Wix v. Bowling

87 A. 759, 120 Md. 265, 1913 Md. LEXIS 118
CourtCourt of Appeals of Maryland
DecidedApril 9, 1913
StatusPublished
Cited by5 cases

This text of 87 A. 759 (Wix v. Bowling) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wix v. Bowling, 87 A. 759, 120 Md. 265, 1913 Md. LEXIS 118 (Md. 1913).

Opinion

*267 Thomas, J\,

delivered the opinion of the.Court.

The hill in this case was tiled by the appellant to enforce an alleged mechanics’ lien against the property of the appellee, and the appeal is from a decree of the Circuit Court for Prince George’s County dismissing the bill as to the appellant.

The relief prayed is resisted on two grounds: first, because the claim was not filed in accordance with the provisions of the Code; and, second, because the lien was waived by the appellant.

The Code requires the claim to be filed within six months after the work has been finished or the materials furnished and section 19 of Article 63 of the Code of 1912 provides that, “Every such claim shall set forth: first, the name of the party claimant, and the owner or reputed owner of the building, and also of the contractor or architect- or builder when the contract was made by the claimant with such contractor, architect or builder; second, the amount or sum claimed to be due and the nature or kind of work or the kind and amount of materials furnished and the time when the materials were furnished or the work done; thirdly, the locality of the building and the number and size of the stories of the same, or such other matters of description as may be necessary to identify the same.” In the case of German Lutheran Church v. Heise, 44 Md. 453, the Court said that in the absence of evidence of an express contract, “the character of the account, the time within which the work was done or the materials were furnished, and the object of the work or materials, may afford proper grounds for the presumption that the work was done or the materials were furnished with reference to an understanding from the commencement that such work or materials should be done or furnished, if required by the builder; and in such case, it is from the last item in the account that the notice and the time within which to take the lien, should date. But where the materials are furnished for separate and distinct purposes, or at different times, or at considerable intervals, or under distinct contracts *268 or orders, though to he used by the contractor, or builder in executing one and the same contract with the owner, no such presumption will arise, and the right to take the lien must date from the time of furnishing the different parcels of' material, and not from the last item in the account.” In other words, where the work is done or the materials are furnished under distinct contracts, the claim must be filed within six months from the completion of the work or the furnishing of the materials under each contract.

The claim in this case was filed on the 24th day of December, 1910, and states that it is for work and materials furnished “at the particular time, and of the nature or kind and amount and for the purposes set fbrth in a bill of particulars hereto annexed, and which work has been finished and materials furnished within less than six months before the filing of this claim.” The bill of particulars contains three items. The first is “To plumbing as per contract including furnishing of material and labor, furnished and performed between April 2nd and August 16th, 1910 — $200.00.” The second item is “To heating plant as per contract including furnishing of material and labor, furnished and performed between April 2nd, 1910, and August 16th, 1910, — $400.00; .and the third item is “To extra bath room outfit as per agreement including furnishing of material and labor furnished and performed between June 2lth, 1910, and August 15th, 1910, — $135.00.” It therefore appears from the bill of particulars that the last item is for work done and materials furnished within six months before the filing of the claim, - but it fails to show, as to the first two items, that the work was done and the materials were furnished within that time. If the work referred to in these two items was done and the materials therein mentioned were furnished at any time between the second day of April and the twenty-fourth of June, 1910, said work was “finished and materials furnished,” at the time mentioned in the bill of particulars, yet as to such work and materials the claim was not filed in time,- unless all the work referred to in the bill of particulars was done and *269 the materials were furnished under one contract. It is true, the claim states that the “work has been finished and the material furnished within less than six months before the filing of this claim,” but if the work was done and the materials furnished under separate and distinct contracts, it would be impossible to tell what work and materials this statement refers to. The statement would be literally true if the work done and materials furnished under either of two contracts had been finished and furnished within six months prior to the filing of the claim, and yet the work done and the materials furnished under the other contract may have been finished and furnished at any time after the 2nd of April and prior to the 16th of August, 1910. The evidence shows that the work referred to in the first two items of the bill of particulars was done and the materials were furnished under one contract, while the work and materials referred to in the third item were covered by a separate and distinct contract. The claim is, therefore, defective as to the first two items of the bill of particulars, because it fails to show that the work charged for in those items was done, and that the materials therein referred to were furnished, within the time required by the statute. In the case of Clark v. Boarman, 89 Md. 428, Judge Boyd said: “When materials are furnished and work is done under distinct contracts, the material man or mechanic is not entitled to a lien to secure himself under all the contracts by simply counting from the last item of one of them. He must file his lien within six months after the work is finished or the materials furnished under each contract. * * * That being so, it is apparent that a lien-claim which includes work done and materials furnished under two or more separate contracts should give the dates for each, and a mere statement that the work Tas been finished and materials furnished within less than six months before filing of the claim’ is not sufficient. It may be true that work was done and materials were furnished under one of the contracts within the six months, but if more than six *270 months had expired since the work was done or the materials furnished under the other contracts, the lien would not attach to them. If the dwelling was completed more than six months before the claim was filed, the lien could not attach for any balance due for it, and if the outhouses were, then it would be of no avail as to them. So if it be conceded that some work was done, or materials furnished, within six months, it would be impossible to say under which contract, and hence the Court could not pass a decree.”

The defect in the claim to which we have alluded affects, however, only the first two items of the bill of particulars. The third item, as we have said, relates to work done and materials furnished under a separate contract, and the bill of particulars shows that the work was done and the materials were furnished within six months before the filing of the claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kitchen v. Himelfarb
254 A.2d 694 (Court of Appeals of Maryland, 1968)
Parkway Estates, Inc. v. Burnham
122 A.2d 326 (Court of Appeals of Maryland, 1956)
Crane Co. v. Onley
69 A.2d 903 (Court of Appeals of Maryland, 1949)
Atlantic Mill & Lumber Realty Co. v. Keefer
20 A.2d 178 (Court of Appeals of Maryland, 1941)
Frederick County National Bank v. Dunn
93 A. 984 (Court of Appeals of Maryland, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
87 A. 759, 120 Md. 265, 1913 Md. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wix-v-bowling-md-1913.