W.O. Grubb Steel Erection Incorporated v. Coastal Dredging, LLC

District Court, E.D. Virginia·Decided June 12, 2025·No. 3:24-cv-00313·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Richmond Division W.O. GRUBB STEEL ERECTION, INC., ) Plaintiff, ) ) v. ) Civil Action No. 3:24CV313 (RCY) ) COASTAL DREDGING, LLC, ) Defendant. ) ) MEMORANDUM OPINION Thisis anegligence action originally brought by Plaintiff W.O. Grubb Steel Erection, Inc. (“W.O. Grubb”)against Defendant Coastal Dredging, LLC (“Coastal”). Coastal has now brought a counterclaim against W.O. Grubb, and the matter is before the Court on W.O. Grubb’s Motion to Dismiss the Counterclaim. The Motion has been fully briefed, and the Court dispenses with oral argument because the facts and legal contentions are adequately presented in the materials before the Court, and oral argument would not aid in the decisional process. E.D. Va. Loc. Civ. R. 7(J). For the reasons stated below, the Court will deny W.O. Grubb’s Motion to Dismiss. I. FACTUAL AND PROCEDURAL BACKGROUND1 In this action, W.O. Grubb alleges that Coastal engaged W.O. Grubb to provide a construction crane and operator for a dredging project in Wilmington, North Carolina. Compl. ¶¶ 8–9, ECF No. 1-2 at 2–6.2 W.O. Grubb alleges that, upon arriving at the job site, Coastal’s agent signed a “crane ticket,” an electronic agreement prepared by W.O. Grubb containing “information about the job, the crane that is being rented, and the customer renting the crane.”

1 The Court has previously set out a more detailed recitation of the factual background of the dispute between the parties in its earlier Memorandum Opinion denying Defendant’s Motion to Dismiss, ECF No. 13. Because those facts are not essential to resolving the present motion, the Court dispenses with reciting them in full yet again here. 2 Because this matter was removed from state court, the Complaint and its attachments were uploaded to the electronic record as a single file, ECF No. 1-2. For ease of identification, the Court provides pin-cites to the portion of ECF No. 1-2 where the relevant exhibit may be found. Id. ¶ 5–8. W.O. Grubb alleges that the crane ticket had the force of contract. Id. Relevant here, the crane ticket contract produced by W.O. Grubb assigned all responsibility for property damage and injury to Coastal, waiving W.O. Grubb’s liability. Compl. Ex. C at 15–16, ECF No. 1-2 at 12–69. Finally, W.O. Grubb alleges that Coastal was negligent in rigging W.O. Grubb’s crane to the dredge, which caused significant damage to W.O. Grubb’s crane. Compl. ¶ 15. On May 7, 2024, Coastal filed a Motion to Dismiss the Complaint, asserting that neither it nor its agent had any knowledge of the substance of the crane ticket and therefore could not be

constrained by its terms. See generally Mem. Supp. Mot. Dismiss, ECF No. 4. The Court denied the Motion to Dismiss, finding that W.O. Grubb had adequately alleged the existence of a contract between the parties by way of the crane ticket. See generally Mem. Op., ECF No. 13. On March 31, 2025, Coastal filed its Answer as well as a Counterclaim against W.O. Grubb. Coastal’s Answer, Affirmative Defenses, & Countercl. (“Answer” & “Countercl.”),3ECF No. 17. Therein, Coastal denies the existence of a contractual relationship between the parties, Answer ¶¶ 6–7, and alleges that W.O. Grubb acted negligently itself, causing damage to Coastal’s dredge, Countercl. ¶¶ 20–25. On April 21, 2025, W.O. Grubb filed the instant Motion to Dismiss Coastal Dredging, LLC’s Counterclaim (“Motion to Dismiss the Counterclaim”), ECF No. 18. On May 5, 2025,

Coastal filed its Opposition to theMotion to Dismiss Coastal’s Counterclaim (“Opposition”), ECF No. 20. On May 12, 2025, W.O. Grubb filed its Reply in Support of its Motion to Dismiss Coastal Dredging, LLC’s Counterclaim (“Reply”), ECF No. 22.

3 Docket filing ECF No. 17 is separated into two, discrete, legally operative sections: Coastal’s Answer, from pages 1–6, and Coastal’s Counterclaim, from pages 6–10. Both sections are comprised of enumerated paragraphs. For ease of reference, the Court will cite to the Answer and Counterclaim as distinct documents with an accompanying pin cite to the relevant paragraph. II. LEGAL STANDARD The Rule 12(b)(6) standard governing counterclaims is identical to that which governs complaints. See, e.g., Fisher v. Va. Elec. & Power Co., 258 F. Supp. 2d 445, 447 (E.D. Va. 2003). “A motion to dismiss under Rule 12(b)(6) tests the sufficiency of a [pleading]; importantly, it does not resolve contests surrounding the facts, the merits of a claim, or the applicability of defenses.” Megaro v. McCollum, 66 F.4th 151, 157 (4th Cir. 2023) (quoting Republican Party of N.C. v. Martin, 980 F.2d 943, 952 (4th Cir. 1992)). Federal Rule of Civil Procedure 8 only requires that

a counterclaim set forth “‘a short and plain statement of the claim showing that the pleader is entitled to relief,’ in order to ‘give the defendant fair notice of what the . . . claim is and the grounds upon which it rests.’” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555 (2007) (quoting Conley v. Gibson, 355 U.S. 41, 47 (1957)). While a counterclaim’s “[f]actual allegations must be enough to raise a right to relief above the speculative level,” “detailed factual allegations” are not required in order to satisfy the pleading requirement of Federal Rule 8(a)(2). Id. (citations omitted). The counterclaimant’s well-pleaded allegations are assumed to be true, and the counterclaim is viewed in the light most favorable to the plaintiff. Mylan Lab’ys, Inc. v. Matkari, 7 F.3d 1130, 1134 (4th Cir. 1993) (citations omitted); see also Martin, 980 F.2d at 952. III. ANALYSIS

In support of its Motion to Dismiss, W.O. Grubb argues that Coastal’s Counterclaim fails to articulate a claim because, by signing the crane ticket contract, Coastal agreed to bear all responsibility for damages, waiving W.O. Grubb’s liability entirely. Mem. Supp. Mot. Dismiss Coastal’s Countercl. (“Pl. Mem. Supp.”) 5–7, ECF No. 19. In response, Coastal argues that W.O. Grubb cannot rely on the provisions of the crane ticket, since Coastal neither references nor relies upon the crane ticket in its Counterclaim. Opp’n 4–5, ECF No. 20. The Court agrees with Coastal that the terms of the contract cannot be considered by the Court in the context of a Motion to Dismiss. Because W.O. Grubb’s arguments for dismissal wholly rely on those terms,4 the Court will deny its Motion. In determining whether a counterclaim adequately articulates a claim for relief, the Court is generally constrained to those facts alleged on the face of the counterclaim. Philips v. Pitt Cnty. Mem’l Hosp., 572 F.3d 176, 180 (4th Cir. 2009). The Court may consider, however, limited materials outside the counterclaim, namely: “documents incorporated into the [pleading] by reference, and matters of which a court may take judicial notice.” Tellabs, Inc. v. Makor Issues &

Free access — add to your briefcase to read the full text and ask questions with AI

W.O. Grubb Steel Erection Incorporated v. Coastal Dredging, LLC, (E.D. Va. 2025).

W.O. Grubb Steel Erection Incorporated v. Coastal Dredging, LLC (W.O. Grubb Steel Erection Incorporated v. Coastal Dredging, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Philips v. Pitt County Memorial Hospital
572 F.3d 176 (Fourth Circuit, 2009)
Fisher v. Virginia Electric & Power Co.
258 F. Supp. 2d 445 (E.D. Virginia, 2003)
Republican Party of North Carolina v. Martin
980 F.2d 943 (Fourth Circuit, 1992)
Halscott Megaro, P.A. v. Henry McCollum
66 F.4th 151 (Fourth Circuit, 2023)