Worth Construction Co. v. Department of Public Works

54 A.3d 628, 139 Conn. App. 65, 2012 WL 5357926, 2012 Conn. App. LEXIS 524
CourtConnecticut Appellate Court
DecidedNovember 6, 2012
DocketAC 33699
StatusPublished
Cited by3 cases

This text of 54 A.3d 628 (Worth Construction Co. v. Department of Public Works) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Worth Construction Co. v. Department of Public Works, 54 A.3d 628, 139 Conn. App. 65, 2012 WL 5357926, 2012 Conn. App. LEXIS 524 (Colo. Ct. App. 2012).

Opinion

Opinion

GRUENDEL, J.

The plaintiff, Worth Construction Company, Inc., appeals from the judgment of the trial court in favor of the defendant, the state department of public works. The plaintiff contends that the court erroneously found that the defendant did not waive its [67]*67claim to liquidated damages. We affirm the judgment of the trial court.

The relevant facts found by the court are as follows. On May 29, 2001, the plaintiff entered into a contract with the defendant to construct additions and renovations to Engelman Hall at Southern Connecticut State University for the sum of $33,497,050. The contract contained, inter alia, a liquidated damages clause that authorized the defendant to assess liquidated damages of $3000 per calendar day that the plaintiff failed to complete the project “within the [c]ontract [t]ime.” The term “contract time” is defined in the contract as “[t]he period of time allotted in the [c]ontract ... for [substantial [completion of the [w]ork . . . ,”1 Although the contract originally specified a period of 1068 calendar days for substantial completion, the parties subsequently executed a change order whereby an additional 394 calendar days were permitted. The plaintiff thus was required to attain substantial completion of the work within 1462 days, which period culminated on June 12, 2005. It is undisputed that the plaintiff reached substantial completion on August 25,2005, seventy-four days after June 12, 2005.

In July, 2007, the plaintiff commenced a breach of contract action against the defendant, alleging that the defendant failed to pay a balance of $1,434,068.87. In response, the defendant filed an answer, three special defenses and a three count counterclaim. Relevant to the present appeal is the first count, in which the defendant averred that because the plaintiff “caused the [p]roject to suffer a delay of [seventy-four] calendar days,” it was entitled to liquidated damages “at the daily rate of $3000 for a total of $222,000.” A bench trial [68]*68followed, at the conclusion of which the court found in favor of the defendant on both the plaintiffs complaint and the defendant’s counterclaim for liquidated damages. The court awarded the defendant $222,222 in liquidated damages, and this appeal followed.2

On appeal, the plaintiff challenges only the court’s award of liquidated damages.3 It claims that the court’s finding that the defendant did not waive its claim to said damages is clearly erroneous. We disagree.

It is well established that “[w]aiver is a question of fact.” AFSCME, Council 4, Local 704 v. Dept. of Public Health, 272 Conn. 617, 622,866 A.2d 582 (2005). Accordingly, our review of a trial court’s finding thereon is governed by the clearly erroneous standard. Lehn v. Marconi Builders, LLC, 120 Conn. App. 459, 465, 992 A.2d 1137 (2010). “A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. ... In making this determination, every reasonable presumption must be given in favor of the trial court’s ruling.” (Internal quotation marks omitted.) Gordon v. Tobias, 262 Conn. 844, 849, 817 A.2d 683 (2003).

The following additional facts are relevant to the plaintiffs claim. After the plaintiff belatedly attained substantial completion of the work specified in the contract, the defendant’s director of project management, Scott Jellison, notified the plaintiff via certified mail, on October 17, 2005, that “[p]er the [g]eneral [c]onditions [69]*69[s]ection 00700 of your contract, liquidated damages will be assessed for each day beyond the date given for substantial completion of the contract according to the contract time. Pursuant to the contract, [liquidated [d]amages will be assessed at the rate of $3000.00 per day for each day beyond the date for [substantial [completion. Pursuant to the contract . . . [the plaintiff] was required to attain [substantial [completion by June 12,2005. Substantial [c]ompletion was not attained until August 26, 2005. Since [the plaintiffs] contract obligations were not met, this is to notify you that the [defendant] may assess liquidated damages at the rate of $3000.00 for each day beyond June 12,2005, [through] August 26, 2005.”

On November 22, 2005, the defendant’s project manager, Randy Daigle, completed a “liquidated damage assessment field report” form. In so doing, Daigle miscalculated the period of time in which the plaintiff was to attain substantial performance. Although it is undisputed that the plaintiff was required to reach substantial completion of the work within 1462 days, Daigle erroneously indicated that the “total days allowed” was 1552. As a result of that mistake, Daigle concluded that because the plaintiff attained substantial completion within 1536 days, no days were “subject to liquidated damages.” He, thus, checked the box for “I do not recommend [liquidated damages to be assessed” in the project manager’s recommendation portion of the field report form. Kenneth Quimby, the defendant’s supervising project manager, approved Daigle’s field report on May 4, 2006. On that same date, Daigle submitted a “field evaluation report” that contained an identical miscalculation of the total days allowed for the plaintiff to attain substantial completion.

At trial, Daigle testified that he had miscalculated the total days allowed for substantial completion under the contract. He explained that he mistakenly included “the [70]*70punch list” period of ninety days in his calculations,4 which resulted in his calculation of 1552 days instead of 1462. Daigle further testified that his recommendation not to assess liquidated damages was predicated on that miscalculation, and he agreed that the calculations contained in Jellison’s October 17, 2005 letter to the plaintiff were accurate.

On appeal, the plaintiff asserts that the defendant “waived liquidated damages through the actions of . . . Daigle.” It is well established that waiver is the “intentional relinquishment or abandonment of a known right or privilege.” Johnson v. Zerbst, 304 U.S. 458, 464, 58 S. Ct. 1019, 82 L. Ed. 1461 (1938); C. R. Klewin Northeast, LLC v. Bridgeport, 282 Conn. 54, 86, 919 A.2d 1002 (2007). “Waiver is based upon a species of the principle of estoppel and where applicable it will be enforced as the estoppel would be enforced. . . . Estoppel has its roots in equity and stems from the voluntary conduct of a party whereby he is absolutely precluded, both at law and in equity, from asserting rights which might perhaps have otherwise existed . . . .” (Citation omitted; internal quotation marks omitted.) AFSCME, Council 4, Local 704 v. Dept. of Public Health, supra, 272 Conn. 623.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charter Oak Health Center, Inc. v. Barcelona
234 Conn. App. 758 (Connecticut Appellate Court, 2025)
Yuille v. Parnoff
206 A.3d 766 (Connecticut Appellate Court, 2019)
Walters v. Performant Recovery, Inc.
124 F. Supp. 3d 75 (D. Connecticut, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
54 A.3d 628, 139 Conn. App. 65, 2012 WL 5357926, 2012 Conn. App. LEXIS 524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/worth-construction-co-v-department-of-public-works-connappct-2012.