Wisconsin Power & Light Co. v. Gerke

121 N.W.2d 912, 20 Wis. 2d 181
CourtWisconsin Supreme Court
DecidedJune 4, 1963
StatusPublished
Cited by16 cases

This text of 121 N.W.2d 912 (Wisconsin Power & Light Co. v. Gerke) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Power & Light Co. v. Gerke, 121 N.W.2d 912, 20 Wis. 2d 181 (Wis. 1963).

Opinion

Fairchild, J.

Sec. 66.047, Stats. 1959, provides:

“No contractor having a contract for any work upon, over, along or under any public street or highway shall interfere with, destroy or disturb the structures of any public service corporation encountered in the performance of such work so as to interrupt, impair or affect the public service for which such structures may be used, without first procuring written authority from the commissioner of public works, or other properly constituted authority. It shall, however, be the duty of every public service corporation, whenever a temporary protection of, or temporary change in, its structures, located upon, over, along or under the surface of any public street or highway is deemed by the commissioner of public works, or other such duly constituted authority, to be reasonably necessary to enable the accomplishment of such work, to so temporarily protect or change its said structures; provided, that such contractor shall give at least 2 days’ notice of such required temporary protection or temporary change to such corporation, and shall pay or assure to such corporation the reasonable cost thereof, except when such corporation is properly liable therefor under the law, but in all cases where such work is done by or for the state or by or for any county, city, village, or town, the cost of such temporary protection or temporary change shall be borne by such public service corporation.”

1. Contractor’s liability for damage to transmission line. Gerke contends that the Power Company was obliged to *186 remove the line; that the line was therefore a nuisance which he could summarily abate. It seems to us, however, that the first sentence of sec. 66.047, Stats. 1959, just quoted, furnishes a clear answer.

The term “commissioner of public works, or other properly constituted authority,” as used in the statute, requires interpretation. From the history and context of the section, the “commissioner of public works” must mean the board of public works (consisting of commissioners) in cities where they exist and have supervision over construction and maintenance of streets. 1 “Other properly constituted authority” is construed to mean the public body having supervision over construction and maintenance of the highway in question similar to the supervision vested in the board of public works in cities where such boards exist. In the case before us the properly constituted authority was the state highway commission.

Mr. Gerke had had no written authority from the highway commission (or any other body) to interfere, with the Power Company’s line. Whatever duty the Power Company had to remove it, the clear terms of sec. 66.047, Stats. 1959, prohibited his knocking it down. Recovery by the Power Company of its damage was properly allowed.

2. Contractor’s cause of action for interference with the conduct of his business. Mr. Gerke contends that the Power Company wrongfully interfered with the conduct of his business by leaving the line in place. At the trial he proved that he was hampered in the use of some of his machinery by the presence of the line. It was not only a physical barrier, but a source of great hazard if parts of his machine came close enough to the line for the electricity to arc from the line to the machine.

“. . . one who, without a privilege to do so, induces or otherwise purposely causes a third person not to . . . per *187 form a contract with another, ... is liable to the other for the harm caused thereby.” 2

Here it is the one whose acts are interfered with who seeks redress because the performance of his contract was made less profitable. It has been recognized that,

“. . . the value of a bargain may be impaired although there is no failure of performance. In such a case, it may be the promisor rather than the promisee who sustains the loss. Thus, any conduct which is intended to and which, in fact, makes performance more onerous is, unless privileged, a tort against the promisor.” 3

We have no difficulty with the concept of the cause of action Mr. Gerke asserts he has, but we do have difficulty with its application to the circumstances now under consideration.

The Power Company served about 50 customers west of 1-90 by means of the transmission line involved here. It had a permit from the town board of the town of Burke. 4 Before the laying out of 1-90, the line apparently complied with all requirements. The construction of 1-90 brought about two new duties: (1) The Power Company must change its lines on a permanent basis so that it would provide at least 22 feet of clearance above the surface of 1-90 when finished, 5 either by raising the line in approximately *188 the same location, along State Trunk Highway 19, or by relocating the line elsewhere so as to cross with proper clearance; 6 (2) if the performance of the work of construction at any time made some additional temporary change reasonably necessary to enable the accomplishment of such work, the Power Company must make such temporary change. 6a

As applied to the circumstances of this case, the two duties are somewhat interwoven. The least drastic and least expensive method of fulfilling the first duty would be to raise the wires along approximately the same route by the use of taller poles. Gerke claimed, however, that neither a 42-foot nor even a 60-foot clearance over ground level would fulfil the second duty. A complete rerouting of the line so that the crossing would occur at a point where ground conditions were different and would not require the same type of operations as Gerke was performing, would be more expensive, and would apparently fulfil both duties. Presumably the representatives of the Power Company thought that such rerouting would involve a greater change than reasonably necessary for Gerke to perform his work.

If Mr. Gerke’s only complaint was that the Power Company should have raised its line to a 42-foot clearance above ground level, and if he claimed that he could have carried on his work with the line at that height, and if he had given *189 proper notice 7 we would have no difficulty in concluding that the Power Company’s deliberate delay in raising its line would entitle Gerke to damages for intentional, unprivileged interference with his performance of his contract. This, however, is not the situation, as it is Gerke’s position that he could not operate his machine with a clearance of 42 or even 60. feet, as offered August 13th.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tele-Port, Inc. v. Ameritech Mobile Communications, Inc.
49 F. Supp. 2d 1089 (E.D. Wisconsin, 1999)
Magnum Radio, Inc. v. Brieske
577 N.W.2d 377 (Court of Appeals of Wisconsin, 1998)
Sampson Investments v. Jondex Corp.
499 N.W.2d 177 (Wisconsin Supreme Court, 1993)
Kerns v. Madison Gas & Electric Co.
396 N.W.2d 788 (Court of Appeals of Wisconsin, 1986)
Liebe v. City Finance Company
295 N.W.2d 16 (Court of Appeals of Wisconsin, 1980)
Sprecher v. Weston's Bar, Inc.
253 N.W.2d 493 (Wisconsin Supreme Court, 1977)
Wisconsin Gas Co. v. Craig D. Lawrenz & Associates, Inc.
241 N.W.2d 384 (Wisconsin Supreme Court, 1976)
Chrysler Corp. v. Lakeshore Commercial Finance Corp.
389 F. Supp. 1216 (E.D. Wisconsin, 1975)
St. Francis Savings & Loan Ass'n v. Hearthside Homes, Inc.
221 N.W.2d 840 (Wisconsin Supreme Court, 1974)
Lorenz v. Dreske
214 N.W.2d 753 (Wisconsin Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
121 N.W.2d 912, 20 Wis. 2d 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-power-light-co-v-gerke-wis-1963.