WORTHINGTON COMMUNITIES, INC. v. Mejia

28 So. 3d 79, 2009 Fla. App. LEXIS 19608, 2009 WL 4825111
CourtDistrict Court of Appeal of Florida
DecidedDecember 16, 2009
Docket2D07-1490, 2D07-3698
StatusPublished
Cited by2 cases

This text of 28 So. 3d 79 (WORTHINGTON COMMUNITIES, INC. v. Mejia) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WORTHINGTON COMMUNITIES, INC. v. Mejia, 28 So. 3d 79, 2009 Fla. App. LEXIS 19608, 2009 WL 4825111 (Fla. Ct. App. 2009).

Opinions

VILLANTI, Judge.

Worthington Communities, Inc., and Ohio Casualty Insurance Co. appeal the final judgment and amended final judgment entered against them in this personal injury action arising out of a construction accident. On cross-appeal, the Mejias raise a standing argument as to Ohio Casualty and two arguments directed to the judgments. We affirm the final judgment in all respects. While we have carefully considered all of the arguments raised by the parties, we write to address only two issues raised in the direct appeal.

Facts

In 1999, Worthington was developing a condominium project in Fort Myers, Florida. As to that project, Worthington was both the owner of the property and the general contractor in charge of the construction of multiple condominium units.

Worthington contracted with Sunshine Masonry, Inc., for the masonry work on the condominium project. The scope of this work included installing forms and pouring concrete for the structural divisions between the floors of each condominium unit. The project plans called for Sunshine Masonry to use a joist system developed by Hambro Structural Systems to form the floors and ceilings within and between the units. The Hambro joist system required the masonry contractor to place steel joists across the span between the exterior masonry walls. The stability of these joists during construction was ensured by the installation of steel cross members, called rollbars, both around the perimeter of the walls and at designated intervals along the length of the joists. After the rollbars were installed, sheets of plywood were installed as the form on which the concrete would be poured. Wire reinforcement mesh was then placed on the plywood before the concrete was poured. Once the concrete was poured and had cured, the rollbars were removed and the plywood was stripped away, leaving a reinforced poured concrete floor/ceiling.

[82]*82The bundles of wire mesh used with the Hambro system were large, and each bundle weighed 3700 pounds. Evidence presented at trial established that Hambro’s product literature represented that it was safe to load and store mesh bundles on top of completed masonry walls. The product literature also represented that it was safe to load and store mesh bundles on the steel joists after the rollbars were completely installed. Either of these options was a permissible “staging” technique that allowed the mesh bundles to be accessible for use in an adjoining condominium unit. However, it was not acceptable to load or store mesh bundles on the steel joists before the rollbars were fully installed because the joists were too unstable at that point to support the weight and mass of the mesh bundles. This danger was made clear in both the documentation from Hambro about the joist system and in the general notes on the blueprints for the condominium project.

On Friday, May 14, 1999, Sunshine Masonry used a crane to place steel Hambro joists between the first and second floors of one of the condominium units that was under construction. After the joists were in place but before the rollbars were fully installed, Sunshine Masonry used the crane to place bundles of wire mesh on top of the unbraced joists. The following day, Sunshine Masonry was on site continuing with the installation of the Hambro joist system. Mr. Mejia, who worked for Sunshine Masonry as an unskilled laborer, was working below the unbraced joists that were supporting the mesh bundles. As he did so, the unbraced joist system collapsed and a bundle of wire mesh fell on him. The weight and force of the impact rendered Mr. Mejia a quadriplegic.

The Mejias initially sued numerous entities involved in the construction of the condominium project. However, by the time of trial, the sole claim to be tried was the Mejias’ claim that Worthington was negligent by failing to provide Mr. Mejia with a safe place to work. The Mejias did not allege that Worthington was vicariously liable for the negligence of Sunshine Masonry. Instead, they alleged that Worthington had been actively negligent in causing this accident. The essence of the Mejias’ claim was that Worthington, as the owner/general contractor, had a duty to maintain the site in a safe condition for all workers and that Worthington had breached that duty by failing to correct, or arrange to have corrected, the dangerous condition created by Sunshine Masonry when it loaded mesh bundles onto the unbraced Hambro joists.

After a two-week trial, the jury awarded the Mejias damages in excess of $6.5 million. The jury apportioned five percent of the negligence to Mr. Mejia, ten percent to Worthington, and eighty-five percent to Sunshine Masonry. Under the applicable version of the joint and several liability statute, section 768.81, Florida Statutes (1999), Worthington was liable for ninety-five percent of the economic losses, which totaled more than $5 million. Ohio Casualty, as Worthington’s insurer, was added as a party to the lawsuit pursuant to section 627.4136(4), Florida Statutes (1999), after the jury’s verdict.

In this appeal, Worthington contends that final judgment should have been entered in its favor because the trial court should have granted its motion for directed verdict at the close of the Mejias’ case. In the alternative, Worthington contends that it is entitled to a new trial because the jury instructions given by the trial court were confusing and included incorrect statements of the law. We address each of these arguments in turn.

[83]*83Motion for Directed Verdict

In its first argument, Worthington contends that the trial court erred by denying its motion for directed verdict because there was no evidence that it breached any duty it owed to Mr. Mejia or that any breach was the proximate cause of his injuries. Because there was disputed evidence on these issues, the trial court properly denied this motion.

The focus of the parties’ dispute on this issue lies in the extent of the duties owed to a subcontractor’s employee by an entity that is both the owner and general contractor on a construction project. While an owner who hires an independent contractor is not generally liable for injuries sustained by that contractor’s employees, an exception to this general rule exists when the owner “has been actively participating in the construction to the extent that he directly influences the manner in which the work is performed” or has engaged in “acts either negligently creating or negligently approving the dangerous condition resulting in the injury or death to the employee.” Conklin v. Cohen, 287 So.2d 56, 60 (Fla.1973); see also Johnson v. Boca Raton Cmty. Hosp., Inc., 985 So.2d 593, 595-96 (Fla. 4th DCA 2008), review denied, 1 So.3d 172 (Fla.2009); Atl. Coast Dev. Corp. v. Napoleon Steel Contractors, Inc., 385 So.2d 676, 679 (Fla. 3d DCA 1980). Thus, an owner who is also acting as a general contractor “has the ultimate duty to maintain a construction site in a reasonably safe condition.” Griggs v. Ryder, 625 So.2d 950, 951 (Fla. 1st DCA 1993); see also Lewis v. Sims Crane Serv., Inc., 498 So.2d 573, 574 (Fla. 3d DCA 1986); Atl. Coast Dev. Corp., 385 So.2d at 679 (“Nelacar, who was the owner and general contractor and actively supervised the daily construction operations, had a duty to keep its premises safe for all the workmen on the job and will be ultimately held liable for injuries occurring on its worksite.”).

The origin of this heightened duty of an owner/general contractor is the supreme court’s decision in Conklin.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cannon v. Fournier
57 So. 3d 875 (District Court of Appeal of Florida, 2011)
WORTHINGTON COMMUNITIES, INC. v. Mejia
28 So. 3d 79 (District Court of Appeal of Florida, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
28 So. 3d 79, 2009 Fla. App. LEXIS 19608, 2009 WL 4825111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/worthington-communities-inc-v-mejia-fladistctapp-2009.