Parkway Estates, Inc. v. Burnham

122 A.2d 326, 210 Md. 64, 1956 Md. LEXIS 439
Court of Appeals of Maryland·Decided May 4, 1956·No. [No. 160, October Term, 1955.]·Published·Cited by 4 cases

Opinion

Hammond, J.,

delivered the opinion of the Court.

A mechanic’s lien claimant was granted a decree against the corporate property owner, which appeals, assigning as error the chancellor’s rejection of its attacks on the legal sufficiency of the notice of intention to claim the lien, the lien claim, the bill to enforce the lien and the evidence offered in support of the bill.

In January, 1954, the appellee Burnham, a plastering contractor, agreed with The Georgetown Construction Company, the general contractor, that for a price of $6,520.00 he would plaster twenty-six two story houses it was building in south Baltimore for the owner, Parkway Estates, Inc., the appellant. Georgetown paid Burnham all of the contract price but $900.00. When this balance due was not forthcoming, *66 Burnham, on June 30, 1954, within sixty days of the doing of the last of the plastering, caused notice of intention to claim a lien to be personally served on Parkway’s resident agent. In July, he filed the lien and in the following January, the bill to enforce it. Parkway posted bond to guarantee payment of any decree against it. Its demurrer to the bill was overruled and after hearing testimony, the chancellor granted Burnham a decree for $900.00.

Parkway’s demurrer claimed the bill to be defective for failure to set forth facts that showed that the notice of intention to claim the lien met the requirements of the statute. The bill alleges that “* * * after compliance with all legal prerequisites as to notice to the said Parkway Estates, Inc., the owner or reputed owners of said properties, your Orator filed a Mechanic’s Lien * * * the original of which is hereto attached and prayed to be taken as a part of this bill of complaint, and marked ‘Complainant’s Exhibit A’.” In Exhibit A was this statement: “* * * and notice has been given by Raymond F. Burnham in writing to the said PARKWAY ESTATES, INC. of the intention of the said Raymond F. Burnham to claim this lien within sixty days from the last work done under said subcontract.” We think the allegations of the bill, read with the statements of fact in the exhibit, are sufficient and that the demurrer properly was overruled.

Parkway’s main defense is that the period of the performance of the contract and the time that the last work under it was done, are not shown in the notice of intention, the claim itself, or the proof in support of the bill. The questions as to the notice and the lien may be discussed as one. The notice, delivered on June 30, 1954, states that Burnham intends to claim a lien against twenty-six houses designated by street numbers and identified by deed references to secure a $900.00 balance due (apportioned as to each house) on a contract “for labor in plastering each of said houses furnished by said Raymond F. Burnham within sixty days last past to The Georgetown Construction Company, the contractor, for the building thereof, under an agreement made by the said Raymond F. Burnham with the said The George *67 town Construction Company * * *.” The statement of claim appended to the notice recites the contract agreement with Georgetown, sets out the contract price of $6,520.00, the dates of payment on account beginning February 11, 1954, and ending March 30, 1954, in the total amount of $5,620.00, the balance due of $900.00, the apportionment as to each house, and the statement “Work completed May 3, 1954”.

The lien claims $900.00 for plastering twenty-six houses, again designated by street numbers and identified by the deed whereby Parkway acquired the lots on which they were built, and adds that the said claim is “* * * for work done and labor performed in the plastering of each of said houses * * * at the instance and request of The Georgetown Construction Company, the general contractor for the erection and construction of the said buildings, at that particular time, and of the nature and kind and amount, and for the contract price as set forth in the Bill of Particulars annexed hereto, of which $900.00 remains unpaid, and which labor and work has been finished and completed within less than six months before the filing of this claim.” The bill of particulars shows the total contract price for plastering of twenty-six houses, divided into $250.00 for each of twenty-two houses, and $255.00 for each of four houses. It shows payments on account on February 11, 1954, February 19, 1954, March 20, 1954, March 24, 1954, and March 30, 1954. It states that: “The said subcontract was completed on May 3rd, 1954 * * *.”

Free access — add to your briefcase to read the full text and ask questions with AI

Parkway Estates, Inc. v. Burnham, 122 A.2d 326, 210 Md. 64, 1956 Md. LEXIS 439 (Md. 1956).

122 A.2d 326 (Parkway Estates, Inc. v. Burnham) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mashkes v. Jakenjo, Inc.
154 A.2d 439 (Court of Appeals of Maryland, 2001)
S.K. Drywall, Inc. v. Developers Financial Group, Inc.
819 P.2d 931 (Arizona Supreme Court, 1991)
Himelfarb v. B & M Welding & Iron Works, Inc.
253 A.2d 842 (Court of Appeals of Maryland, 1969)
G. Edgar Harr Sons v. Newton
155 A.2d 480 (Court of Appeals of Maryland, 1959)