Woodall v. Citizens Banking Co.

503 N.E.2d 427, 1987 Ind. App. LEXIS 2313
CourtIndiana Court of Appeals
DecidedJanuary 29, 1987
Docket80A04-8601-CV-18
StatusPublished
Cited by5 cases

This text of 503 N.E.2d 427 (Woodall v. Citizens Banking Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Woodall v. Citizens Banking Co., 503 N.E.2d 427, 1987 Ind. App. LEXIS 2313 (Ind. Ct. App. 1987).

Opinion

YOUNG, Judge.

John and Janet Woodall appeal the Tip-ton Circuit Court's entries of partial and final summary judgment in favor of Citizens Banking Company. The only issue raised by this appeal is whether Citizens, as a mortgagee who disbursed the proceeds of a construction loan made to the Woodalls, had a duty to protect the Woodalls from mechanics liens. 1 We affirm.

On October 25, 1978, John and Janet Woodall executed a note and mortgage in favor of Citizens Banking Company. The mortgaged property was a residence that was in the process of being constructed by Ren Corporation under the supervision of Johnson, Ritchart & Associates, Inc., an architectural firm. In the mortgage the Woodalls agreed to "warrant and defend generally the title to the property against all claims and demands" and to "promptly discharge any lien which [had] priority over [the] Mortgage." 2 In addition to the note and mortgage, the Woodalls executed a Loan Settlement Statement which provided that the funds were to be disbursed by Citizens "as construction progresses in *428 strict accordance with plans and specifications and approved by Johnson, Ritchart & Associates, Inc." The Woodalls signed the statement and thereby acknowledged its receipt, agreed to its correctness and authorized and ratified the disbursement of the funds as it provided. Citizens required that the loan proceeds and $35,000.00 of the Woodalls' personal funds be deposited with it to insure that sufficient funds were available to pay for the construction. A 5%-10% retainage fund was also created.

Ren made periodic requests to the architect for payment on an Application and Certificate for Payment Form. Each certificate allegedly contained the following statement:

The undersigned Contractor certifies that the Work covered by this application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by him for work for which previous certificates for Payment were issued and payments received from the Owner, and that the current payment shown herein is now due.
Contractor:
By:
In accordance with the Contract and this Application for Payment the Contractor is entitled to payment in the amount shown above.
Architect:
By:

Ren's twelve Application and Certificate for Payment Forms were forwarded to Citizens. Citizens issued two checks payable only to Ren on the first application. This was done at closing and approved by the Woodalls in the Loan Settlement Statement. On the next eight applications, checks were issued payable to the Woodalls and Ren. On applications ten and eleven, Citizens issued checks payable only to the Woodalls but with the following endorsement on the back:

Pay to the order of
Contractor For Deposit Only
Mortgagor
Mortgagor

During the course of construction, one lien waiver was obtained from Ren 3 Additionally, a Citizens official periodically and randomly checked with subcontractors to verify that they had received payment from Ren. 4 Between July 9, 1979 and July 17, 1979, however, the Woodalls became concerned that Ren would not be able to complete the residence with the funds remaining on deposit with Citizens. The Woodalls refused to endorse the check issued for Ren's ninth Application and Certificate for Payment. Upon the architect's and Citi zens' alleged assurances that the construction loan proceeds would be disbursed only pursuant to the architect's approval and that the construction bills were paid, the Woodalls endorsed the check. They later, however, refused to endorse the check issued by Citizens for Ren's eleventh Application and Certificate for Payment. Citi zens refused to issue a check for Ren's twelfth Application and Certificate for Payment, which had been approved by the architect, upon learning that the balance due Ren's materialmen exceeded the remaining balance in the Woodalls' Construction Loan *429 Fund. 5 Ren stopped work as a result of Citizens' refusal to issue the check. Ren filed a mechanics lien for the amount of its unpaid bills. In addition, seven of Ren's materialmen filed mechanics liens. 6

Three of the materialmen filed suit to foreclose their mechanics liens and the Woodalls filed a third-party complaint against Citizens, alleging that Citizens had a duty to protect them against mechanics liens through either an express agreement, custom and practice, or as a result of their relationship. Citizens defended on the grounds that the language in the mortgage negated any duty on its part and, after extensive discovery, moved for summary judgment. On February 25, 1983, the trial court granted partial summary judgment in favor of Citizens, listing two remaining questions of fact. These questions were as follows:

1. Whether local custom and practice in Madison County, Indiana imposed a duty upon CITIZENS BANKING COMPANY to protect WOODALLS and their Free Road property from mechanics Hens.
2. Whether any such duty arising from local custom and practice can be rendered inapplicable because of the course of the parties' dealings, the agreement of the parties, and of the representations of the mortgagor to the mortgagee.

On July 22, 1985, the trial court entered final summary judgment in favor of Citi zens.

The Woodalls primarily rely upon Prudential Ins. Co., Etc. v. Executive Estates (1977), 174 Ind.App. 674, 369 N.E.2d 1117, for the proposition that Citizens had a duty to protect them and their property from mechanics liens. In Prudential, the See-ond District held that Prudential, the mortgagor, had a duty to protect Executive Estates, its mortgagee, from mechanics liens. The court found that the duty arose from the express agreement of the parties, the custom and practice in the local real estate community, and the relationship of the parties. Prudential, however, is distinguishable from this case on all three points.

In Prudential, the mortgagee, specifically told the mortgagor, who was concerned about mechanics liens, that it would take care of the liens at closing. While the Woodalls argue that Citizens expressly agreed to protect them from mechanics liens, they state in their brief that the facts "indicate overwhelming support for the conclusion that ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peoples Bank & Trust Co. v. Price
714 N.E.2d 712 (Indiana Court of Appeals, 1999)
Crum v. AVCO Financial Services of Indianapolis, Inc.
552 N.E.2d 823 (Indiana Court of Appeals, 1990)
Woodall v. Citizens Banking Co.
507 N.E.2d 999 (Indiana Court of Appeals, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
503 N.E.2d 427, 1987 Ind. App. LEXIS 2313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/woodall-v-citizens-banking-co-indctapp-1987.