Wolsiffer v. Bechill

146 P. 513, 76 Or. 516, 1915 Ore. LEXIS 309
CourtOregon Supreme Court
DecidedJune 22, 1915
StatusPublished
Cited by13 cases

This text of 146 P. 513 (Wolsiffer v. Bechill) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolsiffer v. Bechill, 146 P. 513, 76 Or. 516, 1915 Ore. LEXIS 309 (Or. 1915).

Opinions

Mr. Justice Burnett

delivered the opinion of the court.

1. The first question to be considered is the relation, if any, existing between the plaintiff and Bechill Bros. The accident happened February 6, 1913. There is in evidence an agreement in writing dated November 10, 1912, between O’Donnell and Bechill Bros., whereby the former was to do the grading, involving the filling of the pit already mentioned, according to the engineer’s plans and specifications, and to receive as compensation 20 cents per cubic yard for excavation and nothing for fill. It was admitted that Bechill Bros, had entered into a contract with the City of Portland in pursuance of a special ordinance authorizing the improvement in question, which agreement contained this condition:

[520]*520“The said work shall he performed under the personal supervision of the contractor, and no part of this contract, nor any interest therein, shall he sublet, assigned or transferred without the written consent of said city, by its executive board, and no such written consent shall release the contractor from any obligation, either to said city or to the persons employed by any subcontractor, and all subcontractors shall be considered merely as employees of the contractor and may be discharged by said city for incompetency, neglect of duty or misconduct.”

The evidence likewise tended to show that the plaintiff was not on the pay-roll of Bechill Bros., but was employed directly by O’Donnell and paid by him. It was also admitted that no consent had been given by the city or by anyone representing it authorizing Bechill Bros, to sublet any of the work to O’Donnell. What then is the legal conclusion to be drawn from this record respecting the relation existing between the plaintiff and the defendants?

In the control of the streets within its boundaries and the improvement thereof, the City of Portland was exercising a governmental function. Its ordinances and contracts made in pursuance thereof operate at least upon the parties concerned with the force of a law. It is analogous to the principle announced by Mr. Chief Justice Bean in Salem v. Anson, 40 Or. 339 (67 Pac. 190, 91 Am. St. Rep. 485, 56 L. R. A. 169). There the City of Salem had granted a franchise to the defendant Anson to use its streets, alleys and highways for the purpose of establishing and maintaining an electric light plant in the city, and had exacted from him a bond in the sum of $5,000, conditioned that he should install his plant and have it in operation by a date named. He utterly failed to construct the plant [521]*521in any respect, and the city brought an action to recover the amount of the bond. The court there said:

“The ordinance granting to Anson the right and privilege to use the streets and highways of the city in the construction and maintenance of his plant had the force and effect of a statute, and by his acceptance of its provisions he became bound to comply with its terms as a statutory duty.”

The ordinance under which the contract was promulgated in the case at bar required that:

“The contractor or contractors for said improvement shall take entire charge of the work during its progress and shall be responsible for any loss or accident resulting from carelessness or negligence and the improvement shall be completed to the satisfaction of the executive board of the said City of Portland.”

By stipulating as they did under the ordinance mentioned, Bechill Bros, in a sense assumed a statutory obligation, the benefit of which inures to any person coming within its terms. They agreed that the contractor should not be released from any responsibility either to the city or to the persons employed by any subcontractor. Under these circumstances, they could not evade their statutory duty by subletting the work to O’Donnell, and, when they attempted to install the latter as an independent contractor, the only effect accomplished as to the questions here involved when measured by their engagement with the city was merely to make him an employee in charge of the work. In short, the dealing with O’Donnell by Bechill Bros, was in derogation of a duty imposed upon them by the very ordinance and the contract under which they were operating and cannot affect their obligation to the plaintiff. In principle it comes within the doctrine [522]*522of Ackles v. Pacific Bridge Co., 66 Or. 110 (133 Pac. 781), where Mr. Chief Justice McBride said:

“Where a statute or city ordinance requires certain precautions to be taken for the safety of the public in the manner of doing the work, the contractor cannot shift his liability for failure to take these precautions by employing a subcontractor: Colgrove v. Smith, 102 Cal. 220 (36 Pac. 411, 27 L. R. A. 590); Luce v. Holloway, 156 Cal. 162 (103 Pac. 886); Storrs v. City of Utica, 17 N. Y. 104 (72 Am. Dec. 437); North Chicago St. R. R. Co. v. Dudgeon, 184 Ill. 477 (56 N. E. 796); Robbins v. Chicago City, 4 Wall. 657 (18 L. Ed. 427); Hawver v. Whalen, 49 Ohio St. 69 (29 N. E. 1049, 14 L. R. A. 828); Werthheimer v. Saunders, 95 Wis. 573 (70 N. W. 824, 37 L. R. A. 146).”

In Morgan v. Bross, 64 Or. 63 (129 Pac. 118), the defendant was a contractor engaged in the construction of a brick building, and the plaintiff was a plumber installing pipes on the first floor beneath where the defendant and his employees were at work on the fourth story. The action was instituted under the employers’ liability law, the substance of the charge being that for want of temporary floors in the edifice, as required by a building ordinance of the City of Portland a brick falling from where the defendant was at work struck the plaintiff and injured him. At the trial the defendant was refused the right to show that the man in charge of the carpenter work had agreed to install the temporary floors. This court, however, approved this action of the Circuit Court, speaking by Mr. Justice Moore in this language:

“The obligations to lay such coverings, in order to. protect the life and limbs of persons employed in a building under construction, having been placed by the statute and ordinance referred to on a contractor, [523]*523the defendant, who sustained that relation to the owner, could not escape liability for a neglect to comply with such requirements by showing that the carpenter had agreed to discharge that duty.”

2. The principal error assigned by all the defendants is that the Circuit Court was mistaken in holding the case to be one stated under the initiative act of November, 1910, and commonly known as the employers’ liability law (Chapter 3, p. 16, Laws 1911; L. O. L. xxxvi). That is a statute which specifies in its title that:

It is “for the protection and safety of persons engaged * * in any dangerous occupation, and extending and defining the liability of employers in any or all acts of negligence, or for injury or death of their employees, and defining who are the agents of the employer. * *

Section 1 of that act, so far as deemed even possibly applicable to the case in hand, reads thus:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wienke v. OCHOCO LUMBER COMPANY
558 P.2d 319 (Oregon Supreme Court, 1976)
Johnson v. Salem Title Co.
425 P.2d 519 (Oregon Supreme Court, 1967)
Larson v. Heintz Construction Co.
345 P.2d 835 (Oregon Supreme Court, 1959)
Williams v. Clemen's Forest Products, Inc.
217 P.2d 252 (Oregon Supreme Court, 1950)
Hale v. Electric Steel Foundry Co.
192 P.2d 257 (Oregon Supreme Court, 1948)
Smith v. Shevlin-Hixon Co.
157 F.2d 51 (Ninth Circuit, 1946)
Coomer v. Supple Investment Co.
274 P. 302 (Oregon Supreme Court, 1929)
McCauley v. Steamship
215 P. 892 (Oregon Supreme Court, 1923)
Rorvik v. North Pac. Lumber Co.
190 P. 331 (Oregon Supreme Court, 1920)
Nordin v. Lovegren Lumber Co.
156 P. 587 (Oregon Supreme Court, 1916)
McGee v. Carlton Lumber Co.
151 P. 652 (Oregon Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
146 P. 513, 76 Or. 516, 1915 Ore. LEXIS 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolsiffer-v-bechill-or-1915.