This text of 1916 OK 929 (Wyman v. Chicago, R. I. & P. Ry. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyman v. Chicago, R. I. & P. Ry. Co., 1916 OK 929, 184 P. 758, 76 Okla. 172, 1916 Okla. LEXIS 594 (Okla. 1916).

Opinions

Opinion -by

COLLIER, C.

This is an action brought by plaintiff in error against defendant in error to recover damages for personal injuries received by tie collapse of a bridge spanning tie South Canadian river, due to the alleged negligence of defendant in error.

Hereinafter tie parties will be styled as they were in the trial court.

Tie negligence alleged in tie petition is:

“That tie south portion of said bridge was constructed of timbers and embankments,'and that tie portion of said bridge over tie main channel of said stream was of steel and concrete and apparently a safe and substantial bridge and structure, and apparently a safe place to be and perform tie work assigned; still, notwithstanding tie apparent stability of said bridge, there was a latent defect in tie construction of tie same and tie abutment and approach at either end of tie steel portion of said bridge, in this, that while the abutment and piers were of concrete it was so negligently and carelessly constructed by tie defendant that they failed, in this, that instead of tie abutment being solid and reinforced concrete, which should have been under tie circumstances and conditions, tie same was so negligently and carelessly constructed that tie upper part of said concrete work was separated from the lower part, by the carelessness and negligent allowing or permitting tie lower part to set, become solid and hard before tie top part of tie concrete was placed thereon; that in each and all of tie piers and abutments tie same were not reinforced and had not been reinforced, which defect was negligent and careless and showed negligent and careless building of the same.
“Plaintiff further states that tie defendant herein had knowledge of the defective construction of said bridge at tie time that it was made, but notwithstanding this knowledge, and notwithstanding tie defective condition of tie construction of tie same, tie said defendant through its authorized ageDts, *173 officers and representatives, carelessly, negligently and willfully ordered this plaintiff thereon, informing him that the same was a safe place to work, when in truth and in fact it was not a safe place to work, all of which facts was well known to the defendant, and which facts were absolutely unknown to the plaintiff.
“That if the defendant had built and constructed said bridge, abutment and approaches as it should have been built, the said bridge would not have become broken, washed «ut, went down or become destroyed.
“That said defects were hidden from view and could not have been seen by this plaintiff and he knew nothing of them, but believed them to be perfect and sufficient and trusted and relied on the special knowledge or the supposed special knowledge and information of the said W. B\ Werner as such master carpenter, superintendent or foreman, and relying thereon and believing said bridge to be safe this plaintiff went upon said bridge and performed his work under the orders and directions of the said W. F. Wer-ner as such master carpenter, superintendent and foreman, at said time.
“Plaintiff further states that had it not been for the defective concrete work as here-inbefore set forth said abutment, approaches and piers would not have given way or gone out, nor would the bridge have been wrecked, nor would the injuria received by this plaintiff have occurred.1'

The answer of the defendant denies all the material allegations of the petition and pleads assumption of risk, contributory negligence on the part of the plaintiff, and the act of God.

The uncontradicted evidence discloses that an unprecedented flood existed in the South Canadian river, across which was a bridge supported by two piers and an abutment, a pier on the south side, and a pier in the center of the stream, and an abutment — also designated as a pier — on the north side of the stream; that plaintiff was in the employ of the defendant; that quantities of driftwood coming down the river had lodged against the piers of said bridge; that the plaintiff was directed by a vice principal of the defendant to go upon the bridge and aid in dislodging the drift which was accumulating against the center pier; that prior to plaintiff going upon the bridge he was assured by the vice principal of defendant that the bridge was safe; that the plaintiff went upon the bridge about 1:30 p. m., and aided in freeing the pier from the drift which was accumulating against it, and so continued until about 5:30 p. m., at which time the entire bridge collapsed, and plaintiff was thrown into the water, received serious injuries,drifted down the river about two miles, lodged against an island, from which he was not rescued until about 7 o’clock the nexl morning. The evidence further discloses that the bridge was not built by the defendant, but was purchased by the defendant from another road; that on inspection of the north pier or the abutment, after the disaster, it was found to be broken off near the water line; that the indications were that the lower part of said pier had been permitted to set prior to the addition of the upper part, and that consequently the two parts of said pier did not adhere; that said pier was not reinforced. There is no evidence tending to show that the other piers — on the south side and in the middle of the stream — were improperly constructed, or that there was • a defect in the bridge which would have been disclosed by any inspection that might have been made by the defendant, or that the defendant knew, or ought to have known, that the condition of the bridge, or any part thereof, was defective. It was also shown by the evidence that by the collapse of the bridge the plaintiff suffered serious, and possibly permanent, injuries.

Upon the conclusion of the evidence the defendant interposed a demurrer to the evidence, which was sustained, and judgment entered for the defendant, to which the plaintiff duly excepted.

Within the statutory time plaintiff duly moved for a new trial, which was overruled and exception saved, and ■ to reverse said judgment this proceeding in error is prosecuted.

The only error assigned in the trial of the cause is that the court erred in sustaining a demurrer to the evidence of the plaintiff and rendering judgment for the defendant.

In order to entitle plaintiff to recover, the burden is upon him to show by a preponderance of the evidence that the negligence averred and proved was the proximate cause of the injury; and this, we think, he has clearly failed to do.

“In every case involving negligence, three elements are essential to constitute actionable negligence, when the wrong charged is not willfully and intentionally done, viz.: (1) The existence of a duty on the part of the master to protect the servant from injury; (2) the failure of the master to perforjn that duty; and (3) injury to the servant approximately resulting from such failure. * * * When these elements are brought together, they unitedly constitute actionable negligence, and the absence of any one of these elements renders the complaint bad, or the evidence insufficient.” Midland Valley R. R. Co. v. Williams, 42 Okla. 444, 141 Pac. 1103, *174 29 Cyc. 419; St. L. & S. F. R. R. Co. v. Snowden, 48 Okla. 115, 149 Pac. 1083; C., R. I. & P. R. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leigh v. Wadsworth
1961 OK 62 (Supreme Court of Oklahoma, 1961)
J. C. Penny Co. v. Forrest
1938 OK 303 (Supreme Court of Oklahoma, 1938)
St. Louis-S. F. Ry. Co. v. Ford
1929 OK 421 (Supreme Court of Oklahoma, 1929)
Atchison, T. & S. F. Ry. Co. v. Clark
1926 OK 225 (Supreme Court of Oklahoma, 1926)
Jenkins v. Davis
1925 OK 580 (Supreme Court of Oklahoma, 1925)
Armstrong v. City of Tulsa
1924 OK 532 (Supreme Court of Oklahoma, 1924)
Grand v. St. Louis & San Francisco Ry. Co.
1924 OK 97 (Supreme Court of Oklahoma, 1924)
Payne v. Holder
1923 OK 772 (Supreme Court of Oklahoma, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
1916 OK 929, 184 P. 758, 76 Okla. 172, 1916 Okla. LEXIS 594, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wyman-v-chicago-r-i-p-ry-co-okla-1916.