Wire Corp. v. United States

166 F. Supp. 744, 143 Ct. Cl. 688, 1958 U.S. Ct. Cl. LEXIS 185
CourtUnited States Court of Claims
DecidedOctober 8, 1958
DocketNo. 19-54
StatusPublished
Cited by1 cases

This text of 166 F. Supp. 744 (Wire Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wire Corp. v. United States, 166 F. Supp. 744, 143 Ct. Cl. 688, 1958 U.S. Ct. Cl. LEXIS 185 (cc 1958).

Opinion

Littleton, Judge,

delivered the opinion of the court:

Plaintiff has brought this suit to recover sums alleged to be due it under a contract with defendant acting through the Army Signal Corps. Defendant has counterclaimed for amounts alleged to be due it under the same contract.

In 1950 the Army Signal Corps was interested in obtaining a high production of a new type of telephone cable it had designed and which was of value in the Korean War then in progress. The new cable, known as “spiral-four cable”, could carry twelve simultaneous conversations, whereas the type previously used had a capacity of only one conversation in each direction. Contracts for the production and supply of this new cable were entered into by the Signal Corps with sis of the major cable producers in the country.

One of the components of the outside covering of the new cable was a woven or braided mesh of stainless steel, nonmagnetic wire .015 in diameter. This wire was not produced [690]*690by the six companies holding prime contracts with the Army, but was in turn obtained by them from subcontractors.

Plaintiff interested itself in producing the .015 steel wire, and by October 1951 had obtained five purchase order subcontracts to produce the wire for cable companies with prime contracts with the Army.

In support of the efforts of the prime contractors to acquire this part of the cable-covering the Army, after making a survey in the industry, entered into what are known as “special facilities contracts” with subcontractors and those who desired to obtain such subcontracts.

A special facilities contract is a contract with the Government wherein equipment and machinery is bought and installed in a plant of a contractor to increase its productive capacity. The machinery is ordered, installed and paid for in the first instance by the contractor. When it has been inspected and approved by the agency and when actual payment by the contractor has been established, the contractor is reimbursed. When the equipment and machinery has been paid for by the Government by way of reimbursement, title to the same passes to and remains in the Government. The equipment and machinery are to be used in connection with the Government work of the particular agency involved and cannot be used for other Government work or for commercial work, unless there is express written authority to do so.

Following its acquisition of the subcontracts, plaintiff began negotiations with the Army relative to acquiring a special facilities contract. The Army raised two questions with respect to plaintiff’s capabilities to produce the wire. The first was the matter of plaintiff’s plant which the Army found too small, and the second, concerned plaintiff’s financial condition. Plaintiff had applied to the Eeconstruction Finance Corporation for a loan, and the EFC, after being assured that a special facilities contract would be given to plaintiff if the loan could be secured, granted a loan in the sum of $75,000. Plaintiff thereupon purchased a new plant, which the Army had recommended as being satisfactory, and vacated its old one. A later loan of $150,000 was secured from the EFC for use as working capital. The first loan was secured by a mortgage on the real estate and the other by [691]*691a mortgage on plaintiff’s equipment, machinery and other personal property.

On February 11,1952, plaintiff and defendant entered into a contract entitled “Special Facilities Contract” under which certain facilities in the total value of $98,753.92 were to be installed in plaintiff’s plant for use in producing the .015 steel wire. By supplemental agreement this amount was later raised to $100,504.19. Plaintiff was one of ten companies to be awarded a special facilities contract with respect to the production of the spiral-four cable.

Plaintiff’s experience in producing the wire with which it had had no prior experience was not very successful. In the spring of 1952, despite the availability of raw materials and labor, plaintiff could not meet the delivery dates and quality requirements contained in its subcontracts because of manufacturing difficulties. Although plaintiff by means of trial and error, overcame such manufacturing difficulties and produced wire which met the necessary standards, it never was able to fulfill all its orders for the wire, even during the latter period of its production when the spiral-four cable program was cut back because of the turn of events in the Korean War. Production of 75,000 pounds per month was estimated as needed in order for plaintiff to meet its obligations to the RFC. It never approached that capacity, and despite the RFC loans and the installation of the Government-owned equipment, plaintiff lacked sufficient credit and necessary equipment. The Army subsequently granted plaintiff permission to use the installed machinery and equipment to do commercial as well as other Government work, but by mid-1953 plaintiff’s plant was idle because of lack of working funds, although it had a backlog of both Government and commercial orders.

On July 15, 1953, the Army terminated the special facilities contract, and plaintiff was eventually petitioned into bankruptcy by its creditors. After establishing title thereto, the Army removed its machinery and equipment from plaintiff’s plant. This suit has been brought by plaintiff in its own name with the knowledge, acquiescence and approval of the trustee in bankruptcy, for the benefit of its creditors and for its own benefit.

[692]*692After the facilities called for under the contract were installed, plaintiff submitted vouchers to defendant totalling $102,806.78. Of this amount, plaintiff was paid only $94,184.24 leaving unpaid on such vouchers the amount of $8,622.54. Plaintiff claims that it is entitled to be paid some $27,709.04 for equipment and machinery although its actual recorded expenditures, not all of which are supported by vouchers, totaled only $109,765.82. If such expenditures were incurred in the amount recorded on its books, this would leave a difference of only $15,581.08 between the recorded expenditure of $109,765.82 and the $94,184.24 already received by plaintiff, and not the $27,709.04 claimed. In addition to the $94,184.08 already paid to plaintiff, the record establishes that only $9,542 was actually paid out by plaintiff and not reimbursed by defendant, and of that amount only $8,622.54 was covered by vouchers submitted to the Army.

The Government admits that there is due and owing to plaintiff $5,377.08 of the above $8,622.54. Defendant denies liability for the remaining $3,245.46 on the grounds that as to part of the amount plaintiff has failed to show actual payment to suppliers, and as to the other part of the amount plaintiff failed to render proper billing. For reasons which will be explained hereinafter in connection with our discussion of item one of defendant’s counterclaim, we hold that plaintiff is entitled to recover the $3,245.46 as well as the $5,377.08 which defendant admits is due and owing plaintiff.

Under the first item of its counterclaim, defendant says that there is due the Government by plaintiff the sum of $12,818.55 which sum was paid to plaintiff by way of reimbursement on vouchers 1-8 inclusive, in connection with the installation of machinery and equipment. This $12,818.55 is composed of costs the payment of which was later disapproved in the amount of $4,372.20 and was suspended in the amount of $8,446.35, as the result of a reaudit by the Government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
166 F. Supp. 744, 143 Ct. Cl. 688, 1958 U.S. Ct. Cl. LEXIS 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wire-corp-v-united-states-cc-1958.