Woodstock Solar Project, L.L.C. v. Rush Twp. Bd. of Zoning Appeals

2025 Ohio 567
Ohio Court of Appeals·Decided February 21, 2025·No. 2024-CA-24·Published

Opinion

[Cite as Woodstock Solar Project, L.L.C. v. Rush Twp. Bd. of Zoning Appeals, 2025-Ohio-567.]

IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT CHAMPAIGN COUNTY

WOODSTOCK SOLAR PROJECT, LLC :

:

Appellee : C.A. No. 2024-CA-24 :

v. : Trial Court Case No. 2022 CV 088 :

RUSH TOWNSHIP BOARD OF : (Civil Appeal from Common Pleas ZONING APPEALS : Court)

:

Appellants :

...........

OPINION

Rendered on February 21, 2025 ...........

JACK A. VAN KLEY & JANE A. NAPIER, Attorneys for Appellants ANNE MARIE SFERRA & KARA HERRNSTEIN, Attorneys for Appellee .............

EPLEY, P.J.

{¶ 1} Rush Township zoning inspector Bradley Herron appeals from a judgment of the Champaign County Court of Common Pleas, which found a stop work order he had issued to be invalid and vacated the order. For the reasons that follow, the judgment of

the trial court will be reversed.

I. Facts and Procedural History

{¶ 2} In 2018, Woodstock Solar Project, LLC (“Woodstock”) began to develop a solar energy project in Rush Township, Champaign County. To build the facility, Woodstock entered into lease agreements with local landowners. In all, Woodstock acquired 500 acres of land, and of that, solar panels will be installed on 209 acres.

{¶ 3} Once built, the project will contain numerous solar panels placed on top of a metal or aluminum framework. The panels will be connected to each other with wiring which will transmit electricity to a Dayton Power & Light substation directly across the street. From there, the electricity will be delivered into a larger transmission system managed by the PJM regional wholesale electric grid. This regional transmission organization is responsible for powering about a dozen states ranging from Illinois in the west to New Jersey in the east. When completed, the Woodstock Solar Project will have a capacity of 40 megawatts – enough energy to power approximately 6,700 homes.

{¶ 4} In March 2022, Woodstock applied for a conditional use permit to use the land as a “Public Service Facility” or, in the alternative, as a “Light Manufacturing Facility” as defined in the Rush Township Zoning Resolution. On March 30, 2022, Herron, the township zoning inspector, rejected the application for a conditional use permit, reasoning that the project would not fit within the parameters of a conditional use in Rush Township and therefore was ineligible to be considered by the Rush Township Board of Zoning Appeals (“BZA”).

{¶ 5} Woodstock filed an appeal of Herron’s determination with the Rush Township

BZA and, after a hearing on the matter, the BZA voted to reject Woodstock’s appeal. Upon receipt of a short, written decision from the BZA, Woodstock appealed to the Champaign County Court of Common Pleas pursuant to R.C. 2506.01. The trial court reversed, finding that the decision of the BZA was “not supported by substantial, reliable, and probative evidence. Instead, there is substantial, reliable, and probative evidence from which to conclude that Woodstock is a public utility and therefore exempt from the Rush Township Zoning Resolution.” Trial Court Decision at 23. In June 2023, we affirmed the trial court’s decision in Woodstock Solar Project, LLC v. Rush Twp. Bd. of Zoning Appeals, 2023-Ohio-2215 (2d Dist.), and the Ohio Supreme Court declined jurisdiction.

{¶ 6} During the pendency of that case, however, Governor DeWine signed H.B.

501, a bill that amended R.C. 519.213(B) to give township trustees and BZAs greater authority to regulate solar facilities, especially “small solar facilities,” which were designated as those with a single interconnection to the electrical grid and a power capacity of less than 50 megawatts.

{¶ 7} On July 3, 2023, Rush Township amended Sections 564 and 1237-60 of its zoning code to allow “accessory” solar facilities (those designed to supply electricity for on-site usage) but prohibited “production” solar facilities (those below 50 megawatts but designed to supply electricity to the electrical grid at-large). The changes became effective on August 2, 2023.

{¶ 8} On June 20, 2024, the Rush Township zoning inspector issued a notice of zoning violation (also known as a stop work order) to Woodstock. The notice alleged that the project, if constructed, would be a “Principal Solar Energy Production Facility” as

defined by Rush Township Zoning Ordinance Section 1237-60, which violates Section 564’s prohibition of those in the township. It further stated that the township zoning ordinance had banned industrial solar facilities since July 2022 and noted that in April 2023, the legislature had amended R.C. 519.213 to authorize townships to regulate solar facilities smaller than 50 megawatts. “Accordingly, the language of the Zoning Ordinance has been effective to prohibit the construction of the Project in Rush Township since that time. . . . Consequently, pursuant to Section 1000 of the Zoning Ordinance, I hereby order Woodstock Solar to discontinue and refrain from any further field activities for the Project.” The notice did not contain any information regarding Woodstock’s right to appeal.

{¶ 9} On July 2, 2024, Woodstock mailed and e-mailed a response to the notice of violation in the form of a letter; the Rush Township board of trustees and fiscal officer were copied as recipients of the letter. Woodstock’s response argued that the notice of violation was “invalid, unlawful, and unenforceable” because of the common pleas court’s previous judgment, which had determined that the project was a public utility. Further, the letter argued that retroactive application of the zoning ordinance violated Woodstock’s right to due process of law, i.e., enforcement of the zoning ordinance infringed on its vested property rights. Woodstock demanded that the stop work order be withdrawn and that the township govern itself according to the common pleas court’s January 25, 2023 judgment. Woodstock stated that it was “prepared to pursue all available remedies and enforce its rights under the Court Order.” Woodstock did not appeal the order to the BZA.

{¶ 10} Several weeks later, on July 31, 2024, Woodstock filed a contempt motion in the Champaign County Court of Common Pleas asking the BZA and the zoning

inspector to show cause why they should not be held in contempt for failing to comply with the trial court’s 2023 decision finding that the proposed Woodstock facility was a public utility and exempt from zoning regulations. It also sought recission of the stop work order, statutory penalties under R.C. 2705.05(A), and to “reopen [the prior proceedings] for the purpose of enjoining further interference with the solar project.” Sept. 24, 2024 Decision. On September 24, the common pleas court issued a journal entry finding stop work to be invalid and ordering the Rush Township zoning inspector to vacate the order. Id.

{¶ 11} The zoning inspector, Herron, has appealed, raising five assignments of error. We will address them in a manner that facilitates our analysis.

II. Administrative Appeals

{¶ 12} In his first and second assignments of error, Herron makes several arguments, including that the trial court erred when it held that the stop work order was inconsistent with its 2023 entry, that Woodstock should have first filed an appeal with the BZA before appealing to the trial court, and that the trial court erred when it adjudicated Woodstock’s “vested right” claim. We begin our analysis with the question of whether Woodstock should have gone directly to the common pleas court to address the stop work order or, instead, appealed to the BZA.

{¶ 13} According to R.C. 519.14, a BZA may “[h]ear and decide appeals where it is alleged there is error in any order, requirement, decision, or determination made by an administrative official in the enforcement of sections 519.02 to 519.25 of the Revised Code, or of any resolution adopted pursuant thereto.” This recourse is also codified in

Free access — add to your briefcase to read the full text and ask questions with AI

Woodstock Solar Project, L.L.C. v. Rush Twp. Bd. of Zoning Appeals, 2025 Ohio 567 (Ohio Ct. App. 2025).

2025 Ohio 567 (Woodstock Solar Project, L.L.C. v. Rush Twp. Bd. of Zoning Appeals) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Boddie v. Connecticut
401 U.S. 371 (Supreme Court, 1971)
Mathews v. Eldridge
424 U.S. 319 (Supreme Court, 1976)
Stewart v. Lockland School Dist. Bd. of Edn. (Slip Opinion)
2015 Ohio 3839 (Ohio Supreme Court, 2015)
Mega Outdoor, L.L.C. v. City of Dayton
878 N.E.2d 683 (Ohio Court of Appeals, 2007)
Ferguson v. State (Slip Opinion)
2017 Ohio 7844 (Ohio Supreme Court, 2017)
Noernberg v. City of Brook Park
406 N.E.2d 1095 (Ohio Supreme Court, 1980)
State ex rel. Nicodemus v. Industrial Commission
448 N.E.2d 1360 (Ohio Supreme Court, 1983)
Willow Grove v. Olmstead Twp. Bd. of Zoning Appeals
2022 Ohio 4364 (Ohio Supreme Court, 2022)
Piqua Store & Lock, L.L.C. v. Miami Cty. Bd. of Zoning Appeals
2023 Ohio 1403 (Ohio Court of Appeals, 2023)
Dayton v. Siff
2023 Ohio 4685 (Ohio Court of Appeals, 2023)