Wolf Creek Eng. & Contracting, Inc. v. Ohio Dept. of Transp.

2011 Ohio 1406
CourtOhio Court of Claims
DecidedFebruary 11, 2011
Docket2008-07934
StatusPublished

This text of 2011 Ohio 1406 (Wolf Creek Eng. & Contracting, Inc. v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolf Creek Eng. & Contracting, Inc. v. Ohio Dept. of Transp., 2011 Ohio 1406 (Ohio Super. Ct. 2011).

Opinion

[Cite as Wolf Creek Eng. & Contracting, Inc. v. Ohio Dept. of Transp., 2011-Ohio-1406.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

WOLF CREEK ENGINEERING AND CONTRACTING, INC.

Plaintiff

v.

OHIO DEPARTMENT OF TRANSPORTATION

Defendant Case No. 2008-07934

Judge Joseph T. Clark Magistrate Lee Hogan

MAGISTRATE DECISION

{¶ 1} Plaintiff, Wolf Creek Engineering and Contracting , Inc. (Wolf Creek), brought this action on behalf of its subcontractor, Youngstown Bridge & Iron, Inc. (YBI), against defendant, Ohio Department of Transportation (ODOT). In its complaint, plaintiff alleges that this action is an appeal of the denial by the Claims Board Hearing Panel of the claim for compensation sought by YBI for the cost of replacing bolt assemblies that ODOT found to have been over-tightened beyond contract specifications. The issues of liability and damages were not bifurcated and the case proceeded to trial on both issues. {¶ 2} The parties stipulated that they entered into a contract with regard to a bridge project in Summit County, that YBI was plaintiff’s subcontractor performing structural bolt replacement, that the specifications governing and applicable to this dispute include both “Specification 10509” and “Section 513 of the 2005 Construction and Material Specification [CMS] as to Structural Steel Members,” and that the parties had completed the contractual dispute resolution process. The parties further stipulated Case No. 2008-07934 -2- MAGISTRATE DECISION

that the “singular issue subject to trial” is whether plaintiff “complied with the project contract and satisfactorily performed its work” or whether plaintiff did not meet the contract such that plaintiff “was required, for no compensation, to remove and/or replace the bolt assemblies” or otherwise satisfy defendant that “replacement of bolt assemblies was not necessary.” (Stipulation of Parties, as read into the record.) {¶ 3} According to ODOT, the contract required YBI to perform four steps: 1) the bolt and nut were to be assembled to a snug-tight connection; 2) the position of the nut on the bolt was marked; 3) the nut was then rotated 1/3 of a turn; and 4) a torque wrench was applied to ensure a predetermined minimum tightness. Specification Section 513.20 states, in part, that bolts are “snug tight when an impact wrench begins to impact the nut.” (Defendant’s Exhibit A.) Once the ironworker tightens the nut on the bolt to the “snug-tight” position, he then performs the “match mark” process. According to the specification, “the wrench operator shall match-mark the outer face of the nut with the flush or protruding portion of the bolt using a crayon or paint. The engineer will use the match-marks to determine the relative rotation between the bolt and nut during final tightening using the turn-of-the-nut method.” (Defendant’s Exhibit A.) After the components of the assembly have been marked, the installer uses a torque wrench to tighten the nut by 1/3 of a turn, plus or minus 30 percent. The bolts used in the project were supplied by Wolf Creek. {¶ 4} Martin DePerro testified that he is the owner of YBI and that although he was never at the job site during construction, in his stead he sent his foremen, either Kenneth Orf or Brian Filip, and that each of them had over ten years experience. On August 14, 2007, ODOT notified YBI’s ironworkers that some of the bolts were being turned 3/4 turn after match marking rather than the 1/3 turn.1 On August 15, 2007, ODOT determined that some of the bolt assemblies had failed in that the nuts were

1 ODOT inspectors noted in their daily logs that some match marks exceeded the 1/3 turn and that the ironworkers were going too far. (Defendant’s Exhibits J, K.) Case No. 2008-07934 -3- MAGISTRATE DECISION

stripped and these defective assemblies were marked for replacement. (Defendant’s Exhibit K.) According to DePerro, YBI replaced approximately 18 bolts out of 1,000 and then tested the majority of the remaining bolts with the torque wrench in the presence of the ODOT inspector. After YBI had completed their portion of the work and left the project, ODOT notified Wolf Creek that it had concerns that the remaining bolts may have been over-tightened. {¶ 5} In a letter dated August 28, 2007, ODOT stated that “[d]ue to the significant number of failed high strength bolts in splice #1 and numerous other match marked bolts which appear to have been tightened beyond the specified tolerance, it appears that bolts may have been over tensioned during the erection and detailing of the structural steel members. The concern is that this condition may result in premature failure of these assemblies. * * * In lieu of removal and replacement of these non- specification assemblies, submit for review and acceptance a proposal, prepared and signed by a registered professional engineer, to address this condition.” (Plaintiff’s Exhibit 28.) {¶ 6} DePerro testified that the option of finding an engineer to guarantee the performance of the bolts was not feasible inasmuch as no engineer would certify such condition without having been present when the bolts were installed. Subsequently, YBI removed and replaced all of the bolts. During cross-examination, DePerro acknowledged that he had observed some bolts in place prior to their replacement and that he also saw that some had been tightened beyond the match mark specification contained in Section 513.20 of the contract. DePerro conceded that if the nuts had been turned in excess of 1/3 of a turn including tolerance, such condition would not be in compliance with the contract. {¶ 7} Brian Filip testified that he is a union ironworker who has been employed by YBI for several years and that he was a foreman on this project until August 13, 2007. Filip identified David James as the ODOT engineer who inspected the bolt assembly operation. Filip attributed the differences in the match marks to the individual Case No. 2008-07934 -4- MAGISTRATE DECISION

techniques used by the various installers. Filip testified that in response to ODOT’s rejection of the work, YBI cut out and replaced all the bolts and that each replacement bolt assembly was measured to be in compliance with the 1/3-turn specification.2 {¶ 8} Kenneth Orf testified that he has worked for YBI for over ten years and that he replaced Filip as the foreman on the project. Orf testified that the usual approach for each bolt assembly project involved performing the “Skidmore test” first. He explained that for each size bolt used on the project, YBI took an average torque measurement for three random bolts and set the torque wrench accordingly. Regarding match marks, Orf noted that they can differ if all the bolts were not snug-tightened at the same place. Nonetheless, he acknowledged that all the match marks in one splice should be at the same place. He admitted that ODOT inspectors notified him that some of the bolt assemblies were stripped but that such assemblies were replaced. He testified that he did not learn of ODOT’s concerns regarding the match marks until near the end of the job. He recalled that some of the beams were spliced at night on the ground and other beams were spliced in place on the bridge. {¶ 9} Plaintiff presented the expert testimony of Alan Sheppard, a licensed engineer who had been employed for over 34 years with Bethlehem Steel Company. He stated that he has experience with bolt assembly and has supervised the same. Sheppard described how the nuts are placed on the bolts with an air or vacuum- powered tool and how the installer listens as the nut makes a “whirring” sound until it makes contact, then the sound changes to a “click” at each turn. The click indicates an impact strike.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skivolocki v. East Ohio Gas Co.
313 N.E.2d 374 (Ohio Supreme Court, 1974)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
Kelly v. Medical Life Insurance
509 N.E.2d 411 (Ohio Supreme Court, 1987)
Shifrin v. Forest City Enterprises, Inc.
597 N.E.2d 499 (Ohio Supreme Court, 1992)
Saunders v. Mortensen
801 N.E.2d 452 (Ohio Supreme Court, 2004)
City of St. Marys v. Auglaize County Board of Commissioners
875 N.E.2d 561 (Ohio Supreme Court, 2007)
Shifrin v. Forest City Ent., Inc.
1992 Ohio 28 (Ohio Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 1406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolf-creek-eng-contracting-inc-v-ohio-dept-of-tran-ohioctcl-2011.