Wonderland Greyhound Park, Inc. v. Autotote Systems, Inc.

144 F. Supp. 2d 25, 2001 U.S. Dist. LEXIS 6976, 2001 WL 539457
CourtDistrict Court, D. Massachusetts
DecidedMay 10, 2001
DocketCiv.A. 00-12077-JLT
StatusPublished
Cited by1 cases

This text of 144 F. Supp. 2d 25 (Wonderland Greyhound Park, Inc. v. Autotote Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wonderland Greyhound Park, Inc. v. Autotote Systems, Inc., 144 F. Supp. 2d 25, 2001 U.S. Dist. LEXIS 6976, 2001 WL 539457 (D. Mass. 2001).

Opinion

MEMORANDUM

TAURO, District Judge.

BACKGROUND

Plaintiffs, The Westwood Group, Inc. and Wonderland Greyhound Park, Inc. (collectively ‘Wonderland”), operate a greyhound race track in Massachusetts. Defendant, Autotote Systems, Inc. (“Auto-tote”), provides totalisator services to race tracks. A totalisator registers bets and computes the payoffs in pari-mutuel betting.

On or about August 30, 1991, Wonderland contracted (the “Contract”) with Au-totote for totalisator services at Wonderland’s greyhound race track. The Parties executed three Amendments to the Contract. Only the Third Amendment is at issue here, but the first two amendments provide a context for the Parties’ dealings.

The First Amendment occurred on or about April 2, 1992. It granted Autotote exclusive rights to provide on-track totali-sator services, including intra-state and inter-state simulcast racing events. This First Amendment also extended the Contract’s term for one additional year. Auto-tote agreed to pay one million dollars to Wonderland in consideration for these exclusive rights. Autotote claims that this milhon-dollar payment was an advance that Wonderland requested be characterized as an exclusive-rights purchase. The Second Amendment, which occurred on or about October 2, 1995, extended the term of services for an additional year.

The Parties executed a Third Amendment on or about February 1, 1999, extending services on live races and intrastate and inter-state simulcast races for an additional seven-year term (ending on September 25, 2005). This Amendment also required: (1) Autotote to provide upgraded self-service machines and customer- *27 tracking software; and (2) Wonderland to pay a weekly fee of $1,373.63 for video equipment rental over seven years, total* ing $500,000.

Autotote failed to provide the updated self-service equipment and customer-tracking software under the Third Amendment. Wonderland served a notice of default on Autotote. Autotote failed to cure the default and Plaintiff terminated the contract effective June 13, 1999. Autotote then commenced arbitration alleging that Wonderland improperly terminated the contract. 1

After completing depositions, the Parties appeared before an Arbitrator with the American Arbitration Association, as the Contract provided. On August 27, 2000, the Arbitrator issued an Award, finding that “Autotote’s failure to supply the desired additions was a material breach of the 1991 contract as extended and amended.” 2 But the Arbitrator also determined that the Contract was divisible and accelerated the $1,373.63 weekly equipment-rental payments that Wonderland was to pay Autotote over the next five years. That decision’s net effect was to deem Wonderland as immediately owing Auto-tote almost $500,000, rather than the agreed upon weekly payout over seven years.

At issue is Wonderland’s Motion to Vacate the Arbitrator’s determination requiring Wonderland to pay Autotote a lump-sum amount for the money owed on the seven-year video-equipment rental, rather than installments as set forth under the Third Amendment. Wonderland alleges that, in negotiating the Third Amendment, the Parties expressly bargained for and agreed that the seven year, weekly installment amount was a non-divisible element of an “entire” Contract. Wonderland further states that since Autotote’s counsel drafted and produced the original Contract, and each Amendment and Extension, any ambiguity should be interpreted against Autotote. Wonderland states that Autotote insisted on the “Limitation of Remedies” clause, which Wonderland alleges the Arbitrator ignored. 3

Wonderland claims that the Arbitrator ignored the plain language of the contract, specifically the Limitation of Remedies provision and the agreed remedy for breach clause. Wonderland further argues that the Award should be vacated because the Arbitrator acted in manifest disregard of the law. Wonderland states that by requiring an accelerated payment in a lump-sum amount now, Autotote will be in a better position than called for under the Amendment, i.e. the present use of almost $500,000 that it otherwise would have received piecemeal over a seven year period.

The Arbitrator ultimately directed Wonderland to pay Autotote the net principal sum of $477,790.84 before September 27, 2000, with interest accruing at 12% per annum, compounded monthly, commencing on September 28, 2000. Wonderland applied to the Arbitrator to modify the Award from a lump-sum payment to the *28 seven-year weekly payment plan outlined in the Contract. In a two-page Memorandum issued on November 1, 2000, the Arbitrator denied Wonderland’s Application for Reconsideration/Modification and upheld the lump-sum Award.

In this court, Autotote argues that Wonderland’s right to challenge or modify that Award has been exhausted, and the Award is final and binding. Because Wonderland refused to pay the Award, Autotote seeks a judgment from this court confirming the Award.

DISCUSSION

In reviewing arbitration awards, a district court’s “review ... must be extremely narrow and exceedingly deferential.” 4 This review is “highly deferential because the parties have contracted to have disputes settled by an arbitrator and thus, it is the arbitrator’s view of the facts and of the meaning of the contract that they have agreed to accept.” 5 Furthermore, “[w]hile the arbitrator’s award must draw its essence from the contract, as long as the arbitrator is even arguably construing or applying the contract and acting within the scope of his authority, that a court is convinced he committed serious error does not suffice to overturn his decision.” 6

An arbitration decision can be vacated either if federal statutory authority -provides for it, or if the arbitrator acted in manifest disregard of the law. 7 Federal statutory law explicitly provides that a district court can vacate the award “[wjhere the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.” 8

Alternatively, a district court can vacate an arbitration decision if “[b]eyond the specific grounds enumerated in § 10 ... an award is contrary to the plain language of the [contract] and ... if it was made in manifest disregard of the law.” 9 The issue before this court, therefore, is whether the Arbitrator acted in manifest disregard of the law or exceeded his authority.

In this Circuit, the determining test is:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
144 F. Supp. 2d 25, 2001 U.S. Dist. LEXIS 6976, 2001 WL 539457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wonderland-greyhound-park-inc-v-autotote-systems-inc-mad-2001.