Worthwhile Wind, LLC v. Worth County Board of Supervisors

Supreme Court of Iowa·Decided April 24, 2026·No. 24-1813·Published

Opinion

In the Iowa Supreme Court No. 24–1813

Submitted December 17, 2025—Filed April 24, 2026 Worthwhile Wind LLC,

Appellee,

vs.

Worth County Board of Supervisors, Appellant.

Appeal from the Iowa District Court for Worth County, Colleen Weiland, judge.

A county passed a moratorium and later an ordinance regulating wind energy development within its borders, and the county now appeals the district court’s decision to allow a wind energy developer to continue its project under preexisting law. Reversed and Case Remanded.

McDonald, J., delivered the opinion of the court, in which all justices joined except McDermott, J., who filed a dissenting opinion.

Eric M. Updegraff (argued) of Hopkins & Huebner, P.C., Des Moines, for appellant.

Bret A. Dublinske (argued), Brant M. Leonard, Nicci Ledbetter, Kelcy Whitaker, and Kristy Dahl Rogers (until withdrawal), of Fredrikson & Bryon, P.A., Des Moines, for appellee.

McDonald, Justice.

A wind energy developer devoted several years and expended millions of dollars planning a commercial wind turbine project in Worth County, but the developer never applied for or obtained a permit to construct the project. When the county adopted a resolution imposing a moratorium on further wind projects and then an ordinance regulating commercial wind turbines, the developer filed this suit. The developer claimed the moratorium and the new ordinance effectively precluded it from developing the project. The developer contended that it acquired vested rights in the prior zoning regime and that the county enacted the ordinance in bad faith. The district court agreed with both contentions and held that the developer could complete development of its wind energy system in accord with the law as it existed before the resolution and new ordinance were passed. For the reasons explained below, we reverse.

I.

Worthwhile Wind LLC is an affiliate of Invenergy, LLC, a Chicago-based renewable energy development company. Beginning in 2018, Worthwhile undertook efforts to develop a commercial wind energy conversion system (C- WECS) in Worth County. As conceived, the project involved the construction and operation of as many as fifty-five commercial wind turbines across approximately 100 parcels with the capacity to generate 165 megawatts of electricity. Worthwhile was not actually going to construct and operate the energy system. Instead, this was a “development-transfer” project. As a development-transfer project, Worthwhile would complete the preliminary work, including conducting studies and obtaining necessary regulatory approvals and permits, among other things, so that it could sell the project to a third party who would then construct and operate the turbines. Between 2018 and early 2021, Worthwhile undertook

these preliminary development activities. It commissioned environmental screenings, engineering assessments, avian use studies, bat acoustic surveys, sound and shadow flicker analyses, and other studies. It executed wind energy leases with over 100 landowners. It filed an application with the Midcontinent Independent System Operator (MISO), which manages the electrical grid and the generator interconnection process, and posted approximately $3.8 million in interconnection security deposits.

Although Worthwhile completed many preliminary activities in the development of the project, the essential parameters of the project remained unspecified and unstarted. Worthwhile had not selected a wind turbine model to use in the development. It thus could not identify the number of turbines that needed to be built within the county to achieve the projected 165-megawatt output because that number depended upon the turbine selected. The only physical construction Worthwhile performed was the erection of two meteorological (MET) towers and the excavation of two locations for cement- stabilized “seal slabs” intended to serve as preliminary bases for future turbine foundations. Worthwhile’s own witness described this work as preliminary to actually laying a foundation and testified it was done to secure a favorable federal production tax credit. No additional construction activity took place on the approximately 160 parcels that were part of the project area. In total, Worthwhile claims to have invested $2,800,814.55 in these preliminary activities prior to the enactment of the challenged ordinance, exclusive of the MISO interconnection deposits. At no point prior to the enactment of the moratorium and the new ordinance at issue in this case did Worthwhile apply for or obtain any permit or other authorization to develop, construct, or operate the commercial wind turbines that constitute the core of the project.

Worthwhile perceived Worth County as favorable toward the development of wind energy projects. At the time Worthwhile began its preparatory work on the project, Worth County was partially zoned. Three townships within the county were governed by a zoning ordinance originally adopted in 2009. The remainder of the county was unzoned. No countywide ordinance regulating the construction of wind turbines existed, and no county permits were required for development in the unzoned portions of the proposed project area. In 2017, the Worth County Board of Supervisors passed a resolution supporting a different wind energy project, one that was centered in Freeborn County, Minnesota that would extend into Worth County:

WHEREAS wind energy is a renewable energy source and an important component of our nation’s energy independence portfolio;

WHEREAS wind energy now supplies over 35% of Iowa’s total energy produced;

....

WHEREAS Worth County, Iowa, currently has 229 turbines, which contribute close to $172,000,000.00 in assessed valuation to our count[y’s] tax base;

WHEREAS that assessed valuation is nearly 16% of Worth County’s total property valuation;

AND WHEREAS the development and existence of wind farms in Worth County not only contributes to the property tax base but also provides jobs to our citizens and ancillary support business opportunities, including a major off load intermodal transportation facility at Manly, Iowa, and multiple wind industry maintenance businesses in Winnebago and Worth Counties that work with wind farms across the Midwest;

....

WHEREAS[] the development of wind projects in Worth County provides continued economic opportunity for residents and property owners of Worth County;

WHEREAS Worth County’s experience with other wind projects has been positive and fruitful;

....

THEREFORE, BE IT RESOLVED: The Worth County Supervisors support the further development of the Freeborn Wind Farm and confirm there are no county ordinances, permits or other approvals required for construction and operation of the project, and Worth County looks forward to seeing the Freeborn Wind Farm constructed and operating in the very near future.

In 2021, public sentiment in the county regarding wind development turned based on the public’s complaints about the turbines following the completion of the Freeborn Wind Farm project. The public elected two new supervisors to the Board of Supervisors reflecting the change in sentiment. On April 12, 2021, the Board of Supervisors adopted a temporary moratorium on construction of commercial wind energy systems pending the development of updated regulations. The moratorium resolution stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Worthwhile Wind, LLC v. Worth County Board of Supervisors, (iowa 2026).

Worthwhile Wind, LLC v. Worth County Board of Supervisors (Worthwhile Wind, LLC v. Worth County Board of Supervisors) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Federal Crop Ins. Corp. v. Merrill
332 U.S. 380 (Supreme Court, 1947)
Application of Campsites Unlimited, Inc.
215 S.E.2d 73 (Supreme Court of North Carolina, 1975)
Shriver v. City of Okoboji
567 N.W.2d 397 (Supreme Court of Iowa, 1997)
Keller v. City of Council Bluffs, Iowa
66 N.W.2d 113 (Supreme Court of Iowa, 1954)
Graziano v. BOARD OF ADJUSTMENT, ETC.
323 N.W.2d 233 (Supreme Court of Iowa, 1982)
City of Lamoni v. Livingston
392 N.W.2d 506 (Supreme Court of Iowa, 1986)
Kasparek v. Johnson County Board of Health
288 N.W.2d 511 (Supreme Court of Iowa, 1980)
Perkins v. Board of Supervisors
636 N.W.2d 58 (Supreme Court of Iowa, 2001)
United States Cellular Corp. v. Board of Adjustment
589 N.W.2d 712 (Supreme Court of Iowa, 1999)
Stoner McCray System v. City of Des Moines
78 N.W.2d 843 (Supreme Court of Iowa, 1956)
Geisler v. CITY COUNCIL OF CEDAR FALLS
769 N.W.2d 162 (Supreme Court of Iowa, 2009)
Neuzil v. City of Iowa City
451 N.W.2d 159 (Supreme Court of Iowa, 1990)
Board of Supervisors of Scott County v. Paaske
98 N.W.2d 827 (Supreme Court of Iowa, 1959)
City of New Hampton v. Blayne-Martin Corp.
594 N.W.2d 40 (Supreme Court of Iowa, 1999)
Quality Refrigerated Services, Inc. v. City of Spencer
586 N.W.2d 202 (Supreme Court of Iowa, 1998)
Anderson v. City of Cedar Rapids
168 N.W.2d 739 (Supreme Court of Iowa, 1969)
Crow v. Board of Adjustment of Iowa City
288 N.W. 145 (Supreme Court of Iowa, 1939)