 (2000).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evexia Holdings, Inc. v. Geurts
Connecticut Appellate Court, 2025
Lemma v. York & Chapel, Corp.
Connecticut Appellate Court, 2021
Girolametti v. Rizzo Corp.
Connecticut Appellate Court, 2014
Bumbolow v. Foreman
Connecticut Appellate Court, 2014
Design Tech, LLC v. Moriniere
76 A.3d 712 (Connecticut Appellate Court, 2013)
Town of Marlborough v. AFSCME, Council 4, Local 818-052
23 A.3d 798 (Connecticut Appellate Court, 2011)
Porter v. Morrill
949 A.2d 526 (Connecticut Appellate Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
942 A.2d 455, 106 Conn. App. 401, 2008 Conn. App. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zelvin-v-jem-builders-inc-connappct-2008.