Witter v. Bachman

49 P. 202, 117 Cal. 318, 1897 Cal. LEXIS 660
CourtCalifornia Supreme Court
DecidedJune 17, 1897
DocketL. A. No. 207
StatusPublished
Cited by15 cases

This text of 49 P. 202 (Witter v. Bachman) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Witter v. Bachman, 49 P. 202, 117 Cal. 318, 1897 Cal. LEXIS 660 (Cal. 1897).

Opinion

Chipman, C.

T'his is an action to foreclose a contractor’s lien for certain work done upon the sidewalks in front of certain lots in the city of San Luis Obispo.

Plaintiff filed a complaint, and caused summons to issue, which was served upon defendant Sallie Zederman only. Plaintiff caused default to be entered against her [319]*319by the clerk for not answering, whereupon her counsel moved to set aside the default. The court granted the motion. Plaintiff prepared a bill of exceptions to bring up this alleged error of the court. Much of his brief is devoted to a discussion of the law as to when a defendant may have a default judgment set aside, which has been entered against him. But plaintiff, shortly after this order was made, filed an amended complaint, introducing an additional defendant (W. W. Tinker), and alleging some new matter, to which the defendants, Zederman and Tinker, answered, and plaintiff went to trial on this amended complaint and answer. Besides, there was no judgment entered upon the default, and none asked for. The amended complaint constituted a new complaint, which superseded all other pleadings in the case. By amending bis complaint in matter of substance, as was done here, it had the effect to open the default. (Thompson v. Johnson, 60 Cal. 292.)

The action set forth in the amended complaint was to recover the contract price of certain work mentioned in the original complaint, and to foreclose the lien thereof. Defendants had judgment. This appeal is from the judgment and from the order denying plaintiff’s motion for a new trial.

The case arises under the several acts so frequently before this court. (Stats. 1885, p. 147; Stats. 1889, p. 357; Stats. 1891, p. 196.) No question is presented as to the sufficiency of the complaint. Plaintiff offered in evidence the assessment, diagram, warrant, certificate, and affidavit of demand and nonpayment. The warrant was duly signed by the superintendent of streets and countersigned by the president of the board of trustees, and recorded. Evidence was offered of the ownership of the lots in question, and also that a deposit had been made to provide for the payment of the assessment in controversy, and plaintiff rested.

It was shown by defendants that the street superintendent did not in fact make the entries in the assessment-roll, but he authorized them to be entered and he [320]*320afterward signed the record. This was sufficient to make the entries his own.

The defendants were then permitted to prove, against plaintiff’s objection, that defendant Zederman asked permission through one Dickerson from the district attorney to construct the sidewalks in front of her lots (the lots in question); that she made a contract with said Dickerson August 15,1892, to do the work for her, and he did it. Defendants were also permitted, against plaintiff’s objection, to introduce the miqutes of the board, where the council awarded the contract to plaintiff’s assignor (one Pollard, the contractor), to show that the council granted permission to defendant Zederman to construct the sidewalks in front of her lots. Defendants then had read from the minutes the resolution of intention and the contract with said Pollard to do the work. The resolution included the work in question, was introduced August 17, 1891, and passed on September 7, 1891, and ordered published for two days successively. The contract was introduced by defendant and bears date September 24, 1892, and recites that it is made pursuant to proceedings of the board on September 5, 1892, awarding the contract, which latter proceedings do not appear in the record; in the body of the contract is to be found the resolution of intention and various proceedings of the board by way of recitals, and among these is a resolution of the board in which occurs the following:

“ 1. That sidewalks be constructed on Osos street of said city in accordance with the resolution of intention passed on September 7, 1891 (excepting, however, such places where, in the meantime, sidewalks may have been constructed),” etc. This resolution was passed October 19, 1891. The court found the facts as alleged in the complaint, except that it found: 1. That on August 15, 1892, upon the application of defendant Zederman, the then owner of the lots in question, the board granted her permission to construct the sidewalks in front of said lots, under private contract with one Dickerson; that the [321]*321work was done by him and was substantially completed before the contract was let to Pollard; 2. That Pollard did no work and furnished no material upon the lots sought to be charged with the lien; 3. That the record of the return upon the warrant and assessment was not signed by tire superintendent of streets, and that, while the contract was left with him, it was not recorded or marked as filed or recorded by him or at all.

Plaintiff offers no evidence to show that the work for which he claims pay was done by him, except the assessment, diagram, warrant, certificate, and affidavit of demand of nonpayment, which he alleges made a prima facie case; and he further claims that when recorded in the office of superintendent of streets they constituted a lien; that it was error to prove by parol the permission to defendant Zederman to do the work on her own lots; that three-fourths of the owners were not shown to have entered into a written contract nor made written application within ten days after the first posting and publication of the notice of award, nor did they elect to take the work at any price; that no contract with said Zederman was shown; that the board acquired jurisdiction of the matter, and that defendants’ only remedy was by appeal to the council.

There is no brief on file for respondents, and we are left without any assistance from them. The certified copy of what purported to be the assessment, diagram, warrant, certificate, and affidavit of demand and nonpayment, was introduced without objection. The assessment shows items against the lots in question amounting to one hundred and forty-five dollars and seventy-eight cents.

There is no evidence to justify the finding of the court that the council granted permission to defendant Zederman to construct the sidewalks in front of her lots. There is no evidence to sustain the finding that this defendant completed the work before the contract was let to Pollard, the contractor, although there is evidence tending to show that she did the work, and that [322]*322the contractor did no part of it. The evidence justifies the finding that the record of the return upon the warrant was not signed by the superintendent of streets, and there is evidence to justify the finding that, althoúgh the contract of Pollard was left with the superintendent, it was not recorded or marked filed or recorded by him or at all.

Section 10 of the act of 1885 requires that the warrant shall be returned to the superintendent, with a return indorsed thereon by the contractor, verified by oath, stating the nature and character of the demand, etc. “Thereupon the superintendent of streets shall record the return so made, in the margin of the record of the warrant and assessment, and also the original contract referred to therein, if it has not already been recorded, at full length in a book to be kept for that purpose in his office, and shall sign the record.”

The indorsement upon the return is as follows: “Returned this 15th day of July, 1893, and return recorded. Supt. of Public Streets.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Talbot v. Wake
74 Cal. App. 3d 428 (California Court of Appeal, 1977)
Howard Park Co. v. City of Los Angeles
259 P.2d 977 (California Court of Appeal, 1953)
Thompson v. Cook
127 P.2d 909 (California Supreme Court, 1942)
W. H. Marston Co. v. Kochritz
251 P. 959 (California Court of Appeal, 1926)
Rutledge v. City of Eureka
234 P. 82 (California Supreme Court, 1925)
Price v. Skylstead
222 P. 1059 (Montana Supreme Court, 1924)
Cole v. Roebling Construction Co.
105 P. 255 (California Supreme Court, 1909)
Gilbert v. American Trust & Savings Bank
118 Ill. App. 678 (Appellate Court of Illinois, 1905)
San Diego Savings Bank v. Goodsell
70 P. 299 (California Supreme Court, 1902)
Couco v. Drinkhouse
69 P. 968 (California Supreme Court, 1902)
Blanchard v. Ladd
67 P. 130 (California Supreme Court, 1901)
Tappendorff v. Moranda
66 P. 491 (California Supreme Court, 1901)
Reid v. Clay
66 P. 262 (California Supreme Court, 1901)
Greenwood v. Chandon
62 P. 736 (California Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
49 P. 202, 117 Cal. 318, 1897 Cal. LEXIS 660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/witter-v-bachman-cal-1897.