York v. Tyler

21 D.C. 265
CourtDistrict of Columbia Court of Appeals
DecidedNovember 21, 1892
DocketNos. 9,104, 9,105, 9,106
StatusPublished

This text of 21 D.C. 265 (York v. Tyler) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
York v. Tyler, 21 D.C. 265 (D.C. 1892).

Opinion

The Chief Justice

delivered the opinion of the Court:

The bill in the case of York against Tyler seeks to em force a mechanics’ lien, and alleges that on the 18th of August, 1883, the plaintiff entered into a contract with the defendants, Tyler & Rutherford, described in the said contract as agents, to build and construct seven houses upon seven sub-lots in square 115, in this city, for the sum of $30,800; that the plaintiff proceeded to perform the contract on his-part, and while so performing and carrying out the same, on the 8th of October, 1883, the defendants, Tyler & Rutherford, took possession of the buildings so being erected, dispossessed the plaintiff and refused to allow him to proceed with his contract, and thereupon proceeded to complete the work themselves; that at the latter date materials had been furnished and labor performed by the plaintiff upon all of the said houses, and some payments had been made by the defendants, Tyler & Rutherford, on account of such work and materials, leaving a balance due to the plaintiff; that at the date of the contract, four of these lots, 69 to 72, inclusive, were owned by the defendant Tyler; another lot, 73, by Emma J. Brewer, and two others, 74 and 75, by George L. Knowles and Joseph A. Jones, as tenants in common; that on the 24th of November, 1883, plaintiff filed his notice of lien on the first four mentioned lots and premises in the name of Tyler & Rutherford, as owners, and subsequently on the 12th' of July, 1884, filed another such notice of lien against the said lots in the name of Richard W. Tyler as owner. There are other averments in the bill which are not material to the stating of this account. The original answer of the defendants, Tyler & Rutherford, admits the making of the contract and partial execution of the work; also the taking possession by them on the 8th of October, and their refusal to allow the plaintiff to proceed, and that they finished the said work. This answer also assigns as [267]*267reasons for the said acts, that the plaintiff had failed to comply with the terms of the contract and requirements of the plans and specifications. The defendants also state that the necessary cost of completing the buildings exceeded the original contract price. Exceptions to this answer were filed and sustained by the court, and thereupon the said defendants filed an amended answer, in which they aver that the plaintiff did not comply with his said contract, in the following among other particulars: That the workmanship by the plaintiff on the said buildings was not true, perfect, or thoroughly workmanlike and according to the plans and specifications as required by his contract; that the materials were not good, proper or sufficient, or of the best description as required by the said contract, and that neither workmanship nor materials were satisfactory to the architect as required by the said contract; that the plaintiff delayed entering upon the said work for several weeks after the execution of the contract, and then failed to give it proper personal superintendence, or to cause the work to be done in the manner required by the contract. It is further specified that neither the bricks nor mortar were o.f the description required by the specifications, that the walls were not constructed in accordance therewith, nor were the joists or bridging of the description required, and that the workmanship and materials were in other ways deficient and defective. It is also averred in the answer that by reason of the plaintiff’s determination not to comply with the contract, and the slow progress of the work and the confusion attending the same, it was apparent that the houses would not be completed within the period provided for in said contract; and that the plaintiff had suspended work for want of means to carry it on.

The plaintiff brought similar suits to enforce similar liens in causes Nos. 9105 and 9106. Proofs were taken, and by stipulation are to be used in the three causes. A copy of the contract of August 18, 1885, is filed as an exhibit to the bill. The agreement was made between the plaintiff, as [268]*268builder, of the one part, and Richard W. Tyler and Robert G. Rutherford, agents,' of the other part. The plaintiff agreed that on or before the ist of February, 1884, he would well and sufficiently erect, finish and deliver, in a true, perfect and thoroughly workmanlike manner, seven three-story and basement brick dwelling-houses as per plans and specifications to the contract attached and signed by the parties, and dated the same as the agreement, on ground situated in this city, and agreeably to the plans, drawings and specifications aforesaid, prepared for the said houses by John G. Myers, architect, to the satisfaction and under the direction and personal supervision of the said Myers, architect, and to find and provide such good, proper and sufficient materials of all kinds whatsoever, as should be proper and sufficient for the completing and finishing of the said houses within the time aforesaid, for the sum of $30,800. The parties of the second part agreed, in consideration of the execution of the agreement by the party of the first part, to pay to him the said sum in certain specified instalments or payments, as the work reached certain points in its progress; the first payment, $2,000, to be made when the basement walls were up to the first tier of floor joists, leveled up and bridged. The contract further provides that in each case of such payments a certificate should be obtained from the architect. The contract ’ contains a number of other provisions, of which we may refer here to the fourth, ninth and tenth. The fourth provides as follows: “Should the contractor, at any time during the progress of said work, become bankrupt, refuse or neglect to supply a sufficiency of material or workmen, or cause any unreasonable neglect or suspension of work, or fail or refuse to follow the drawings and specifications, or comply with any of the articles of agreement, the proprietors (parties of the second part) or their agent, shall have the right and power to enter upon and take possession of the premises, and may at once terminate the contract, whereupon all claims of the contractor, his heirs, executors, administrators or assigns, shall cease and [269]*269the proprietors may provide materials and workmen sufficient to complete the said works, after giving forty-eight hours’ notice in writing, directed and delivered to the contractor, . . . and the expense of such notice, and the completing of the works will be deducted from the amount of contract or any part of it due or to become due to the contractor,” etc. The ninth clause provides, among other things, that all work and materials as delivered on the premises to form part of the works are to be considered the property of the proprietors, and are not to be removed without their consent. The tenth clause provides that if the contractor fails to finish his work at or before the time agreed upon he should pay or allow the proprietors, by way of liquidated damages, the sum of $35 per day for each day the work remained incomplete or undelivered.

The specifications in general terms required that all material should be of the best description; that the contractor should furnish all material and do all necessary work to complete the buildings, whether specified or not, excepting certain things which were specifically omitted; no changes were to be made without previous agreement, and that the plans and drawings should form a part of both contract and specifications.

Replication was made to the answers of defendants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harding v. Wheaton
24 U.S. 103 (Supreme Court, 1826)
Story v. Livingston
38 U.S. 359 (Supreme Court, 1839)
Tilghman v. Proctor
125 U.S. 136 (Supreme Court, 1888)
Kimberly v. Arms
129 U.S. 512 (Supreme Court, 1889)
Crawford v. Neal
144 U.S. 585 (Supreme Court, 1892)
Furrer v. Ferris
145 U.S. 132 (Supreme Court, 1892)
Evans v. State Bank
141 U.S. 107 (Supreme Court, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
21 D.C. 265, Counsel Stack Legal Research, https://law.counselstack.com/opinion/york-v-tyler-dc-1892.