Won Suk Lee v. Holyfield Construction, Inc.

93 So. 3d 868, 2012 WL 2335994, 2012 La. App. LEXIS 875
CourtLouisiana Court of Appeal
DecidedJune 20, 2012
DocketNo. 47,204-CA
StatusPublished
Cited by6 cases

This text of 93 So. 3d 868 (Won Suk Lee v. Holyfield Construction, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Won Suk Lee v. Holyfield Construction, Inc., 93 So. 3d 868, 2012 WL 2335994, 2012 La. App. LEXIS 875 (La. Ct. App. 2012).

Opinion

MOORE, J.

| ]Dr. and Mrs. Won Suk Lee appeal a judgment based on a jury verdict that awarded them $250,000 in repair or replacement cost under the New Home Warranty Act (“NHWA”), La. R.S. 9:3141-3150, less $83,338 for the balance due on the building contract, and denied their claim for delay damages for late completion of the house. The Lees contest one evidentiary ruling of the district court and the jury’s failure to award delay damages. For the reasons expressed, we affirm.

Factual and Procedural Background

Dr. Lee is an OB-GYN in Monroe; his wife, Kathryn, is a chemist and now a full-time homemaker. Largely on the strength of Joe Holyfield’s (hereinafter “Holyfield”) reputation for building doctors’ homes, in December 2005 the Lees contracted with Holyfield to build them a custom 5,484 sq. ft. (7,600 sq. ft. under the roof) house on an 8-acre tract on Heron Trail in West Monroe. The contract price was $1,132,114 and the completion date was to be November 30, 2006.

Ms. Lee was intensely interested in the construction process, usually visiting the site daily and prompting many change orders. With these changes, the final price rose to about $1.3 million. The house was not ready on November 30, 2006; Holy-field ascribed the delay not to the plethora of change orders but to abnormally wet weather in early 2006.

The Lees moved in on April 4, 2007. Within weeks Ms. Lee began to notice a stale, musty odor, chiefly in the master bath and closet. By early July she spotted “strings of green stuff,” which she reported to Holyfield; two of his workers came out and sprayed the area with bleach. This, 12however, did not abate the problem, and Ms. Lee complained that Holyfield avoided her calls and generally stalled for most of July. The Lees hired an engineer, a home inspector and an industrial hygienist who turned up a host of deficiencies: they compiled a punch list with 44 complaints. Concerned about the possible effect of mold on Ms. Lee and their two daughters, the Lees moved out on September 14, 2007. The house has been vacant ever since.

The Lees filed this suit under NHWA in November 2007. They alleged that the moisture and mold problem, plus myriad other defects, made the house uninhabitable. Holyfield conceded that various items were indeed defective, but maintained that he could repair them if only the Lees let him.

The case proceeded to a six-day jury trial in November 2010. The evidence was extremely detailed, as the Lees, Holyfield and their respective experts discussed all 44 items on the punch list. The Lees’ expert contractor, Warner, testified that repairs would cost at least $525,000; Holy-field and his expert environmental engineer, Dowling, estimated that repairs and mold remediation would not exceed $47,500. The Lees admitted that they never paid Holyfield his final $83,338 draw. Dr. Lee testified that at one point he asked Holyfield to buy back the house for $1.3 million, if the problems could be so easily addressed, but he declined; Holy-field conceded at trial that he could not afford to buy the houses he built.

Is Overview of Trial Evidence

Because the issue on appeal is an evi-dentiary ruling, this court will not belabor the profuse evidence covering all aspects of the trial. The only issue germane to the appeal is the brick. Prior to construction, Holyfield drove Ms. Lee around to various buildings in Monroe, showing her exterior brick. Their testimony differed, but Ms. Lee’s choice, either suggested or merely approved by Holyfield, was an an[870]*870tique, sun-dried, southwestern-style brick that everyone agreed was artistically striking. Unfortunately, this style of brick is much more porous than modern, kiln-baked brick, and was unsuited to the Lees’ house, in which one wall was partially submerged into the slope of the terrain. The Lees’ experts also testified that workers improperly applied mortar on the corner joints, left inadequate space (a vapor barrier) between the brick and wallboard, improperly installed flashing at the base of the walls and around the windows, and failed to install “weep holes” in the walls. Because of these deficiencies, rainwater constantly soaked into the west wall and could not escape, leaving the interior wall damp and prone to mold. At trial, Holy-field admitted that the brick had to be removed and replaced with a modern brick.

About two weeks before trial (and after discovery deadlines had run) another round of heavy rain pelted the area; the Lees argued that on a check of the vacant house, they discovered, for the first time, a puddle of water in a closet by the west wall. They got their new contractor, Warner, to remove all the exterior brick from the west wall; they argued that this was to pinpoint the cause of the problem. Holy-field, however, argued that the Lwater situation was “staged,” primarily so the jury would think the house was not substantially complete and the contract never fulfilled.1 Holyfield moved to exclude any testimony concerning what Warner found when he removed the bricks.

The district court granted Holyfleld’s motion, noting that the Lees provided no reports to the defense, and that allowing expert testimony at that late date would amount to “trial by ambush.” On the final day of trial, the jury toured the house, but the court admonished them that the wall had been only recently removed. The Lees’ experts were not permitted to testify about what they just recently found inside the wall.

Verdict and Judgment

In response to special interrogatories, the jury found the house was defective because Holyfield failed to comply with building standards; repair or replacement cost was $250,000; the Lees failed to make reasonable efforts to mitigate the damage; the house was not substantially complete by November 30, 2006; even though completion did not occur until April 4, 2007, the Lees sustained no damages for late completion; the Lees sustained no nonpe-cuniary damages; and the Lees still owed Holyfield the final $83,338 payment.

Judgment was rendered in accordance with these findings. The judgment also incorporated posttrial rulings assessing expert witness fees of $6,250, incidental costs of $700 and attorney fees of $24,000.

[aThe Lees have appealed, raising two assignments of error.

Discussion: Evidentiary Ruling

By their first assignment of error, the Lees urge the district court erred in refusing to permit testimony concerning what was revealed by the removal of brick in November 2010. They contend that they faced a dilemma when they discovered the puddle in the closet long after the discovery deadline had run: they had to decide whether to ignore the damage or try to discover its cause, and they chose the latter. They felt this was reasonable because res judicata would bar evidence of some other cause. Further, they show that they notified Holyfield’s counsel by email on November 6 and phone call on [871]*871November 8; Holyfield inspected the site on November 10; and they did not deny him the chance to be present when the brick was removed. They conclude that under these facts, the evidence was relevant under La. C.E. art. 402 and not unduly or unfairly prejudicial. They concede the trial court’s discretion in ruling on the probative value of evidence but maintain that this ruling resulted in gross unfairness and mandates a new trial.

Holyfield replies that the ruling was no abuse of discretion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dawson Jetton v. Tierny Jetton
Louisiana Court of Appeal, 2024
Germain Dodson v. Master Lube Express Inc.
Louisiana Court of Appeal, 2022
State of Louisiana v. Brandon Bell-Brayboy
Louisiana Court of Appeal, 2020
Berry v. Anco Insulations
273 So. 3d 595 (Louisiana Court of Appeal, 2019)
Terry v. Simmons
215 So. 3d 410 (Louisiana Court of Appeal, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
93 So. 3d 868, 2012 WL 2335994, 2012 La. App. LEXIS 875, Counsel Stack Legal Research, https://law.counselstack.com/opinion/won-suk-lee-v-holyfield-construction-inc-lactapp-2012.