Yaffe v. Scarlett Place Residential Condominium, Inc.

45 A.3d 844, 205 Md. App. 429, 2012 WL 1998066, 2012 Md. App. LEXIS 64
Court of Special Appeals of Maryland·Decided June 5, 2012·No. 2775, September Term, 2010·Published·Cited by 11 cases

Opinion

*435 EYLER, JAMES R„ J.

On May 5, 2009, Peter N. Yaffe, individually and as successor in interest to and assignee of Budreaux & Sammy, LLC (“Budreaux”) and Columbus Piazza, LLC (“Columbus Piazza”) (collectively referred to as “appellants”), filed the instant action in the Circuit Court for Baltimore City against Scarlett Place Residential Condominium, Inc. (“Scarlett Place”), Karl A. Knutsen, and Knutsen Engineering Group, LLC (“KEG”) (collectively referred to as “appellees”). Appellants sought damages, specific performance, and injunctive relief stemming from alleged reoccurring water leaks and moisture infiltration in several condominiums owned by appellants located at Scarlett Place in Baltimore City. The circuit court conducted a bench trial and, at the conclusion of appellants’ case, granted appellees’ motions for judgment. This timely appeal followed. For the reasons set forth below, we shall affirm. 1

Factual and Procedural Background

Budreaux was formed in 2002 by Mr. Yaffe and his father, with Mr. Yaffe possessing a 99 percent ownership interest in the company. He acquired the remaining 1 percent interest in 2007. In 2008 and 2004, Budreaux purchased Scarlett Place Condominium units 612 and 613. According to Mr. Yaffe, he intended to combine units 612 and 613 and live in them. In 2009, Budreaux assigned all of its rights in units 612 and 613 to Mr. Yaffe. Mr. Yaffe is also the sole member of Columbus Piazza, which purchased unit 1011 in 2007.

In 2004 and 2005, there was considerable water infiltration into the Scarlett Place units, including appellants’ units. In 2005, Budreaux filed suit against Scarlett Place in circuit court. In October 2006, the parties entered into a settlement agreement in which Scarlett Place agreed to pay damages and to make permanent repairs. Scarlett Place also agreed that it would deliver to Budreaux, prior to February 1, 2007, a *436 certification from a registered professional engineer that the water leak and moisture penetration repairs had been completed or, if not, pay $6,000 per month until delivered.

Scarlett Place had been experiencing water infiltration problems with respect to many units for many years. As a result, on January 18, 2006, Scarlett Place entered into a contract with KEG pursuant to which KEG agreed to make repairs to the terrace decks and walls of the entire building (“the AIA contract”). Shortly after the October 2006 settlement agreement, KEG agreed to investigate leaks, including in units 612 and 613, and to create a design to prevent water infiltrations in those units.

With respect to the October 2006 settlement, Scarlett Place did not deliver a timely certification. Scarlett Place delivered a certification dated March 30, 2007, but Mr. Yaffe did not accept it. According to Mr. Yaffe, leaks continued.

In April 2007, Budreaux filed a second suit in circuit court against Scarlett Place. On June 29, 2007, the parties entered into a second settlement agreement. Scarlett Place paid Budreaux money, agreed to install terrace doors, and delivered a certification dated June 28, 2007, as described in the October 2006 settlement agreement.

In the fall of 2007, Columbus Piazza purchased unit 1011. In late 2007 and thereafter, Mr. Yaffe complained about leaks in all three units.

In February 2008, Budreaux and Columbus Piazza filed a third suit in circuit court against Scarlett Place. Throughout this period of time, appellants were performing some renovation work on their units but also took the position that they could not move forward until after the leaks were stopped.

On July 21, 2008, the parties entered into a third settlement agreement. Scarlett Place agreed to pay money and conduct more repairs. Scarlett Place also delivered a certification dated July 21, 2008, as described in the October 2006 settlement agreement.

*437 More leaks and repair work followed. By January 2009, Scarlett Place took the position that repairs had been completed. In May 2009, appellants filed this suit against Scarlett Place and the Knutsen entities.

The fifth amended complaint is the operative complaint. Most counts of the complaint are relevant to this appeal. In count 1, appellants requested the court to grant specific performance of the July 2008 settlement agreement by Scarlett Place.

In count 6, Mr. Yaffe alleged that he was a third party beneficiary of the repair agreement between Scarlett Place and KEG entered into after the first settlement agreement in October 2006, and that KEG breached that contract. Appellants sought compensatory damages.

In count 9, appellants sought a permanent injunction against Scarlett Place, requiring it, inter alia, to repair all leakage and other water problems.

In the remaining relevant counts of the complaint, appellants collectively and separately alleged a variety of claims against Scarlett Place and the Knutsen entities, such as negligence, breach of contract, negligent misrepresentation, and trespass. Appellants sought compensatory damages.

Eventually, the parties went to trial. Following the conclusion of appellants’ case, appellees filed motions for judgment. After hearing argument on the motion, the circuit court granted the motions in an oral opinion.

With respect to count 1, the court found that specific performance was not warranted because appellants had not established the absence of an adequate remedy at law.

With respect to count 6, the court found that the appellees did not intend for appellants to be third party beneficiaries of the AIA contract and any subsequent contract for repairs specific to units 612 and 613.

With respect to count 9, the court found that the elements for injunctive relief had not been satisfied.

*438 As to the seven remaining relevant counts, the court found that appellants did not adequately prove damages. The court found that appellants did not prove damages based on diminution in value of units 612 and 613 because the evidence did not support the valuation of the Plaintiffs real estate expert, Jennifer Stick. Thus, the court did not find the expert’s testimony credible. The court noted that all parties agreed that the property damage was repairable. The court found appellants had not proved the cost of restoring the property to a non-damaged condition. The court concluded that the measure of damages based on the claim for loss of use was the reasonable rental value of comparable property, and appellants failed to present such evidence. In addition, the court found that appellants had not shown a loss of use for units 612 and 613 because appellants were not precluded from using the units due to water infiltration. The court also found that appellants had failed to prove breach of the 2007 settlement agreement; failed to prove any reliance on or misrepresentation by KEG related to the June 29, 2007 settlement agreement; and found that appellants had released appellees from any claims predating the June 29, 2007 settlement agreement. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Yaffe v. Scarlett Place Residential Condominium, Inc., 45 A.3d 844, 205 Md. App. 429, 2012 WL 1998066, 2012 Md. App. LEXIS 64 (Md. Ct. App. 2012).

45 A.3d 844 (Yaffe v. Scarlett Place Residential Condominium, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related