Kerns v. Madison Gas & Electric Co.

396 N.W.2d 788, 134 Wis. 2d 387, 1986 Wisc. App. LEXIS 4022
CourtCourt of Appeals of Wisconsin
DecidedOctober 28, 1986
Docket85-0772
StatusPublished
Cited by2 cases

This text of 396 N.W.2d 788 (Kerns v. Madison Gas & Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kerns v. Madison Gas & Electric Co., 396 N.W.2d 788, 134 Wis. 2d 387, 1986 Wisc. App. LEXIS 4022 (Wis. Ct. App. 1986).

Opinion

DYKMAN, J.

Richard and Kathleen Kerns, personal injury plaintiffs, petitioned for leave to appeal from a nonfinal order granting partial summary judgment in favor of MG&E. We granted the petition. The court dismissed plaintiffs’ claims that MG&E maintained its electrical transmission line below clearance requirements in violation of the electrical code, Wis. Adm. Code, sec. PSC 114 (February, 1982) 1 and the statutes, secs. 196.64, 2 196.67 3 and 196.74, 4 Stats. *390 (1981-82), causing plaintiffs’ damages. MG&E does not challenge plaintiffs’ common law negligence claims on summary judgment. Because we conclude that no genuine issue of material fact exists as to whether MG&E violated the statutes or the electrical code, we affirm the trial court’s order granting partial summary judgment.

FACTS

Richard was injured in 1982 when a metal pole he was holding came in contact with an MG&E electric transmission line. MG&E acquired the line in 1917. At the time of the accident, Richard was standing on the roof of a two-story building which had been constructed beneath MG&E’s line in 1946 as a one-story building. The building’s second story, which reduced the line’s clearance below code requirements, was constructed in 1956. It is undisputed that MG&E last modified the conductors in 1950 and that the line’s clearance complied with the vertical clearance requirements of the 1944 Wisconsin State Electrical Code, Volume I which was in effect in 1950. 5 From 1956 until Richard’s accident, no administrative authority required MG&E to increase the clearance. Section PSC 114.05(2).

*391 SUMMARY JUDGMENT METHODOLOGY

Section 802.08(2), Stats., provides that summary judgment will be granted when there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. When reviewing a grant of summary judgment, we follow the same methodology as the trial court. That methodology is detailed in In re Cherokee Park Plat, 113 Wis.2d 112, 116, 334 N.W.2d 580, 582-83 (Ct.App. 1983), and we will not repeat it here.

PLEADINGS AND AFFIDAVITS

Our review of the pleadings and affidavits reveals that the material facts are undisputed. The second amended complaint states a claim and MG&E’s answer joins issue. Plaintiffs and MG&E submitted the affidavits of their respective experts. However these affidavits do not raise any issue of material fact. They offer conflicting opinions as to whether MG&E violated the statutes and the code and whether the “existing installation” provision applies to the line. Whether the “existing installation” provision applies and whether MG&E violated the statutes and the code are questions of law. Backhaus v. Krueger, 126 Wis.2d 178, 180, 376 N.W.2d 377, 378 (Ct.App. 1985). The affidavits set forth conclusions of law, not disputed facts. Where only a question of law remains, it may properly be decided on summary judgment. Konkel v. Town of Raymond, 101 Wis.2d 704, 707, 305 N.W.2d 190, 192 (Ct.App. 1981).

*392 STATUTORY AND CODE VIOLATIONS

MG&E argues that the line is an “existing installation” under Wis. Adm. Code, sec. PSC 114.05(2) (February, 1982) because it was in place when the building’s first and second stories were built beneath it. MG&E contends that the line complied with the code at the time Richard was injured and that compliance with the code constitutes compliance with sec. 196.74, Stats. Therefore, plaintiffs are not entitled to treble damages under sec. 196.64.

Plaintiffs argue that MG&E had a duty under the electrical code to raise the line after the 1956 addition reduced the clearance, and that MG&E cannot rely on the “existing installation” provision to relieve itself of that duty. They also argue that MG&E breached a separate statutory duty under sec. 196.74, Stats., because the line’s reduced clearance was not “reasonably adequate and safe.” Plaintiffs contend that MG&E’s violation of sec. 196.74 entitles them to treble damages under sec. 196.64.

Plaintiffs concede that whether MG&E had a duty under the code to increase the clearance depends largely on interpretation of the code’s existing installation provision, sec. PSC 114.05(2), which states:

(a) Existing installations, including maintenance replacements, which comply with prior editions of the code, need not be modified to comply with this chapter except as may be required for safety reasons by the administrative authority.
(b) Where conductors or equipment are added, altered, or replaced on an existing structure, the structure or the facilities on the structure need not be modified or replaced if the resulting installation *393 will be in compliance with the rules which were in effect at the time of the original installation.

“We interpret administrative regulations in the same manner as we interpret statutes.” Uebele v. Oehmsen Plastic Greenhouse Mfg., Inc., 125 Wis.2d 431, 434, 373 N.W.2d 456, 458 (Ct.App. 1985). “Interpretation of a regulation is governed by its language.” Larsen v. Wisconsin Power & Light Co., 120 Wis.2d 508, 513, 355 N.W.2d 557, 560 (Ct.App. 1984). If that language is plain and clearly understood, that meaning must be given to the regulation. Stoll v. Adriansen, 122 Wis.2d 503, 510, 362 N.W.2d 182, 186 (Ct.App. 1984). We will apply rules of construction only if the provision is ambiguous. A regulation is ambiguous if well-informed individuals could understand the regulation in different ways. Uebele, 125 Wis.2d at 434, 373 N.W.2d at 458. Plaintiffs do not argue that the existing installation provision is ambiguous. We conclude that the regulation is unambiguous on its face.

The language of the existing installation provision is plain and clearly understood: An existing installation which complies with prior editions of the code need not be modified to comply with the current code unless the PSC has ordered the installation brought into compliance. Section PSC 114.05(2)(a). We reject plaintiffs’ argument that the existing installation provision only applies to changes in code requirements and not to changes in the installation’s surroundings. The provision does not make that distinction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franklin v. Housing Authority of Milwaukee
455 N.W.2d 668 (Court of Appeals of Wisconsin, 1990)
Local Union No. 2490 v. Waukesha County
422 N.W.2d 117 (Court of Appeals of Wisconsin, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
396 N.W.2d 788, 134 Wis. 2d 387, 1986 Wisc. App. LEXIS 4022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kerns-v-madison-gas-electric-co-wisctapp-1986.