Woodstock Solar Project, L.L.C. v. Rush Twp. Bd. of Zoning Appeals

2025 Ohio 567
CourtOhio Court of Appeals
DecidedFebruary 21, 2025
Docket2024-CA-24
StatusPublished

This text of 2025 Ohio 567 (Woodstock Solar Project, L.L.C. v. Rush Twp. Bd. of Zoning Appeals) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodstock Solar Project, L.L.C. v. Rush Twp. Bd. of Zoning Appeals, 2025 Ohio 567 (Ohio Ct. App. 2025).

Opinion

[Cite as Woodstock Solar Project, L.L.C. v. Rush Twp. Bd. of Zoning Appeals, 2025-Ohio-567.]

IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT CHAMPAIGN COUNTY

WOODSTOCK SOLAR PROJECT, LLC : : Appellee : C.A. No. 2024-CA-24 : v. : Trial Court Case No. 2022 CV 088 : RUSH TOWNSHIP BOARD OF : (Civil Appeal from Common Pleas ZONING APPEALS : Court) : Appellants :

...........

OPINION

Rendered on February 21, 2025

JACK A. VAN KLEY & JANE A. NAPIER, Attorneys for Appellants

ANNE MARIE SFERRA & KARA HERRNSTEIN, Attorneys for Appellee

.............

EPLEY, P.J.

{¶ 1} Rush Township zoning inspector Bradley Herron appeals from a judgment of

the Champaign County Court of Common Pleas, which found a stop work order he had

issued to be invalid and vacated the order. For the reasons that follow, the judgment of -2-

the trial court will be reversed.

I. Facts and Procedural History

{¶ 2} In 2018, Woodstock Solar Project, LLC (“Woodstock”) began to develop a

solar energy project in Rush Township, Champaign County. To build the facility,

Woodstock entered into lease agreements with local landowners. In all, Woodstock

acquired 500 acres of land, and of that, solar panels will be installed on 209 acres.

{¶ 3} Once built, the project will contain numerous solar panels placed on top of a

metal or aluminum framework. The panels will be connected to each other with wiring

which will transmit electricity to a Dayton Power & Light substation directly across the

street. From there, the electricity will be delivered into a larger transmission system

managed by the PJM regional wholesale electric grid. This regional transmission

organization is responsible for powering about a dozen states ranging from Illinois in the

west to New Jersey in the east. When completed, the Woodstock Solar Project will have

a capacity of 40 megawatts – enough energy to power approximately 6,700 homes.

{¶ 4} In March 2022, Woodstock applied for a conditional use permit to use the

land as a “Public Service Facility” or, in the alternative, as a “Light Manufacturing Facility”

as defined in the Rush Township Zoning Resolution. On March 30, 2022, Herron, the

township zoning inspector, rejected the application for a conditional use permit, reasoning

that the project would not fit within the parameters of a conditional use in Rush Township

and therefore was ineligible to be considered by the Rush Township Board of Zoning

Appeals (“BZA”).

{¶ 5} Woodstock filed an appeal of Herron’s determination with the Rush Township -3-

BZA and, after a hearing on the matter, the BZA voted to reject Woodstock’s appeal.

Upon receipt of a short, written decision from the BZA, Woodstock appealed to the

Champaign County Court of Common Pleas pursuant to R.C. 2506.01. The trial court

reversed, finding that the decision of the BZA was “not supported by substantial, reliable,

and probative evidence. Instead, there is substantial, reliable, and probative evidence

from which to conclude that Woodstock is a public utility and therefore exempt from the

Rush Township Zoning Resolution.” Trial Court Decision at 23. In June 2023, we affirmed

the trial court’s decision in Woodstock Solar Project, LLC v. Rush Twp. Bd. of Zoning

Appeals, 2023-Ohio-2215 (2d Dist.), and the Ohio Supreme Court declined jurisdiction.

{¶ 6} During the pendency of that case, however, Governor DeWine signed H.B.

501, a bill that amended R.C. 519.213(B) to give township trustees and BZAs greater

authority to regulate solar facilities, especially “small solar facilities,” which were

designated as those with a single interconnection to the electrical grid and a power

capacity of less than 50 megawatts.

{¶ 7} On July 3, 2023, Rush Township amended Sections 564 and 1237-60 of its

zoning code to allow “accessory” solar facilities (those designed to supply electricity for

on-site usage) but prohibited “production” solar facilities (those below 50 megawatts but

designed to supply electricity to the electrical grid at-large). The changes became

effective on August 2, 2023.

{¶ 8} On June 20, 2024, the Rush Township zoning inspector issued a notice of

zoning violation (also known as a stop work order) to Woodstock. The notice alleged that

the project, if constructed, would be a “Principal Solar Energy Production Facility” as -4-

defined by Rush Township Zoning Ordinance Section 1237-60, which violates Section

564’s prohibition of those in the township. It further stated that the township zoning

ordinance had banned industrial solar facilities since July 2022 and noted that in April

2023, the legislature had amended R.C. 519.213 to authorize townships to regulate solar

facilities smaller than 50 megawatts. “Accordingly, the language of the Zoning Ordinance

has been effective to prohibit the construction of the Project in Rush Township since that

time. . . . Consequently, pursuant to Section 1000 of the Zoning Ordinance, I hereby order

Woodstock Solar to discontinue and refrain from any further field activities for the Project.”

The notice did not contain any information regarding Woodstock’s right to appeal.

{¶ 9} On July 2, 2024, Woodstock mailed and e-mailed a response to the notice of

violation in the form of a letter; the Rush Township board of trustees and fiscal officer

were copied as recipients of the letter. Woodstock’s response argued that the notice of

violation was “invalid, unlawful, and unenforceable” because of the common pleas court’s

previous judgment, which had determined that the project was a public utility. Further, the

letter argued that retroactive application of the zoning ordinance violated Woodstock’s

right to due process of law, i.e., enforcement of the zoning ordinance infringed on its

vested property rights. Woodstock demanded that the stop work order be withdrawn and

that the township govern itself according to the common pleas court’s January 25, 2023

judgment. Woodstock stated that it was “prepared to pursue all available remedies and

enforce its rights under the Court Order.” Woodstock did not appeal the order to the BZA.

{¶ 10} Several weeks later, on July 31, 2024, Woodstock filed a contempt motion

in the Champaign County Court of Common Pleas asking the BZA and the zoning -5-

inspector to show cause why they should not be held in contempt for failing to comply

with the trial court’s 2023 decision finding that the proposed Woodstock facility was a

public utility and exempt from zoning regulations. It also sought recission of the stop work

order, statutory penalties under R.C. 2705.05(A), and to “reopen [the prior proceedings]

for the purpose of enjoining further interference with the solar project.” Sept. 24, 2024

Decision. On September 24, the common pleas court issued a journal entry finding stop

work to be invalid and ordering the Rush Township zoning inspector to vacate the order.

Id.

{¶ 11} The zoning inspector, Herron, has appealed, raising five assignments of

error. We will address them in a manner that facilitates our analysis.

II. Administrative Appeals

{¶ 12} In his first and second assignments of error, Herron makes several

arguments, including that the trial court erred when it held that the stop work order was

inconsistent with its 2023 entry, that Woodstock should have first filed an appeal with the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boddie v. Connecticut
401 U.S. 371 (Supreme Court, 1971)
Mathews v. Eldridge
424 U.S. 319 (Supreme Court, 1976)
Stewart v. Lockland School Dist. Bd. of Edn. (Slip Opinion)
2015 Ohio 3839 (Ohio Supreme Court, 2015)
Mega Outdoor, L.L.C. v. City of Dayton
878 N.E.2d 683 (Ohio Court of Appeals, 2007)
Ferguson v. State (Slip Opinion)
2017 Ohio 7844 (Ohio Supreme Court, 2017)
Noernberg v. City of Brook Park
406 N.E.2d 1095 (Ohio Supreme Court, 1980)
State ex rel. Nicodemus v. Industrial Commission
448 N.E.2d 1360 (Ohio Supreme Court, 1983)
Willow Grove v. Olmstead Twp. Bd. of Zoning Appeals
2022 Ohio 4364 (Ohio Supreme Court, 2022)
Piqua Store & Lock, L.L.C. v. Miami Cty. Bd. of Zoning Appeals
2023 Ohio 1403 (Ohio Court of Appeals, 2023)
Dayton v. Siff
2023 Ohio 4685 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ohio 567, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodstock-solar-project-llc-v-rush-twp-bd-of-zoning-appeals-ohioctapp-2025.