Wing Aviation, LLC v. Art Balmanno D/B/A Paint Booth Services
This text of Wing Aviation, LLC v. Art Balmanno D/B/A Paint Booth Services (Wing Aviation, LLC v. Art Balmanno D/B/A Paint Booth Services) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Wing Aviation, L.L.C. appeals the trial court's judgment for $11,188.44 in damages in favor of Art Balmanno d/b/a Paint Booth Services. We affirm the judgment on the contract claim.
Wing hired a general contractor, Southwest Refinishing Systems, Inc., to construct a paint booth facility at the Montgomery County Airport. Southwest subcontracted with Balmanno to provide and install the paint booth's exhaust ducts. Balmanno agreed to additional duct work at the request of Wing's representatives. Balmanno invoiced Wing for the additional labor and materials but never received payment.
Balmanno sued Wing and Southwest for "suit on account" and quantum meruit. The trial court entered a default judgment against Southwest. After a bench trial, the court held Wing directly responsible for the additional work Wing requested of Balmanno. The final judgment found Wing and Southwest jointly and severally liable, and awarded Balmanno actual damages of $11,188.44, prejudgment interest, and attorney's fees.
Wing presents two issues. First, Wing contends that because the express contracts between Wing and Southwest and Southwest and Balmanno covered the services or materials for which Balmanno seeks recovery, Balmanno is precluded from recovering from Wing under quantum meruit. Second, Wing argues there was no open account agreement between Wing and Balmanno. We address Wing's second issue as it is dispositive. (1)
In a suit on account, a plaintiff is required to prove: (1) the sale and delivery of merchandise or performance of services; (2) that the amount of the account is "just," that is, the prices charged are pursuant to an express agreement, or in the absence of an agreement, that the charges are usual, customary, or reasonable; and (3) that the outstanding amounts remain unpaid. Powers v. Adams, 2 S.W.3d 496, 499 (Tex. App.--Houston [14th Dist.] 1999, no pet.); see also Worley v. Butler, 809 S.W.2d 242, 245 (Tex. App.--Corpus Christi 1990, no writ); Tex. R. Civ. P. 185. Wing argues Balmanno cannot recover on this claim. Instead, Wing claims it could only be liable to Balmanno through a "pass through claim," which may permit a general contractor to bring an action against the owner if the general contractor is liable to the subcontractor. We disagree.
The dispute revolves around whether a separate contract existed between Balmanno and Wing. The controversy relates to Wing's instructions to Balmanno for duct work offsets and for duct work welding instead of silicone sealing. Balmanno testified that the original duct-work bid that he provided to Southwest involved twelve exhausts with the duct work going straight through the roof. Balmanno testified Wing representatives later informed him that the duct work would require "offsets" because the exhaust fans were moved on the exhaust plenum. Brian Wing, president of Wing, testified the "offsets" were necessary because of Southwest's poor planning and Southwest's failure to timely provide Wing with plans and specifications. Balmanno testified that when he informed Wing's representatives the offsets were going to cost more, Wing instructed him to do the offsets. Balmanno completed the duct work according to Wing's instructions.
As to the silicone sealing, Balmanno testified he was required to deliver the materials thirty to forty-five days before installation. In order to comply with the request, he delivered the stacks prior to preparing them for installation. He explained that rust appears on ninety-nine percent of the flanges his company buys, and any rust is remedied when the stacks are "cleaned up, primered, and painted" before installation. Balmanno had not yet completed cleaning, priming, and painting the flanges.
According to Brian Wing, the exhaust stacks were "rusting very badly" and the silicone was coming off. When he expressed his concern in a meeting attended by Gregg Goza, president of Southwest, Wing representatives, and Balmanno, Goza offered to take the exhaust stacks back to the shop and rework them. Balmanno testified that Wing requested the changed duct work and when Balmanno explained it would cost more, Wing's representatives told him to go ahead with the welding. Balmanno did the welding as instructed. (2)
The contract between Wing and Southwest provided that Southwest would "[c]omplete electrical wiring, airlines, plumbing and duct work" for the paint booth. According to Balmanno, Southwest hired his company to "furnish and install the exhaust ducts for the exhaust." Balmanno says that offsets requested by Wing representatives were not a part of his contract with Southwest. He stated that if the offsets had been a part of his contract with Southwest, Goza would have informed him of it. Brian Wing admitted that four months before the lawsuit was filed, he acknowledged to Balmanno the changes made to the intake were "engineering changes." Goza testified Southwest hired Balmanno's company to install the two air makeup systems, complete the duct work on the exhaust, and do the elbows and connections for the duct work. Goza testified the extra work by Balmanno was provided at Wing's request and that the extra work was "in excess of the original scope of the project." Balmanno introduced into evidence Southwest's letter to Brian Wing in which Southwest stated:
[T]he issues here relate to work performed beyond the scope of work [Southwest] had contracted [Balmanno] to do. The work [Southwest] contracted [Balmanno] to complete was in accordance to Standard Building Codes which all parties had agreed upon when the project was initiated. [Southwest] paid [Balmanno] accordingly.
The billings in question were additions on the job site requested and approved by WING personnel (i.e. Carlin and Frank). These requests or orders are recognized in the industry as "Changes of Order" and were given by WING, therefore to be billed separately and directly to WING as these specifications were not a part of [Southwest's] contract with either WING or [Balmanno].
Wing asserts the contract between Wing and Southwest was not "complete" until the offset duct work was finished.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Wing Aviation, LLC v. Art Balmanno D/B/A Paint Booth Services, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wing-aviation-llc-v-art-balmanno-dba-paint-booth-s-texapp-2006.