In the Iowa Supreme Court
No. 24–1813
Submitted December 17, 2025—Filed April 24, 2026
Worthwhile Wind LLC,
Appellee,
vs.
Worth County Board of Supervisors,
Appellant.
Appeal from the Iowa District Court for Worth County, Colleen Weiland,
judge.
A county passed a moratorium and later an ordinance regulating wind
energy development within its borders, and the county now appeals the district
court’s decision to allow a wind energy developer to continue its project under
preexisting law. Reversed and Case Remanded.
McDonald, J., delivered the opinion of the court, in which all justices
joined except McDermott, J., who filed a dissenting opinion.
Eric M. Updegraff (argued) of Hopkins & Huebner, P.C., Des Moines, for
Bret A. Dublinske (argued), Brant M. Leonard, Nicci Ledbetter, Kelcy
Whitaker, and Kristy Dahl Rogers (until withdrawal), of Fredrikson & Bryon, P.A.,
Des Moines, for appellee. 2
McDonald, Justice.
A wind energy developer devoted several years and expended millions of
dollars planning a commercial wind turbine project in Worth County, but the
developer never applied for or obtained a permit to construct the project. When
the county adopted a resolution imposing a moratorium on further wind projects
and then an ordinance regulating commercial wind turbines, the developer filed
this suit. The developer claimed the moratorium and the new ordinance
effectively precluded it from developing the project. The developer contended that
it acquired vested rights in the prior zoning regime and that the county enacted
the ordinance in bad faith. The district court agreed with both contentions and
held that the developer could complete development of its wind energy system in
accord with the law as it existed before the resolution and new ordinance were
passed. For the reasons explained below, we reverse.
I.
Worthwhile Wind LLC is an affiliate of Invenergy, LLC, a Chicago-based
renewable energy development company. Beginning in 2018, Worthwhile
undertook efforts to develop a commercial wind energy conversion system (C-
WECS) in Worth County. As conceived, the project involved the construction and
operation of as many as fifty-five commercial wind turbines across approximately
100 parcels with the capacity to generate 165 megawatts of electricity.
Worthwhile was not actually going to construct and operate the energy system.
Instead, this was a “development-transfer” project. As a development-transfer
project, Worthwhile would complete the preliminary work, including conducting
studies and obtaining necessary regulatory approvals and permits, among other
things, so that it could sell the project to a third party who would then construct
and operate the turbines. Between 2018 and early 2021, Worthwhile undertook 3
these preliminary development activities. It commissioned environmental
screenings, engineering assessments, avian use studies, bat acoustic surveys,
sound and shadow flicker analyses, and other studies. It executed wind energy
leases with over 100 landowners. It filed an application with the Midcontinent
Independent System Operator (MISO), which manages the electrical grid and the
generator interconnection process, and posted approximately $3.8 million in
interconnection security deposits.
Although Worthwhile completed many preliminary activities in the
development of the project, the essential parameters of the project remained
unspecified and unstarted. Worthwhile had not selected a wind turbine model to
use in the development. It thus could not identify the number of turbines that
needed to be built within the county to achieve the projected 165-megawatt
output because that number depended upon the turbine selected. The only
physical construction Worthwhile performed was the erection of two
meteorological (MET) towers and the excavation of two locations for cement-
stabilized “seal slabs” intended to serve as preliminary bases for future turbine
foundations. Worthwhile’s own witness described this work as preliminary to
actually laying a foundation and testified it was done to secure a favorable federal
production tax credit. No additional construction activity took place on the
approximately 160 parcels that were part of the project area. In total, Worthwhile
claims to have invested $2,800,814.55 in these preliminary activities prior to the
enactment of the challenged ordinance, exclusive of the MISO interconnection
deposits. At no point prior to the enactment of the moratorium and the new
ordinance at issue in this case did Worthwhile apply for or obtain any permit or
other authorization to develop, construct, or operate the commercial wind
turbines that constitute the core of the project. 4
Worthwhile perceived Worth County as favorable toward the development
of wind energy projects. At the time Worthwhile began its preparatory work on
the project, Worth County was partially zoned. Three townships within the
county were governed by a zoning ordinance originally adopted in 2009. The
remainder of the county was unzoned. No countywide ordinance regulating the
construction of wind turbines existed, and no county permits were required for
development in the unzoned portions of the proposed project area. In 2017, the
Worth County Board of Supervisors passed a resolution supporting a different
wind energy project, one that was centered in Freeborn County, Minnesota that
would extend into Worth County:
WHEREAS wind energy is a renewable energy source and an important component of our nation’s energy independence portfolio;
WHEREAS wind energy now supplies over 35% of Iowa’s total energy produced;
....
WHEREAS Worth County, Iowa, currently has 229 turbines, which contribute close to $172,000,000.00 in assessed valuation to our count[y’s] tax base;
WHEREAS that assessed valuation is nearly 16% of Worth County’s total property valuation;
AND WHEREAS the development and existence of wind farms in Worth County not only contributes to the property tax base but also provides jobs to our citizens and ancillary support business opportunities, including a major off load intermodal transportation facility at Manly, Iowa, and multiple wind industry maintenance businesses in Winnebago and Worth Counties that work with wind farms across the Midwest;
WHEREAS[] the development of wind projects in Worth County provides continued economic opportunity for residents and property owners of Worth County; 5
WHEREAS Worth County’s experience with other wind projects has been positive and fruitful;
THEREFORE, BE IT RESOLVED: The Worth County Supervisors support the further development of the Freeborn Wind Farm and confirm there are no county ordinances, permits or other approvals required for construction and operation of the project, and Worth County looks forward to seeing the Freeborn Wind Farm constructed and operating in the very near future.
In 2021, public sentiment in the county regarding wind development
turned based on the public’s complaints about the turbines following the
completion of the Freeborn Wind Farm project. The public elected two new
supervisors to the Board of Supervisors reflecting the change in sentiment. On
April 12, 2021, the Board of Supervisors adopted a temporary moratorium on
construction of commercial wind energy systems pending the development of
updated regulations. The moratorium resolution stated:
WHEREAS, the Board of Supervisors recently has learned that a wind energy company has obtained easement rights from several land owners in a region of Worth County predominately within drainage districts; and WHEREAS, the aforementioned drainage districts, are governed by Trustees and contain millions of dollars of drainage infrastructure that could be jeopardized by the CWES project; and WHEREAS, research indicates that CWES turbines can interfere with microwave communications signals which could affect our county communication system; and WHEREAS, the County has an interest in preventing and abating any resulting nuisance from decommissioned commercial wind turbines through more robust decommissioning requirements; and WHEREAS, the County has an interest in protecting the County’s infrastructure, natural resources and property rights through adequate setback provisions; WHEREAS, the Board of Supervisors will require substantial time to gather information and coordinate with multiple agencies for the purpose of reviewing, updating or creating ordinances, policies and procedures relative to CWES development;
NOW THEREFORE, BE IT RESOLVED by the Board of Supervisors of Worth County, Iowa, that Worth County now imposes a moratorium, effective immediately on CWES for the purpose of 6
drafting and adopting any necessary and proper revisions to the CWES ordinance. This moratorium shall sunset and be null and void on July 1st 2022.
(Emphasis omitted.) Worthwhile was the only wind energy company actively
developing in the county at the time this resolution was adopted.
Ten days before the moratorium vote, Worthwhile’s counsel sent a letter to
the Worth County Attorney asserting that Worthwhile had vested rights and
proposing a development agreement. From approximately April 2021 through
May 2022, the parties negotiated the terms of such an agreement, exchanging
draft agreements addressing setbacks, sound limits, shadow flicker thresholds,
turbine height, and turbine models. The negotiations proved unavailing. On
May 9, 2022, the Board of Supervisors declined to approve any version of the
development agreement.
On June 27, the Board enacted Worth County, Iowa,
Ordinance 2022.06.27 (June 27, 2022), regulating the construction and
operation of the C-WECS in Worth County. The new ordinance imposed setback
distance requirements, a maximum turbine height of 500 feet, noise restrictions,
and a restriction permitting zero shadow flicker at a human-occupiable building
or the property line of an adjacent building site. Id. The ordinance provided that
the setback requirements could be waived upon agreement of affected
landowners and approval by the Board of Adjustment. Id.
Worthwhile did not attempt to modify the project to comply with the new
ordinance, nor did it seek waivers or any other accommodation. Instead,
Worthwhile filed this declaratory judgment action. In count I, Worthwhile sought
a declaration that it had vested rights to complete the project under pre-
moratorium law. In count I, it also claimed that the county enacted the new
ordinance in bad faith and therefore the new ordinance could not be enforced 7
against Worthwhile. In count II, Worthwhile alleged the new ordinance was
arbitrary, capricious, unreasonable, and contrary to public policy. Following a
bench trial, the district court ruled in favor of Worthwhile on count I. The district
concluded that Worthwhile had vested rights in the project and that the county
acted in bad faith. The court ordered that Worthwhile “has a vested right to
complete development of its commercial wind energy system project in
accordance with Worth County law that existed before Resolution
No. 2020.04.05 (moratorium) and Worth County Ordinance 2022.06.27 (new
ordinance).” The county appealed.
II.
We review the district court’s findings of fact for substantial evidence and
its conclusions of law de novo. See Iowa R. App. P. 6.907; Graziano v. Bd. of
Adjustment, 323 N.W.2d 233, 236–37 (Iowa 1982).
III.
“[N]o property owner has a vested right in the continuation of a particular
zoning classification.” Quality Refrigerated Servs., Inc. v. City of Spencer, 586
N.W.2d 202, 206 (Iowa 1998). When a property owner challenges the denial or
revocation of some permit or other approval of a development, the general rule
is that the reviewing body or court will apply “the zoning law as it exists at the
time of the . . . decision.” U.S. Cellular Corp. v. Bd. of Adjustment, 589 N.W.2d
712, 717 (Iowa 1999) (quoting Arden H. Rathkopf, Daren A. Rathkopf & Edward
H. Ziegler, Rathkopf’s the Law of Zoning and Planning § 26.02(2)(a), at 26-3 to -4
(4th ed. 1996)). There are two recognized exceptions to the time of the decision
rule: the vested rights exception and the bad faith exception. Geisler v. City
Council, 769 N.W.2d 162, 167 (Iowa 2009); U.S. Cellular, 589 N.W.2d at 718. We
address each in turn. 8
A.
1.
The vested rights doctrine in the zoning context mediates a longstanding
tension between the legislative power of local governments to regulate land use
and the property rights of individuals who, in reliance upon administrative
governmental action, have committed substantial resources to a particular
course of development. See 4 Arden H. Rathkopf, Daren A. Rathkopf &
Edward H. Ziegler, Jr., Rathkopf’s the Law of Zoning and Planning § 70:1, at 70-
2 to -3 (4th ed. 2003) [hereinafter Rathkopf et al., Rathkopf’s the Law of Zoning].
The doctrine operates as an exception to the general rule that zoning changes
apply to all properties within the affected jurisdiction, including those whose
owners may have contemplated a different use under the prior regime.
Jurisdictions across the country have adopted varying formulations of the
vested rights doctrine. “In a majority of states, courts have established the
doctrine that a landowner’s right to develop land vests only at that point in time
when there has been substantial construction or action in reliance upon a
lawfully issued permit.” Id. § 70:8, at 70-7. Under the majority rule, a developer
must make “substantial expenditures in reliance upon a permit to establish a
use which, when completed, is contrary to the restrictions of a zoning
amendment enacted after the right has vested.” 3 id. § 37:3 n.2, at 37-5; see also
Steve P. Calandrillo, Chryssa Deliganis & Christina Elles, The Vested Rights
Doctrine: How a Shield Against Injustice Became a Sword for Opportunistic
Developers, 78 Ohio St. L.J. 443, 448 (2017) [hereinafter Calandrillo, Deliganis
& Elles] (stating the majority rule applies only where the developer has expended
substantial sums “on a validly issued building permit” (quoting Gregory
Overstreet & Diana M. Kirchheim, The Quest for the Best Test to Vest: 9
Washington’s Vested Rights Doctrine Beats the Rest, 23 Seattle U. L. Rev. 1043,
1045 (2000)). “[T]he existence of a validly issued building permit was the
principal benchmark of a vested rights claim.” Grayson P. Hanes & J. Randall
Minchew, On Vested Rights to Land Use and Development, 46 Wash. & Lee L.
Rev. 373, 389 (1989) [hereinafter Hanes & Minchew]. Under the majority
approach, expenditures made prior to obtaining a permit cannot form the basis
for a vested rights claim because they are, by definition, not made in reliance
upon any permit. The rationale for the majority rule follows from its doctrinal
foundation: until the property owner has asked for and received a permit, the
property owner’s plans remain speculative, and no property right has crystallized
that could be infringed by a subsequent change in zoning law.
In contrast, the minority rule “generally holds that the right to a permit
vests at the time of application as long as the application is consistent with the
building codes and ordinances then in effect.” 4 Rathkopf et al., Rathkopf’s the
Law of Zoning § 70:16, at 70-18 to -19; see also 101A C.J.S. Zoning and Land
Planning § 290, Westlaw (database updated Apr. 2026) (“In some jurisdictions, a
zoning permit applicant’s rights are determined by the ordinance in existence at
the time of filing an application for the permit.”); Calandrillo, Deliganis & Elles,
78 Ohio St. L.J. at 451 (“Generally, the minority rule allows a developer’s rights
to vest once a complete project application is filed.”). The minority approach
developed as “land development became an intensely regulated process requiring
compliance with a host of complex land use regulations and the issuance of
multiple governmental approvals prior to ground-breaking,” which “forced
landowners to expend substantial resources and crystallized their development
expectations far in advance of the issuance of a building permit.” Hanes &
Minchew, 46 Wash. & Lee L. Rev. at 389. 10
Some states adopt an intermediate approach. Under this intermediate
approach, to obtain vested rights in the completion of the project, the developer
must have engaged the administrative arm of the local government and obtained
some sort of approval to proceed under the prior zoning regime, whether through
obtaining a conditional or special use permit, securing approval of a subdivision
or site plan, or some other form of authorization. See id. at 390 (noting that
courts recognizing the intermediate approach have concluded that the
determinant governmental approval may be “approval of site-specific rezoning
application, approval of a conditional or special use permit, approval of a
subdivision or site plan, approval of a preliminary permit, or an informal
approval given by a public official”).
Whatever the particular formation of the doctrine, courts uniformly
recognize that purely private expenditures, made without any form of
engagement with the administrative arm of the local government, either by
submission of an application for approval or by receiving some sort of approval
to proceed, are not sufficient to support a claim for vested rights. As
commentators have observed, there must be some affirmative administrative
governmental act upon which the landowner can rely to proceed with
development. Id. at 388–90.
2.
In Iowa, zoning by a municipality is “a traditional legislative function.”
Geisler, 769 N.W.2d at 166. Courts generally will not interfere with the legislative
function due to “the traditional separation of powers between the three branches
of government.” Id. Based on that deference to the legislative function, Iowa’s
courts have adopted the rule that a reviewing body or court must determine the
legality of a zoning decision based on the zoning law the legislative body put in 11
place at the time of the decision. See id. at 167. “Employed by a majority of
jurisdictions, the rule rests on the theory that courts should not authorize
construction contrary to legislative provisions in effect at the time of decision.”
Ackman v. Bd. of Adjustment, 596 N.W.2d 96, 101 (Iowa 1999).
Like the majority of other courts, however, our cases recognize a vested
rights exception to this general rule based upon the developer or owner’s reliance
on formally approved plats or a validly issued permit. See Kasparek v. Johnson
Cnty. Bd. of Health, 288 N.W.2d 511, 518 (Iowa 1980) (en banc) (holding that a
developer had vested rights in the completion of a development after the board
of supervisors formally approved development plat maps); Keller v. City of Council
Bluffs, 66 N.W.2d 113, 119 (Iowa 1954) (“The theory of vested rights relates only
to such rights as an owner of property may possess not to have his property
rezoned after he has a building permit and has started his construction or
improvement.”). In Board of Supervisors v. Paaske, we concluded that the
property owner did have a vested right to complete a project where he obtained
permits for the project and expended substantial sums to complete the project
in reliance on those permits. 98 N.W.2d 827, 830–31 (Iowa 1959). In Crow v.
Board of Adjustment, this court explained that “[a] building permit duly and
legally issued by a municipality is more than a mere license revokable at the will
of the licensor.” 288 N.W. 145, 146 (Iowa 1939). “[W]hen the permittee has to
some extent acted thereon and thereby incurred expense such permit is not
revokable on the grounds that the proposed building and business would be
objectionable to residents of the neighborhood.” Id. In that case, we held the
owner could proceed with the development because “the building permit was
valid in its inception” and the “construction work was in progress.” Id. at 147. 12
In contrast, in numerous cases, this court has rejected vested rights
claims where the owner or developer had not obtained a validly issued permit.
In Geisler v. City Council, we rejected the owner’s vested rights claim “[b]ecause
only expenditures made pursuant to a validly-issued permit will support the
vested rights exception.” 769 N.W.2d at 168. In City of New Hampton v. Blayne–
Martin Corp., we rejected the owner’s vested rights claim based on a permit
because “[t]he permit, when issued, was unlawful and furnished no basis for
reliance by the” owners. 594 N.W.2d 40, 45 (Iowa 1999); see also City of
Lamoni v. Livingston, 392 N.W.2d 506, 510 (Iowa 1986) (“[W]hen a permit is
granted wholly without legal authority, the holder does not gain vested rights in
it.”). In United States Cellular Corp. v. Board of Adjustment, we explained that
Iowa law holds “that an applicant has no vested right to a particular zoning
ordinance.” 589 N.W.2d at 718. We explained that the owner in that case could
not make a vested rights claim because “it ha[d] not yet been issued a permit
that could provide a basis for the acquisition of such rights.” Id. In Quality
Refrigerated Services, Inc. v. City of Spencer, a company renovated its building
without obtaining a required building permit and then sought to claim vested
rights. 586 N.W.2d at 204, 206–07. We found no vested rights because the
property owner had not obtained a building permit at the time the property was
rezoned. Id. at 208.
3.
Applying these principles here, we conclude that Worthwhile’s vested
rights claim fails as a matter of law. Worth County never formally approved a
plat. Worthwhile never applied for or obtained a permit to construct or operate
the commercial wind turbines that are the object of the project. The only permit
Worthwhile obtained from Worth County was a permit for a single MET tower. 13
The MET tower is not the project. A permit to erect a MET tower does not vest a
right to construct dozens of commercial wind turbines across one hundred
parcels.
Worthwhile resists this conclusion. Worthwhile argues that requiring
governmental approval as a predicate to vesting produces an absurd result in
this case. In unzoned areas where no permit is required or available, Worthwhile
argues, a developer could never acquire vested rights regardless of the magnitude
of its investment. This argument does not withstand scrutiny. It is not an absurd
result to conclude that the vested rights doctrine applies only in limited
circumstances. The vested rights doctrine protects settled expectations;
expectations that crystallize when the government, through its established
permitting or approval process, has signaled that a proposed use conforms with
the applicable regulatory framework. In an unzoned area, no such signal has
been given. A developer who spends money in an unzoned area does so with
knowledge that local government retains the full scope of its legislative power to
enact zoning regulations. No enforceable right arises in a regulatory vacuum. In
addition, the vested rights doctrine is not the only protection available to a
developer in an unzoned area. The bad faith doctrine, the Contracts Clause, the
Due Process Clause, and the Takings Clause of the State and Federal
Constitutions might provide alternative avenues of relief against arbitrary or
confiscatory governmental action. See, e.g., Incorporated Town of Carter Lake v.
Anderson Excavating & Wrecking Co., 241 N.W.2d 896, 902 (Iowa 1976) (holding
that application of permitting requirement in violation of existing lease
agreement, a vested property right, would violate due process and constitute a
taking without just compensation). None of those claims are implicated here. 14
Related to this argument, Worthwhile also argues that so long as its
expenditures were lawful, the vested rights exception applies. It is true that in
Quality Refrigerated Services, the court, as part of its analysis, determined
whether the expenditures in that case were “lawful.” 586 N.W.2d at 206. The
lawfulness of the developer’s actions in that case was at issue, however, only
because the developer proceeded to develop its property in violation of existing
law by acting without a permit. Id. at 208. Because the property owner’s actions
were unlawful, i.e., taken without a permit, the property owner could not obtain
vested rights. Id. The converse of that holding is not that any expenditure
permitted by law will support a vested rights claim.
As discussed above, our precedents establish that only a lawfully
authorized project—a project for which the developer had obtained a permit or
other official government authorization to proceed—can support a vested rights
claim. This is because the vested rights claim is based on reliance on
administrative approval of the development rather than reliance on the law or,
in this case, the absence of law. The magnitude of the expenditure, standing
alone, even when not unlawful, has never been sufficient in our jurisprudence
to vest development rights. Were we to accept Worthwhile’s position, any
property owner or developer could insulate itself from lawful regulation merely
by directing expenditures toward a project in an unzoned area of a municipality.
Such a rule would interfere with the legislative function and effectively strip local
governments of their police power to regulate land use.
This concern is especially acute here. The project involves as many as fifty-
five commercial turbines at an estimated total cost potentially exceeding
$300 million. Worthwhile’s pre-moratorium expenditure of approximately
$2.8 million represents less than 1% of the total cost. The project remains largely 15
undefined. Worthwhile had not selected a turbine model, could not identify the
number of turbines it would build, and had not purchased a single turbine. The
right Worthwhile claims to have vested—the right to construct an unknown
number of unspecified turbines at unidentified locations to be sold to an
undisclosed buyer—lacks the definiteness that the vested rights doctrine
presupposes and that the permitting and approval process imposes. We note
these facts not because the magnitude of the expenditure alone would alter the
analysis—the permit requirement is a threshold condition, not a sliding scale—
but because they illustrate the consequences of the rule Worthwhile asks us to
adopt and because they underscore the absence of the settled expectations the
vested rights doctrine is designed to protect.
B.
The bad faith doctrine is the second recognized exception to the time of
decision rule. One thing should be noted at the outset regarding the bad faith
doctrine. As traditionally understood, the doctrine applies to challenge
administrative-executive actions relating to the approval or disapproval of a
particular project. Under this doctrine, the reviewing body does not apply a new
ordinance when assessing a challenge to an administrative-executive decision if
the reviewing body concludes that the administrative-executive body acted in
bad faith. For example, in Giesler, we stated, “[A] reviewing court will not apply
a new ordinance if officials acted in bad faith by denying or delaying approval of
a properly submitted and conforming site plan in order to alter a zoning
ordinance to bar the prospective development.” Geisler, 769 N.W.2d at 167.
To find bad faith, Iowa courts require “illegality . . . coupled with an
improper purpose.” Id. at 168 (footnote omitted). “[A]n illegality is established if
the board has not acted in accordance with a statute; if its decision was not 16
supported by substantial evidence; or if its actions were unreasonable, arbitrary,
or capricious.” Id. (quoting Perkins v. Bd. of Supervisors, 636 N.W.2d 58, 64 (Iowa
2001)). As to improper purpose, “it can be discerned that an improper purpose
exists” “[w]hen a zoning authority adopts a new zoning regulation designed to
frustrate a particular applicant’s plans for development.” TSB Holdings, L.L.C. v.
Bd. of Adjustment, 913 N.W.2d 1, 15 (Iowa 2018).
Zoning ordinances carry “a strong presumption of validity.” Id. at 14
(quoting Neuzil v. City of Iowa City, 451 N.W.2d 159, 163 (Iowa 1990)). A person
challenging an ordinance must overcome this presumption by showing the
ordinance is “unreasonable, arbitrary, capricious or discriminatory, with no
reasonable relationship to the promotion of public health, safety, or welfare.” Id.
(quoting Shriver v. City of Okoboji, 567 N.W.2d 397, 401 (Iowa 1997)). “Zoning is
dynamic and changing, with ‘any existing restrictions being always subject to
reasonable revisions [in light of] changing community conditions and needs as
they appear.’ ” Id. at 15 (alteration in original) (quoting Anderson v. City of Cedar
Rapids, 168 N.W.2d 739, 743 (Iowa 1969)). There is a meaningful difference
between a county attempting to properly regulate a proposed future use and a
county passing an ordinance with the improper purpose of frustrating a
particular project. See id. at 15. In United States Cellular, this court identified a
“common theme” among the factual patterns prompting courts to apply the bad
faith exception: cases in which local officials were “trying to keep one jump
ahead” of a developer and “attempting to change the rules,” or where officials “in
bad faith, delay[ed] . . . approval of a properly submitted and conforming
building plan while they alter[ed] a zoning ordinance to bar the prospective
development.” 589 N.W.2d at 717 (first quoting State ex rel. Humble Oil & Refin. 17
Co. v. Wahner, 130 N.W.2d 304, 311 (Wis. 1964); and then quoting Hatcher v.
Plan. Bd., 490 N.Y.S.2d 559, 560 (App. Div. 1985)).
Worthwhile has not carried its burden of showing the Board of Supervisors
acted illegally. The new ordinance imposed setback distances, height limitations,
noise restrictions, and shadow flicker standards—precisely the kinds of
regulatory measures that local governments routinely adopt in the exercise of
their police power. See TSB Holdings, 913 N.W.2d at 14. Worthwhile presented
no evidence that the substantive provisions of the new ordinance lacked a
rational basis or bore no reasonable relationship to the public welfare. The
county presented evidence that the supervisors who voted in favor of the
ordinance did so after reviewing over one thousand pages of material and that
they acted for purposes related to the general health, welfare, and property rights
of the citizens of Worth County. Without a showing of illegality, the bad faith
claim fails.
Nor does the record support a finding that the county acted for an
improper purpose. Worthwhile advances two principal arguments. First,
Worthwhile points to the moratorium resolution, which expressly referenced “a
wind energy company” that had “obtained easement rights from several land
owners.” Second, Worthwhile contends the new ordinance is so restrictive as to
effectively prohibit the project, reducing buildable acreage by approximately
98.2%.
As to the first argument, we acknowledge that the moratorium resolution’s
language is suggestive. The temporal proximity between the county’s learning of
the project and its adoption of the moratorium, combined with the resolution’s
express reference to “a wind energy company,” invites an inference that the
county acted specifically in response to Worthwhile. However, the fact that the 18
citizens in the county and the Board of Supervisors were aware of Worthwhile’s
activities is not sufficient to overcome the strong presumption of validity that
attaches to legislative zoning decisions. See id. More important, Worthwhile
blends the April 2021 moratorium and the June 2022 new ordinance. The
moratorium is not the primary object of this legal challenge. Instead, it is the
new ordinance. The relevant inquiry under the bad faith doctrine, as applied in
this case, is whether the final legislative act was enacted with an improper
purpose. There is no evidence of that. More than one year passed between the
adoption of the moratorium and the adoption of the new ordinance. The
negotiations between the county and Worthwhile in the interim demonstrate that
the county was willing to engage with Worthwhile and to explore a path forward,
which attenuates the inferential force of the moratorium’s language as evidence
of improper purpose in the adoption of the new ordinance.
As to the second argument, the restrictiveness of the new ordinance is a
factor, but it is not dispositive. Worthwhile’s calculation of the 98.2% reduction
in buildable acreage assumed that only turbines at the maximum allowable
height of 500 feet would be used, yet Worthwhile’s own witnesses conceded that
shorter turbine models exist and are commercially available. Worthwhile
performed no analysis of the impact the new ordinance would have if it used
shorter turbines or negotiated setback waivers from adjacent landowners. No
calculations were made of the total number of turbines that could be sited on
the remaining buildable acres under any scenario. One of Worthwhile’s own
witnesses testified only that it was “possible” that the number of available
turbine sites was zero—hardly the showing necessary to overcome the strong
presumption of validity. 19
This is not a case in which a zoning authority delayed action on a
conforming permit application while it rushed to change the rules. Worthwhile
never filed a permit application. It never submitted construction plans for
governmental approval. It never presented the county with a completed,
conforming proposal that the county could approve or deny. The county therefore
had nothing to delay and no pending application to frustrate.
We acknowledge that no countywide permitting regime for commercial wind
energy systems existed prior to the challenged ordinance, and Worthwhile could
not have filed an application under a framework that did not yet exist. But this
fact cuts against Worthwhile’s bad faith claim rather than in favor of it. Where no
permitting process has been established, the decision to create one is a
paradigmatic exercise of the police power, not evidence of bad faith. This court’s
bad faith cases involve governmental interference with an established process—
delaying a pending application, revoking a conforming permit, or changing rules
midstream. Here, there was no process to subvert. The county’s decision to adopt
a moratorium and new ordinance upon learning of a proposed large-scale
commercial wind energy development is consistent with a legitimate interest in
ensuring that an adequate regulatory framework is in place before such a
development proceeds.
We conclude the district court erred in finding bad faith. The presumption
of validity that attaches to legislative zoning decisions requires more than evidence
that the county was aware of and responded to a proposed development. It
requires evidence of illegality coupled with an improper purpose that transcends
a legitimate exercise of the police power. This record does not support such a
finding. 20
IV.
The Board of Supervisors is vested with legislative power over local land use
policy. Ackman, 596 N.W.2d at 104. No property owner has a right to be an island
unto itself and insist that the Board of Supervisors be divested of the power to
make and apply new law in a previously unzoned area of the county. The vested
rights exception and bad faith exception are related to claims arising out of
administrative-executive branch decisions, not stand-alone bases for challenging
legislative action. For the foregoing reasons, we reverse the judgment of the district
court. We remand for further proceedings consistent with this opinion, including
any remaining proceedings on count II of Worthwhile’s petition.
Reversed and Case Remanded.
All justices concur except McDermott, J., who files a dissenting opinion. 21
#24–1813, Worthwhile Wind, LLC v. Worth Cnty. Bd. of Supervisors
McDermott, Justice (dissenting).
After successfully attracting an energy company to develop wind turbine
projects in Worth County, the Worth County Board of Supervisors backtracked
and passed a moratorium barring the projects. But the developer, by that point
three years into its turbine project, had already signed over 160 easement
agreements to acquire land rights for the project, constructed two massive
concrete footings for turbines, secured a connection to the midcontinent
electrical grid, and spent millions of dollars. The majority today blesses the
county’s about-face and effectively kills the project despite its advanced stage.
In my view, the facts here easily establish that the developer has a vested right
under our precedents to finish the project.
The wind energy developer here, Invenergy, created Worthwhile Wind LLC
as a project entity in 2018 to pursue the development of a new wind farm in
Worth County. The Worthwhile project was to be Invenergy’s second wind farm
development in the county. Invenergy’s first project, a smaller wind farm called
Freeborn, was at that time nearing completion.
The Board welcomed Invenergy to develop new wind projects in the county.
When the Worthwhile project began, there were already 229 wind turbines
operating in the county. Seeking to expand the county’s existing wind turbine
network, the Board chair told Invenergy they would “take every additional
[turbine] we can get.” The Board formalized its pursuit in August 2017 by passing
a resolution that officially invited further wind development in the county, stating
in part:
WHEREAS wind energy is a renewable energy source and an important component of our nation’s energy independence portfolio; 22
WHEREAS wind energy now supplies over 35% of Iowa’s total energy produced;
WHEREAS Worth County, Iowa, currently has 229 turbines, which contribute close to $172,000,000.00 in assessed valuation to our count[y’s] tax base;
WHEREAS that assessed valuation is nearly 16% of Worth County’s total property valuation;
AND WHEREAS the development and existence of wind farms in Worth County not only contributes to the property tax base but also provides jobs to our citizens and ancillary support business opportunities, including a major off load intermodal transportation facility at Manly, Iowa, and multiple wind industry maintenance businesses in Winnebago and Worth Counties that work with wind farms across the Midwest;
WHEREAS[] the development of wind projects in Worth County provides continued economic opportunity for residents and property owners of Worth County;
WHEREAS Worth County’s experience with other wind projects has been positive and fruitful;
THEREFORE, BE IT RESOLVED: The Worth County Supervisors support the further development of the Freeborn Wind Farm and confirm there are no county ordinances, permits or other approvals required for construction and operation of the project, and Worth County looks forward to seeing the Freeborn Wind Farm constructed and operating in the very near future.
Given the county’s enthusiastic invitation for wind projects in the Board’s
resolution, the majority’s statement that “Worthwhile perceived Worth County
as favorable toward the development of wind energy projects” is, to say the least,
an interesting characterization. The county deliberately—and successfully—
cultivated that very perception. 23
As the resolution makes clear, the county sought to entice developers by
promoting the county’s favorable regulatory scheme for turbine projects. The
resolution is explicit in trumpeting “there are no county ordinances, permits or
other approvals required for construction and operation.” Under the county’s
then-existing zoning ordinance, which had been in effect since 2009, installing
wind turbines in most of the county required no permit. Worthwhile
understandably designed the Worthwhile project to target the vast expanse of
the county where, in the county’s own words, no “permits or other approvals” to
construct or operate were necessary.
Nonetheless, in April 2021, the Board, in a 2–1 vote, with two new
supervisors on the three-person Board voting in favor, adopted a moratorium
that banned the construction of wind turbines in the county until new wind
regulations could be enacted. The Worthwhile project by this point had been
ongoing for more than three years. Worthwhile attempted to negotiate a formal
development agreement with the county in earnest over the following thirteen
months. Despite these efforts, the Board, again on a 2–1 vote, enacted a new
ordinance on June 27, 2022, that would, for the first time, regulate the
construction and operation of commercial wind energy conversion systems
throughout the county. See Worth County, Iowa, Ordinance 2022.06.27
(June 27, 2022). The various required setbacks in the new ordinance, taken
together, eliminated nearly all the buildable areas that Worthwhile had targeted
for construction. The ordinance also contained additional restrictions on sound,
shadow flicker, lighting, and maximum height that further encumbered the
project. Worthwhile filed suit against the county seeking a declaratory judgment
to complete the project. 24
When a zoning law has been changed in a way that imposes a new
restriction on an ongoing project, courts will not require compliance with the
new law if either (1) the property owner has acquired a “vested right” under the
prior law to complete the project, or (2) the municipality has acted in “bad faith”
against the property owner in enacting the new restriction. Geisler v. City Council,
769 N.W.2d 162, 167 (Iowa 2009). After a trial, the district court ruled in
Worthwhile’s favor, finding both that Worthwhile had obtained a vested right to
complete the project and that the county acted in bad faith with an improper
purpose in adopting the moratorium and new ordinance.
We have been called upon to decide whether a developer has established
a vested right to complete a project on numerous occasions. As we have
observed, the concept of vested rights balances a property owner’s private
interests against the needs of the general public. Kasparek v. Johnson Cnty. Bd.
of Health, 288 N.W.2d 511, 518 (Iowa 1980) (en banc). It recognizes that when
an owner makes significant, legitimate investments before a new regulation is
enacted, those expenditures can create a protected property right. Id. Under the
law, this property right “cannot be arbitrarily interfered with or taken away
without just compensation.” Id.
Whether a property owner has acquired a vested right involves a two-part
inquiry: “(1) did the property owner make substantial expenditures toward the
use in question prior to the zoning change; and (2) were the expenditures made
by the property owner lawful.” Quality Refrigerated Servs., Inc. v. City of Spencer,
586 N.W.2d 202, 206 (Iowa 1998).
The district court found that Worthwhile had committed more than
sufficient financial and human resources to the project to establish a vested right
under the prior regulatory framework. These efforts and expenditures covered a 25
wide range of development activities and expenses before the April 2021
moratorium, including:
Electric grid interconnection. In March 2018, Worthwhile initiated the
formal interconnection process with the Midcontinent Independent System
Operator (MISO). Worthwhile paid over $600,000 in direct fees related to the
MISO study and interconnection process. To maintain its priority in the grid
queue, Worthwhile posted more than $3.8 million in security. These funds were
nonrefundable and subject to forfeiture if the project withdrew.
Land acquisition. Worthwhile conducted a three-year campaign to secure
real estate contracts for its turbines and related infrastructure. Among other
expenditures, it spent upwards of $400,000 on land agents and paid more than
$700,000 directly to Worth County landowners. It entered into 162 easement
agreements. Under these recorded easements, Worthwhile is contractually
obligated to pay an additional $1.7 million over the remaining easement terms.
Technical due diligence and permitting. Worthwhile invested over $160,000
for specialized technical and environmental site studies, including aviation
surveys, microwave path studies, and environmental and wildlife impact
assessments. It also spent roughly $34,000 to erect and operate two
meteorological towers to gather data. One of the towers was within a zoned area
of the county; the Board permitted and approved its installation without
objection. Worthwhile further secured necessary environmental permits from the
Iowa Department of Natural Resources and engaged engineering consultants to
design site-specific infrastructure.
Physical site development. Worthwhile moved into the physical
construction phase by completing “seal slab” foundations for two wind turbines.
These enormous concrete bases were each ninety-one feet across and thirteen 26
feet deep. Between geological testing, professional design, and contractor labor,
the construction of these foundations totaled over $300,000.
All told, the district court calculated that Worthwhile had committed over
$7 million to the project by the time the Board adopted the moratorium. The
district court concluded that the “plans, studies, analysis, regulatory
application, landowner engagement, and financial commitments were
substantial” and thus “secured vested rights in the existing zoning scheme.”
In analyzing whether Worthwhile established a vested right against a
zoning change, the majority abandons our established two-part test. Instead, the
opinion flatly asserts that no vested right exists unless a property holder
possesses a permit at the time of a zoning change. Applying this new standard,
the majority concludes that Worthwhile had no vested right because it had not
sought or received a permit when the Board adopted the moratorium—even
though no permit was required.
The majority’s rationale suffers from two fatal defects. First, our
precedents do not make a permit a prerequisite for a vested right. Indeed, many
of our past decisions directly contradict the majority’s new rule. Take Kasparek
v. Johnson County Board of Health, where a county passed a new ordinance
requiring lot sizes of five acres as a prerequisite to receiving a permit for a septic
tank system. 288 N.W.2d at 516. Property owners who had purchased smaller
lots before the change claimed a vested right under the prior regulations, which
had no lot size requirement. Id. We held that these owners had a vested right to
install septic systems under the prior regulations. Id. at 520. Nothing in our
opinion even hinted that the owners’ lack of a permit at the time of the
ordinance’s adoption somehow disqualified them from having a vested right. 27
The same principle applied in Incorporated Town of Carter Lake v.
Anderson Excavating & Wrecking Co., where the defendant operated a landfill
under a ten-year lease approved by the city. 241 N.W.2d 896, 902 (Iowa 1976).
Two years later, the city passed an ordinance requiring a permit to continue
operating the landfill. Id. at 899. We held that the previously approved lease gave
the defendant a vested right to use the property as a landfill despite having no
permit. Id. at 902.
We reached a similar conclusion in Board of Supervisors v. Paaske. 98
N.W.2d 827, 831 (Iowa 1959). There, a property owner planned to move five
houses onto a 2.4-acre parcel in LeClaire Township. Id. at 828. Although the
owner had a permit to remove the houses from their original locations, the
LeClaire parcel itself was not subject to any zoning laws at the time of the
purchase. Id. But before the houses were installed, the county passed an
ordinance requiring at least one acre per residence in LeClaire. Id. We held that
the owner had a vested right to complete the project despite the new ordinance.
Id. at 831. Notably, our analysis didn’t mention a construction permit as a
prerequisite, which makes sense considering no such permit was required before
the ordinance was adopted. See id.
Likewise, in Nemmers v. City of Dubuque, the United States Court of
Appeals for the Eighth Circuit applied Iowa law to determine whether a developer
had acquired vested rights for industrial development of his property after the
city annexed and rezoned the property for residential use. 716 F.2d 1194, 1197
(8th Cir. 1983). Rather than focusing on a building permit—which the developer
never obtained—the court emphasized that assessing vested rights “is
necessarily an ad hoc inquiry.” Id. Relying heavily on Paaske and Kasparek, the
court held that the developer’s $140,000 investment in preliminary grading and 28
road work was sufficient to vest his right to complete the project for industrial
use under the prior zoning regulations. Id. at 1198–99.
Invenergy designed the Worthwhile project by targeting turbine sites in
unzoned areas of the county. The only part of the project requiring a permit from
the county—for a data tower in a zoned township—was secured before
Worthwhile constructed it. The majority penalizes Worthwhile for lacking a
permit that the county had made clear was never required in the first place. The
majority doesn’t explain what permit was even available, let alone required. What
was Invenergy supposed to do in this situation? Lobby the supervisors to zone
the county’s unzoned areas so it could then ask for a permit?
Stated simply, the majority’s core premise—that “until the property owner
has asked for and received a permit, the property owner’s plans remain
speculative, and no property right has crystallized”—directly conflicts with our
precedents. If vested rights were truly contingent on a building permit, our
repeated recognition of those rights in cases where no permit existed would be
inexplicable. Since the project did not depend on obtaining a county building
permit, Worthwhile’s vested rights claim cannot fail for the lack of one. We
recognize vested rights when a county amends an existing zoning requirement;
there is no logical reason to deny those same rights when no zoning requirement
existed to begin with.
By misstating the proper test, the majority reaches the wrong answer.
Unlike the majority’s new permit rule, our longstanding two-part inquiry for
vested rights offers the better mode of analysis. Again, under that two-part
inquiry, we consider (1) whether the property owner made substantial
expenditures toward the use in question before the zoning change, and
(2) whether the owner’s expenditures were “lawful.” Quality Refrigerated Servs., 29
Inc., 586 N.W.2d at 206. In this case—just as in Kasparek and Paaske—the
expenditures were lawful not because the property owners held building permits
but because none were needed.
A permit is relevant to lawfulness—but only when a permit is required. See
Geisler, 769 N.W.2d at 168 (“[W]ithout the required building permit, the
landowner’s expenditures were illegal and, therefore, could not be relied upon to
acquire a vested right.”) (emphasis added). The majority calls unzoned areas
“regulatory vacuum[s],” where no enforceable rights exist absent the Board’s
approval. But the Board’s decision not to zone an area is itself a regulatory
choice, no less controlling than a decision to impose zoning requirements. Our
precedents establish that owners may rely on the absence of a permit
requirement just as readily as they would on an affirmative requirement. See,
e.g., Kasparek, 288 N.W.2d at 516; Anderson Excavating, 241 N.W.2d at 902;
Paaske, 98 N.W.2d at 831. Where no permit is required, the owner’s
expenditures on a project are lawful and fully capable of supporting a vested
right. See Application of Campsites Unlimited, Inc., 215 S.E.2d 73, 77–78
(N.C. 1975) (clarifying that in prior cases relying on building permits to establish
vested rights, “[t]he only significance of the building permit . . . was that such
permit was required, under the ordinance in effect at the time of its issuance, in
order to make the proposed use of the property lawful”).
Interestingly, the majority attempts to explain our finding of vested rights
in Kasparek—where no permit was ever issued—by suggesting that the county’s
prior approval of a plat map with smaller than five-acre lots sufficed in place of
a permit. But Kasparek certainly does not stand for the proposition that an
approved plat serves as a condition precedent to acquiring a vested property right
against a zoning change. 288 N.W.2d at 518. (Here, no one argues that 30
Worthwhile needed a plat approval for the project.) Kasparek relied on Paaske—
identifying it as “[t]he most analogous Iowa decision”—and its test analyzing the
owner’s “legitimate and valuable expenditures in connection with the use of an
affected tract or in a business conducted on it, before imposition of the
regulation.” Id. The majority confuses the evidentiary weight of a permit or plat
approval in determining whether expenditures were lawful, with a strict legal
requirement to obtain one or the other. Again, our precedents have consistently
focused on the owner’s tangible actions and financial commitments, not whether
the county issued a permit or approved a plat.
The majority’s errors in its vested rights analysis do not stop there. In
discussing whether Worthwhile’s expenditures were sufficiently substantial, the
majority compares the amount expended to the anticipated total cost of the
completed project, which the majority notes could exceed $300 million. But there
is no minimum ratio between expenditures and projected final cost that must be
met to qualify as substantial. In Paaske, we found that the owner had acquired
a vested right to continue with construction of the housing project where the
owners had expended only $8,126 for preparatory work when the county tried
to stop the project. 98 N.W.2d at 828–29. In considering the sufficiency of the
expenditure, we declared: “It is impossible to fix a definite percentage of the total
cost which establishes vested rights and applies to all cases. It depends on the
type of the project, its location, ultimate cost, and principally the amount
accomplished under conformity. Each case must be decided on its own merits,
taking these elements into consideration.” Id. at 831. In the lengthy history of
Iowa cases addressing vested rights, none has ever compared the amount
expended to an estimated final cost. The only Iowa case that mentions such an 31
exercise, Paaske, never actually discussed the project’s total cost, and our
holding certainly does not rely on some ratio derived from it. See id.
What’s more, even if a cost ratio were a relevant consideration in
determining whether expenditures were substantial, the total cost to construct
the project is not the correct comparator here. As the district court found,
Invenergy designed Worthwhile to be a “development-transfer” project, meaning
that it would be sold to a customer to complete construction once Worthwhile
finished developing it. As the trial evidence established, the total sale price of the
developed-but-not-yet-constructed project here ranged from $11.5 million to $33
million. Even if we were to apply a ratio, the district court’s finding that
Worthwhile had spent $7 million by the time the Board passed the moratorium
would be sufficiently substantial as compared to these figures.
More broadly, Worthwhile’s $7 million expenditure blows away sums in
prior cases that we (or the Eighth Circuit applying Iowa law) deemed substantial
enough to create a vested right. See Quality Refrigerated Servs., Inc., 586 N.W.2d
at 206–07 ($650,000 found substantial); Nemmers, 716 F.2d at 1198–99
($140,000); Kasparek, 288 N.W.2d at 518 ($13,000); Paaske, 98 N.W.2d at 829
($8,126); Stoner McCray Sys. v. City of Des Moines, 78 N.W.2d 843, 848–49
(Iowa 1956) ($600). Even when adjusted for inflation and added together, the
combined total of amounts deemed substantial in all these cases is still just a
fraction of the amount Worthwhile spent here. By any standard, Worthwhile’s
pre-moratorium expenditure was substantial.
Worthwhile proved a vested right to complete this project. Because the
district court’s judgment can be upheld by affirming its holding on vested rights
alone, I will forgo discussion of the district court’s alternative holding that 32
Worthwhile is entitled to judgment based on evidence that the Board acted in
bad faith.
Worthwhile had spent three years and millions of dollars developing this
project when the Board passed the moratorium. By declaring Worthwhile’s
efforts insufficient to establish a vested right, the majority leaves future energy
developers completely exposed as they consider the immense cost, risk, and
complexity of large-scale wind energy projects. Beyond inventing a permit
requirement that neither precedent nor logic dictates, today’s opinion suggests
that even tens of millions of dollars in expenditures may still not qualify as
substantial. “Predictability . . . is a needful characteristic of any law worthy of the
name.” Antonin Scalia, The Rule of Law as a Law of Rules, 56 U. Chi. L. Rev. 1175,
1179 (1989) (footnote omitted). By turning away from our vested-rights
precedents, we have severely undermined predictability not only for the developer
in this case, but for all developers considering complex wind energy projects in
our state.
There is an oft-cited legal maxim coined by Justice Oliver Wendell Holmes
that “[m]en must turn square corners when they deal with the Government.” Rock
Island, A. & L. R. Co. v. United States, 254 U.S. 141, 143 (1920). But as Justice
Robert Jackson observed, “It is very well to say that those who deal with the
Government should turn square corners. But there is no reason why the square
corners should constitute a one-way street.” Federal Crop Ins. v. Merrill, 332 U.S.
380, 387–88 (1947) (Jackson, J., dissenting). In this case, the county has been
allowed to treat its obligation to recognize vested rights as precisely the one-way
street Justice Jackson warned against. By failing to recognize Worthwhile’s vested
right to complete the project, the majority has denied Worthwhile the legal
protections it should have been able to rely on. Respectfully, I dissent.