Wright v. Coe & Anderson, Inc.

239 A.2d 493, 156 Conn. 145, 1968 Conn. LEXIS 589
CourtSupreme Court of Connecticut
DecidedFebruary 9, 1968
StatusPublished
Cited by57 cases

This text of 239 A.2d 493 (Wright v. Coe & Anderson, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright v. Coe & Anderson, Inc., 239 A.2d 493, 156 Conn. 145, 1968 Conn. LEXIS 589 (Colo. 1968).

Opinion

Covello, J.

The plaintiff brought this action to recover damages for personal injuries alleged to have been sustained by him when a ditch in which he was working caved in on him. The jury returned a verdict for the plaintiff, and from the judgment rendered thereon the defendant has appealed.

The plaintiff claimed to have proved the following facts: On April 1, 1964, the plaintiff was an employee of Hirsch Brothers, Inc., hereinafter referred to as Hirsch, which had contracted with Wykeham Rise School for Girls to construct and repair buildings on the school property. Hirsch hired the plaintiff in September, 1963, and assigned him to the Wykeham Rise School job in October, 1963. His duties included helping with demolition, form work and footings, and assisting electricians and plumbers.

Hirsch subcontracted to the defendant the excavation work on the Wykeham Rise School job. The defendant commenced that work late in the fall of 1963, using its own equipment. The work included digging and backfilling a trench from the school’s *148 dormitory to the administration building, a distance of 200 to 300 feet, for the purpose of laying conduits and a water main between the two buildings. The defendant’s work did not include the actual laying of the conduits and water main. The agreement between Hirsch and the defendant was that, if in the opinion of the defendant supports or shoring was needed to brace the sides of the ditch in question, the defendant was to notify Hirsch of the need, and Hirsch would then have its carpenters instal the shoring and supports necessary.

On April 1,1964, Frank Rinaldi, a backhoe operator employed by the defendant, commenced digging the ditch. He dug a section approximately thirty feet long, seven feet wide at the top and four and one-half feet deep. After this section of the ditch was dug, the plaintiff and three other Hirsch employees placed conduits in it, fastened them together and pulled the necessary wires through the conduits. While they were so engaged, Rinaldi did not operate the backhoe. After the plaintiff and the other Hirsch employees completed their work, Rinaldi dug a second thirty-foot section, and the plaintiff and the other Hirsch employees performed the same work as they had done in the first section. After the Hirsch employees completed their work in the second section, Rinaldi dug a third thirty-foot section, which was about six feet deep. The surface of the ground adjacent to each side of the third section was damp, muddy and sloppy, water seeped into the ditch from its sides, and the floor of the ditch was muddy and contained water. Theodore J. Anderson, the defendant’s supervisor, saw the third section of the trench and directed Rinaldi to dig a lateral trench leading out of the third section in order to drain the water from it.

*149 The plaintiff and the other Hirsch employees finished their work in the third section at noontime and stopped for lnnch. They returned at 12:30 p.m. and entered a fourth section which had been excavated by Rinaldi. This section was approximately six feet deep, water was seeping through the sides, and the floor was wet and muddy. While the plaintiff was in this section of the ditch, a side of it caved in, causing him the injuries which are the basis of this action. At the time of the accident, Rinaldi was sitting on the backhoe, which was not in operation, about thirty to forty feet from the plaintiff.

The defendant has assigned as error the refusal of the court to include certain claims of proof in the finding. A finding in a case tried to the jury is merely a narrative of the facts claimed to have been proved by each side, made for the purpose of fairly presenting any claimed errors in the charge or rulings of the court. Morgillo v. Evergreen Cemetery Assn., 152 Conn. 169, 172, 205 A.2d 368; State v. Whiteside, 148 Conn. 208, 214, 169 A.2d 260, cert. denied, 368 U.S. 830, 82 S. Ct. 52, 7 L. Ed. 2d 33. Where a party seeks additions to its own claims of proof in a case tried to the jury, the additions should he made if they are material and are supported by the evidence. Phoenix Mutual Life Ins. Co. v. Brenckman, 148 Conn. 391, 394, 171 A.2d 194. The finding is accordingly corrected by adding to it certain facts from the defendant’s draft finding which we have included in our following statement of the defendant’s claims of proof.

The finding as corrected discloses that the defendant claimed to have proved the following facts: The digging by the defendant was to be done under the supervision of Hirsch. The defendant was *150 expected to live up to the specifications in the contract between Hirsch and the trustees of Wykeham Rise School. The defendant had no authority to order Hirsch employees to do or not to do anything. Shoring was not included in the term “excavation work” as used by Hirsch. There was no arrangement with the defendant on shoring, and the defendant was not obligated to give notice of any need for shoring. If shoring had been ordered, Hirsch employees would have installed it. William L. Hirsch came to the ditch at different times during the day and inquired as to its progress. He was in the ditch ten minutes before the accident, and, although he noted it was muddy, he made no observations as to its safety. Rinaldi gave no orders or instructions to the plaintiff or to other Hirsch employees. Although the plaintiff knew before he entered the ditch that it was muddy and that water was seeping out of the ground, he never requested that the ditch be shored nor discussed shoring on April 1, 1964. During the morning, minor sections of the ditch walls had caved in. The cave-in which injured the plaintiff involved a section of earth four or five inches wide and three or four feet in length.

In addition to the assignment of error in the finding, the defendant assigns error in the refusal of the court to set aside the verdict, in rulings on evidence, in the refusal to charge as requested, in the charge as given, in granting the plaintiff’s motion to amend his complaint, and in denying the defendant’s motion to amend its answer by adding a third special defense.

The principal claim of the defendant is that it is not liable for the plaintiff’s injuries because at the time they occurred Hirsch, and not the defendant, was in control of the ditch where the cave-in took *151 place. The established general rule is that where the owner of premises employs an independent contractor to perform work upon them, the contractor, and not the owner, is liable for any losses resulting from negligence in the performance of the work until such time as it has been completed, turned over to and accepted by the owner. Trainor v. Frank Mercede & Sons, Inc., 152 Conn. 364, 368, 207 A.2d 54; Mann v. Leake & Nelson Co., 132 Conn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bracho v. Kent School
D. Connecticut, 2022
Pekera v. Purpora
869 A.2d 1210 (Supreme Court of Connecticut, 2005)
Florio v. Fisher Development, Inc.
309 A.D.2d 694 (Appellate Division of the Supreme Court of New York, 2003)
Van Nesse v. Tomaszewski
829 A.2d 836 (Supreme Court of Connecticut, 2003)
Lane v. Eisenberg, No. Cv02 0812699 S (Jan. 24, 2003)
2003 Conn. Super. Ct. 1518 (Connecticut Superior Court, 2003)
Mancini v. Fusco, No. Cv01-0167203s (Jun. 10, 2002)
2002 Conn. Super. Ct. 7621 (Connecticut Superior Court, 2002)
Welch v. Welch, No. Fa 00-0072505 (May 17, 2002)
2002 Conn. Super. Ct. 6446 (Connecticut Superior Court, 2002)
Russell v. Thierry, No. Cv01 038 51 98 S (Dec. 12, 2001)
2001 Conn. Super. Ct. 17184 (Connecticut Superior Court, 2001)
Hoffmeister v. Westbury Condo. Assn., No. Cv 98 0582041 S (Dec. 6, 2001)
2001 Conn. Super. Ct. 16097 (Connecticut Superior Court, 2001)
Kelley v. Tomas
783 A.2d 1226 (Connecticut Appellate Court, 2001)
Mozeleski v. Thomas, No. X07-Cv98-0077338s (Sep. 12, 2001)
2001 Conn. Super. Ct. 12986 (Connecticut Superior Court, 2001)
Mastrolillo v. City of Danbury
767 A.2d 1232 (Connecticut Appellate Court, 2001)
Cosker v. Metro-North Commuter R.R. Co., No. Cv 98 68566 S (Jul. 19, 2000)
2000 Conn. Super. Ct. 8584 (Connecticut Superior Court, 2000)
Hoover v. Jjl Electric, LLC, No. Cv99-0088118-S (Mar. 9, 2000)
2000 Conn. Super. Ct. 4864-bj (Connecticut Superior Court, 2000)
Isaac v. Truck Service, Inc.
727 A.2d 755 (Connecticut Appellate Court, 1999)
Remington Investments, Inc. v. National Properties, Inc.
716 A.2d 141 (Connecticut Appellate Court, 1998)
Constantine v. Schneider
715 A.2d 772 (Connecticut Appellate Court, 1998)
Giannamore v. City of Waterbury, No. Cv94-0123142s (Apr. 22, 1998)
1998 Conn. Super. Ct. 4204 (Connecticut Superior Court, 1998)
Lannan v. Child Protection Council, No. Cv 94 0049394 S (Oct. 22, 1997)
1997 Conn. Super. Ct. 10575 (Connecticut Superior Court, 1997)
Brosnan v. Sacred Heart University, No. 333544 (Oct. 21, 1997)
1997 Conn. Super. Ct. 9874 (Connecticut Superior Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
239 A.2d 493, 156 Conn. 145, 1968 Conn. LEXIS 589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-v-coe-anderson-inc-conn-1968.