Wright v. Bassinger, Unpublished Decision (5-9-2003)

CourtOhio Court of Appeals
DecidedMay 9, 2003
DocketCase No. 01CA81.
StatusUnpublished

This text of Wright v. Bassinger, Unpublished Decision (5-9-2003) (Wright v. Bassinger, Unpublished Decision (5-9-2003)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright v. Bassinger, Unpublished Decision (5-9-2003), (Ohio Ct. App. 2003).

Opinion

OPINION
{¶ 1} Plaintiffs-appellants Eugene F. Wright and Julie L. Wright appeal the decision of the Mahoning County Court of Common Pleas ordering appellants to convey land to defendants-appellees J. Paul Basinger and Sandra K. Basinger and ordering appellees to tender payment to appellants.

STATEMENT OF THE FACTS AND CASE
{¶ 2} On February, 1993, appellants and appellees executed a Land Installment Contract whereby appellees agreed to purchase a parcel of real property located at 10260 Market Street, Lima, Ohio, from appellees. Appellants' attorney drafted the contract. Appellees ageed to pay the $275,000 purchase price at 10.75 percent interest in 72 monthly installments of $2,567.07. At the end of the 72 months, a final "balloon" payment of $264,592 would be due on January 15, 1999. In addition to these payments, the contract also contained the following paragraph:

{¶ 3} "If any installment payment made to the Vendee under the terms of this contract is not paid by the Vendor when due or within thirty (30) days thereafter, the Vendor may initiate forfeiture of the interest of the Vendee in default, as provided by law (in print). A five (5) percent penalty shall be due for any payment more than ten (10) days delinquent (in type)."

{¶ 4} Appellees made timely monthly payments on the contract through December 15, 1998. In January of 1999, appellees were awaiting approval of a loan from Second National Bank of Warren and advised appellants accordingly. Appellees were uncertain whether they would obtain financing by January 15. As a result, appellants extended the due date for the balloon payment. Additionally, appellees tendered another monthly installment check for $2,567.07, which was received and cashed by appellants. Late in January, appellees were denied financing from Second National Bank. Appellees next applied to Bank One for a loan. While awaiting word on the second loan attempt, appellees wrote February and March installment checks for $2,567.07 each. Appellants accepted both checks, but did not cash either one. On March 8, 1999, appellants advised appellees they would be imposing the five percent penalty on the balloon payment, or approximately $13,209. Appellees countered the penalty was not applicable to the balloon payment. Additionally, appellees maintained they informed appellants they had obtained financing with Bank One. However, appellees did not make the balloon payment.

{¶ 5} On March 23, 1999, appellants' counsel sent appellees a letter declaring the contract in default and threatening foreclosure if all of the calculated balance, which included the disputed penalty, was not paid within ten days. Additionally, the uncashed checks for the February and March payments were returned to appellees with a note which read: "We did not cash these two checks." Appellees contacted Bank One and set a closing date of April 2, 1999. Appellees maintain they informed appellants of the proposed closing date, and also that they intended to pay all monies owed, including the disputed penalty amount, with a reservation of their rights to later litigate the propriety of the penalty. Appellants did not attend the scheduled closing; therefore, the closing did not occur on April 2, 1999.

{¶ 6} At the end of April, appellees' counsel sent a letter to appellants' counsel informing them appellees were willing to tender all amounts owed, including the disputed penalty, but reserving their rights to later litigate the penalty. Appellants refused this offer. On January 12, 2000, appellants filed a complaint seeking payment, interest and costs, and a court order that the property should be sold free from all claims, liens, interests, and rights of redemption of appellees. Appellees' answer asserted multiple affirmative defenses. Further, appellees counterclaimed on four counts, seeking conveyance of the land, dismissal of appellants' suit, damages and costs.

{¶ 7} At the bench trial, the parties presented their testimony, as well as the testimony of appellants' attorney, officers from Bank One and Second National Bank, and appellees' attorney. Appellants' attorney testified he remembered, in reaching the five percent penalty figure, he attempted to calculate the possible damages any late payment of the balloon payment would cause. Appellants acknowledged appellees' attempts to make the final payment, but stated their refusal to accept was based on the attempted reservation of rights to litigate the penalty. The trial court found appellees fulfilled their obligations under the contract. Further, the trial court found appellants were unwilling to accept offers of tender made by appellees and had refused to perform their obligations under the contract. The trial court also found the five percent penalty on the balloon was unenforceable and illegal. The trial court determined appellees were not in default, relying on the statements and actions of appellants. In other words, the trial court found for appellees, but concluded appellees had not proven damages.

{¶ 8} Accordingly, the trial court ordered appellants to convey the deed free and clear to appellees. Appellees were ordered to pay the amount due with interest at 10.75 percent per annum through April 2, 1999. It is from this order appellants appeal, assigning the following errors for our review:

{¶ 9} "I. The trial court erred in finding the application of a five percent late payment fee was illegal and unenforceable.

{¶ 10} "II. The trial court erred in finding defendants made a proper tender of payment to the plaintiffs.

{¶ 11} "III. "Where the undisputed evidence showed that defendants had both the complete control of the subject real estate including the right to receive all rents, and exclusive control and possession of the funds which were purportedly tendered for the purchase price, the trial court erred in limiting the interest payable to the plaintiffs to the amount owed as of April 2, 1999.

{¶ 12} "IV. The decision of the trial court was not sustained by the evidence and against the manifest weight of the evidence.

{¶ 13} "V. The trial court erred in failing to order foreclosure of the land contract.

{¶ 14} "VI. The trial court erred in failing to grant plaintiffs a new trial."

I.
{¶ 15} In appellants' first assignment of error, they maintain the trial court erred in finding the application of a five percent late payment fee to be illegal and unenforceable. We disagree.

{¶ 16} Ohio law recognizes liquidated damages provisions are not per se unenforceable. See Lake Ridge Academy v. Carney (1993),66 Ohio St.3d 376, 381. However, when the stipulated damages have the sole purpose of enacting a penalty, public policy will prevent enforcement. Id.

{¶ 17} To determine whether a sum to be paid is a penalty, or simply a liquidated damage clause, the court will look to the contract as well as the situation leading to the agreement. Miller v. Blockberger (1924), 111 Ohio St. 798, 807-808.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Braun v. Pikus
669 N.E.2d 880 (Ohio Court of Appeals, 1995)
City of North Olmsted v. Eliza Jennings, Inc.
631 N.E.2d 1130 (Ohio Court of Appeals, 1993)
Miller v. Blockberger
146 N.E. 206 (Ohio Supreme Court, 1924)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Sandusky Properties v. Aveni
473 N.E.2d 798 (Ohio Supreme Court, 1984)
Lake Ridge Academy v. Carney
613 N.E.2d 183 (Ohio Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Wright v. Bassinger, Unpublished Decision (5-9-2003), Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-v-bassinger-unpublished-decision-5-9-2003-ohioctapp-2003.