Work Zone Safety, Inc. v. Crest Hill Land Development LLC

2015 IL App (1st) 140088, 29 N.E.3d 520, 390 Ill. Dec. 588, 2015 Ill. App. LEXIS 153
CourtAppellate Court of Illinois
DecidedMarch 10, 2015
Docket1-14-0088
StatusUnpublished
Cited by3 cases

This text of 2015 IL App (1st) 140088 (Work Zone Safety, Inc. v. Crest Hill Land Development LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Work Zone Safety, Inc. v. Crest Hill Land Development LLC, 2015 IL App (1st) 140088, 29 N.E.3d 520, 390 Ill. Dec. 588, 2015 Ill. App. LEXIS 153 (Ill. Ct. App. 2015).

Opinion

2015 IL App (1st) 140088

SECOND DIVISION March 10, 2015

No. 1-14-0088

WORK ZONE SAFETY, INC., ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Cook County. v. ) ) No. 10 CH 38661 CREST HILL LAND DEVELOPMENT, L.L.C., ) ) Honorable ) Thomas R. Allen, Defendant-Appellee. ) Judge Presiding.

JUSTICE LIU delivered the judgment of the court, with opinion. Presiding Justice Simon and Justice Neville concurred in the judgment and opinion.

OPINION

¶1 Plaintiff, Work Zone Safety, Inc. (Work Zone), appeals an order of the circuit court

granting defendant, Crest Hill Land Development (CHLD), equitable relief on a judgment

confirming an arbitration award. The arbitration involved a dispute that arose out of CHLD’s

sale of certain wetlands property to Work Zone. The arbitrator concluded that CHLD was

obligated to repurchase the property at a specific price and awarded Work Zone damages in the

amount of said price—noting that the award "stands" if CHLD failed to repurchase the property.

The circuit court confirmed the award and entered a judgment against CHLD. Subsequently,

CHLD did not repurchase the property or appeal the judgment. Instead, CHLD moved to dismiss

the supplementary proceedings and asked for a “return of excess payment,” arguing that it was

inequitable for Work Zone to both retain the property and collect money damages. Work Zone

challenged the motion as "an improper collateral attack" on the judgment. Following a hearing,

the court ordered Work Zone to transfer the property to CHLD. This appeal followed. No. 1-14-0088

¶2 BACKGROUND

¶3 Work Zone and CHLD entered into a "Wetlands Escrow Agreement" (agreement) in

connection with CHLD’s sale of a 10.75-acre tract of vacant land to Work Zone. Pursuant to the

agreement, CHLD was required to complete certain mitigation work on 3.7 acres of wetlands on

the tract within a year of the closing. The agreement provided that if CHLD failed to perform the

work, Work Zone had a right to elect that CHLD repurchase the wetlands property (property) for

the price of $224,029.08. The agreement also provided that certain monies designated as the

"Wetlands Escrow Funds" would be used for the mitigation work. After CHLD failed to perform

the work, Work Zone demanded that CHLD repurchase the property. CHLD refused to buy back

the property, and Work Zone initiated arbitration proceedings.

¶4 In August 2010, the arbitrator ruled that Work Zone had properly exercised its

contractual right to demand CHLD’s repurchase of the property and that CHLD had failed to

satisfy its repurchase obligation under the agreement. Work Zone was awarded $224,029.08 in

damages, along with $25,000 in legal fees and $9,350 in administrative fees and expenses. The

arbitration award provided, specifically: “If [CHLD] fails or refuses to accomplish its role as

purchaser of the Returned Property, the Award of $224,029.08 in favor of [Work Zone] stands."

¶5 In September 2010, after CHLD failed to repurchase the property, Work Zone filed a

complaint in the circuit court to confirm the arbitration award. CHLD filed an answer and a

counterclaim to vacate the award. On March 11, 2011, the court confirmed the arbitration award

and entered judgment for Work Zone in the amount of $249,029.08, based on $224,029.08 in

damages and $25,000 in legal fees. The court later entered, on April 14, 2011, a corrected order

for a judgment amount of $258,379.08, which included $9,350 in administrative fees and

expenses related to the arbitration. In an effort to collect the judgment amount, Work Zone

2 No. 1-14-0088

issued citations to discover assets to CHLD and other third parties. Despite CHLD's failure to

respond to the citations, Work Zone recovered approximately $105,000 of the judgment amount

through supplementary proceedings.

¶6 In May 2011, in response to an emergency motion filed by CHLD, 1 the circuit court

granted CHLD another opportunity to repurchase the property. The court ordered CHLD to

"close on the sale of the property" in accordance with the agreement and the arbitration award

"on or before June 6, 2011 for a price of $268,379 minus offsets for any amounts collected by

Work Zone in supplemental proceedings." 2 The court further stated: "In the event that the

transaction does not occur on 6-6-11, for reasons within the control of [CHLD], the 3-11-11 & 4-

14-11 orders shall stand." CHLD failed to purchase the property by the June 6 deadline, and

Work Zone continued to seek enforcement of the judgment.

¶7 Twenty-two months later, on March 5, 2013, CHLD filed a motion to dismiss the

citations to discover assets and requested an "Order of Satisfaction with Release of Lien and

Return of Excess Payment" (motion to dismiss). 3 CHLD argued that Work Zone's retention of

the wetlands property and recovery of money damages constituted a windfall and, therefore, was

inequitable. Relying on theories of unjust enrichment or, alternatively, equitable set off, CHLD

asked the circuit court to order the disgorgement of the alleged excess recovery that Work Zone

had obtained in supplementary proceedings. Three days later, on March 8, CHLD filed a motion

for preliminary injunction, seeking to enjoin Work Zone from taking any further action to collect

1 While CHLD's emergency motion is not contained in the record before us, there is no need to supplement the record because neither party has raised an issue on appeal related to the motion itself. 2 The record is silent as to why a discrepancy exists between the $268,379 price in the May 13 order and the $258,379.08 judgment in the April 14 order; however, it has no bearing on our disposition of the case. 3 We note that CHLD's motion to dismiss was filed in the same chancery action in which the arbitration award was confirmed, but a different judge presided over the proceedings related to the motion to dismiss. 3 No. 1-14-0088

the judgment until the circuit court ruled on CHLD's motion to dismiss. For the first time, in its

motion for preliminary injunction, CHLD identified section 12-183(b) of the Code of Civil

Procedure (Code) (735 ILCS 5/12-183(b) (West 2012)) as the basis for its request for an order of

satisfaction and release of lien.

¶8 The circuit court ultimately ruled in favor of CHLD and determined that equitable relief

was warranted. In reaching this decision, the court explained that although Work Zone was

"entitled to its judgment of $258,579.08 with running post judgment interest accruing," it could

not also retain title to the property. The matter was then continued to allow the parties to discuss

a possible remedy. On October 2, 2013, the court entered a written order awarding CHLD title to

the wetlands property, and stating as follows:

"By and large, this Court has already expressed that equitable relief for

[CHLD] is warranted. (Order, May 30, 2013). For Work Zone to enforce

the remaining balance of the judgment against [CHLD] while maintaining

title of the 3.6 acre wetlands goes beyond what the Court finds to be fair

and equitable. *** Work Zone is entitled to such remaining balance of the

judgment reflected in that accounting, plus any interest accrued from the

date of that accounting until the date of this Order. Accordingly, [CHLD]

is entitled to the title of the Returned Property as valued per the Wetlands

Escrow Agreement in the amount of $224,029.08.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northbrook Bank & Trust Company v. Abbas
2018 IL App (1st) 162972 (Appellate Court of Illinois, 2018)
Work Zone Safety, Inc. v. Crest Hill Land Development LLC
2015 IL App (1st) 140088 (Appellate Court of Illinois, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2015 IL App (1st) 140088, 29 N.E.3d 520, 390 Ill. Dec. 588, 2015 Ill. App. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/work-zone-safety-inc-v-crest-hill-land-development-llc-illappct-2015.