Zedot Constr. v. Red Sullivan's Air Serv.

947 So. 2d 396, 2006 WL 1793754
CourtSupreme Court of Alabama
DecidedJune 30, 2006
Docket1041944
StatusPublished
Cited by9 cases

This text of 947 So. 2d 396 (Zedot Constr. v. Red Sullivan's Air Serv.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zedot Constr. v. Red Sullivan's Air Serv., 947 So. 2d 396, 2006 WL 1793754 (Ala. 2006).

Opinion

Zedot Construction, Inc., appeals from the Jefferson Circuit Court's denial of Zedot's motion to compel arbitration.

I. Facts and Procedural History
Zedot, acting as general contractor on a construction project in Jefferson County, entered into a subcontract with Red Sullivan's Conditioned Air Services, Inc. ("CAS"), under which CAS was to perform certain work on the project. The subcontract contained an arbitration clause.

Because, according to Zedot, CAS's work on the project was deficient, Zedot terminated CAS and hired a new subcontractor. On January 20, 2005, CAS sued Zedot in the Jefferson Circuit Court, alleging breach of contract, open account, unjust enrichment, and a violation of the Alabama Prompt Pay Act.

On February 24, 2005, Zedot filed a motion to dismiss, which made no mention of the arbitration clause. Rather, Zedot's motion argued that CAS's claim was barred by the two-year statute of limitations set out in § 6-5-221, Ala. Code 1975, for civil actions against builders. "Builders" are defined in § 6-5-220, Ala. Code 1975, as "[a]ny individual, partnership, firm, or corporation that constructed, or performed or managed the construction of, an improvement, or any portion thereof, on or to real estate, and at the time of the construction waslicensed as a general contractor in the State of Alabama." (Emphasis added.) In support of its contention that §6-5-221 applied to CAS's claims, Zedot attached to its motion to dismiss the affidavit of Joseph Rogers, the executive secretary of the Alabama Licensing Board for General Contractors. Rogers stated in his affidavit that Zedot is a licensed general contractor in Alabama. Because Rogers's affidavit was not excluded by the trial court, Zedot's motion to dismiss was converted to a motion for a summary judgment. See Rule 12(b), Ala. R. Civ. P. ("If, on a motion . . . to dismiss for failure of the pleading to state a claim upon which relief can be granted, matters outside the pleading are presented to and not excluded by the court, the motion shall be treated as one for summary judgment. . . .").

On March 4, CAS filed its opposition to Zedot's motion for a summary judgment. On April 18, without a hearing, the trial court denied Zedot's motion and ordered Zedot to answer CAS's complaint within 30 days. On May 18, Zedot filed an answer to CAS's complaint and a counterclaim alleging breach of contract. In its answer, Zedot pleaded arbitration as an affirmative defense and stated that it asserted its counterclaim only to preserve that claim. On June 16, CAS filed its answer to Zedot's counterclaim. On July 20, Zedot filed a motion to compel arbitration. CAS opposed Zedot's motion to compel arbitration by arguing that Zedot had waived its right to arbitrate by participating in the litigation process. The trial court agreed and denied Zedot's motion. Zedot appealed.

II. Standard of Review
"[T]he standard of review of a trial court's ruling on a motion to compel arbitration at the instance of either party is ade novo determination of whether the trial judge erred on a factual or legal issue to the substantial prejudice of the party seeking review." Ex parte Roberson,749 So.2d 441, 446 (Ala. 1999) (emphasis omitted).

III. Analysis
"In order to show waiver by litigation-related conduct, the party opposing *Page 399 arbitration must demonstrate that the movant has substantially invoked the litigation process and thereby the opposing party would be substantially prejudiced if the case were submitted to arbitration. Companion Life Ins. Co. v. Whitesell Mfg.,Inc., 670 So.2d 897, 899 (Ala. 1995). In Moses H. ConeMemorial Hospital [v. Mercury Construction Corp.,460 U.S. 1 (1983)], the United States Supreme Court recognized a strong federal policy favoring arbitration:

"`The [Federal] Arbitration Act establishes that, as a matter of federal law, any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration, whether the problem at hand is the construction of the contract language itself or an allegation of waiver, delay, or a like defense to arbitrability.'

"460 U.S. at 24-25 (emphasis added; footnote omitted). In order to establish waiver, the party opposing arbitration bears a heavy burden, and waiver is not lightly to be inferred. Thompson v. Skipper Real Estate Co., 729 So.2d 287, 292 (Ala. 1999), and cases cited therein."

Ocwen Loan Servicing, LLC v. Washington, 939 So.2d 6,14 (Ala. 2006). "[A] presumption exists against a finding that a party has waived the right to compel arbitration." ConsecoFin. Corp.-Alabama v. Salter, 846 So.2d 1077, 1080 (Ala. 2002).

Zedot argues that the trial court erred in denying its motion to compel arbitration because, it says, Zedot had not substantially invoked the litigation process and because CAS will not be substantially prejudiced if it is required to arbitrate its claims against Zedot. Zedot points out that it pleaded arbitration as an affirmative defense in its answer to CAS's complaint. Zedot contends that its filing of a motion to dismiss asserting the defense of the statute of limitations, which was treated as a motion for a summary judgment and which was the only pleading Zedot filed before it asserted the affirmative defense of arbitration in its answer, does not constitute a substantial invocation of the litigation process. We agree.

"[T]he mere filing of a pleading does not constitute a waiver of the right to compel arbitration." Salter,846 So.2d at 1081. "`The mere serving of an answer and the making of amotion to dismiss a complaint does not constitute a waiver'" of the right to arbitration. Ex parte MerrillLynch, Pierce, Fenner Smith, Inc., 494 So.2d 1, 3 (Ala. 1986) (emphasis added). See, also, Sharif v. WellnessInt'l Network, Ltd., 376 F.3d 720, 726-27 (7th Cir.2004) ("[I]t is well-established that a party does not waive its right to arbitrate merely by filing a motion to dismiss. SeeCreative Solutions Group, Inc. v. Pentzer Corp.,252 F.3d 28, 33 (1st Cir.2001); Williams v. Cigna Fin.Advisors, Inc., 56 F.3d 656, 661-62 (5th Cir.1995);Rush v. Oppenheimer Co., 779 F.2d 885, 888 (2nd Cir.1985); Lake Communications, Inc. v. ICC Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norvell v. Parkhurst
261 So. 3d 300 (Supreme Court of Alabama, 2017)
African Methodist Episcopal Church, Inc. v. Smith
217 So. 3d 816 (Supreme Court of Alabama, 2016)
O'Neal v. Bama Exterminating Co.
147 So. 3d 403 (Supreme Court of Alabama, 2013)
Todd v. Discover Bank
115 So. 3d 167 (Court of Civil Appeals of Alabama, 2012)
Paragon Ltd., Inc. v. Boles
987 So. 2d 561 (Supreme Court of Alabama, 2007)
SouthTrust Bank v. Bowen
959 So. 2d 624 (Supreme Court of Alabama, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
947 So. 2d 396, 2006 WL 1793754, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zedot-constr-v-red-sullivans-air-serv-ala-2006.