['WINDOW SPECIALISTS, INC. v. FORNEY ENTERPRISES, INC.']

26 F. Supp. 3d 52, 2014 U.S. Dist. LEXIS 34702, 2014 WL 1015717
CourtDistrict Court, District of Columbia
DecidedMarch 18, 2014
DocketCivil Action No. 2011-1610
StatusPublished
Cited by5 cases

This text of 26 F. Supp. 3d 52 (['WINDOW SPECIALISTS, INC. v. FORNEY ENTERPRISES, INC.']) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
['WINDOW SPECIALISTS, INC. v. FORNEY ENTERPRISES, INC.'], 26 F. Supp. 3d 52, 2014 U.S. Dist. LEXIS 34702, 2014 WL 1015717 (D.D.C. 2014).

Opinion

OPINION

ROSEMARY M. COLLYER, United States District Judge

Plaintiff, sub-subcontractor Window Specialists, Inc., brought suit for breach of contract against Forney Enterprises, Inc., alleging that Window Specialists was wrongfully terminated and it is owed monies for labor and materials. Forney Enterprises countersued for breach of contract and indemnification, contending that the work done by Window Specialists was substandard. Plaintiff now moves for partial summary judgment. As explained below, the motion will be granted in part.

I. FACTS

The contract at issue here arose from a U.S. Army project to improve property at Fort McNair in Washington, D.C. General contractor, IIU Consulting Institute, Inc. (IIU), entered into a contract with the Army for the McNair improvements, and Hanover Insurance executed a performance bond on the contract. See Compl. [Dkt. 1], Ex. 1 (Performance Bond and Army/IIU Contract). 1 In December of 2010, IIU subcontracted with Forney Enterprises, Inc. (Forney), and Forney in turn subcontracted with Window Specialists, Inc. (WSI) for labor and material for the supply and installation of over 680 windows and over 60 doors at Fort McNair. Compl. ¶ 11; id, Ex. 2 (For-ney/WSI Contract). The Army found various deficiencies in the work on the project and on May 25, 2011, the Government’s contracting officer sent IIU a 10-day cure notice. Id, Ex. 3 (Cure Notice). The Cure Notice stated:

Work performed thus far by contractor has been substandard and poorly executed. Means and methods used for all aspects of work show lack of professional experience and unqualified technicians onsite performing the work. Demolition has been performed recklessly and restoration of openings cannot be done properly because the substrate has been butchered to the point that [it] inhibits the proper application of follow-on material, i.e., trim, stop, storm windows, etc. Additionally, new window units were installed but left unfinished for days allowing drafts and insects to enter despite attempts at sealing surrounds with insulation. Windows and storm windows were not measured and verified for proper sizing prior to demolition creating situations where ill-fitting windows and storm windows were installed regardless. ... Poor joinery of trim had resulted in open joints filled with caulk to compensate for the poor cuts. Finish caulking was not tooled properly nor wiped down to achieve a finished appearance. ...
Some windows - would be considerably square where as some would have a 2" space from the sill to bottom of the glazing stop on one side and have a 2 %" space on the other side. The fact that the holes for our balances to go into were unsquare was a huge issue in this situation....
Window manufacturer claims that many windows were not measured correctly and will not function correctly in their current state. Contractor has made negative comments onsite to me ... about the quality of windows and that this product is not the correct applica *55 tion for the job. If this is so, why.,wasn’t an alternative product that meets historical requirements and is a better fit offered prior to ordering 600 units that may not work?

Id.; see also Opp’n [Dkt. 43], Ex. 1 (Ukoh Aff.) 2 ¶ 8.

Forney claims that the majority of the issues in the Cure Notice had to do with WSI’s poor workmanship. See Opp’n at 4. WSI hotly contests this, alleging that the deficiencies were all within IIU’s scope of work because IIU did not properly supervise, prepare the window and door openings, or perform the trim work after installation. Mot. for Partial Summ. J. [Dkt. 41-1] at 2-4. Under the Forney/WSI contract, WSI’s scope of work excluded demolition and interior trim. See Forney/WSI Contract.

The window deficiencies were not corrected, and on June 29, 2011, IIU sent a notice of termination to Forney. Compl., Ex. 9 (Notice of Termination). On September 20, 2011, Forney formally terminated WSI. According to IIU, all window installation done by WSI was demolished, and all windows were reordered and reinstalled. Ukoh Aff. ¶ 20. IIU also asserts that none of the doors purchased by WSI could be used, and all of the doors were reordered. Id. ¶ 21. Because IIU claimed that WSI’s work was deficient, it did not pay WSI’s second, third, and fourth payment applications, totaling $936,967.00. 3

WSI disputes that its work was in any way deficient and seeks payment on its contract with Forney. On September 7, 2011, WSI filed a Complaint against For-ney, Hanover, IIU, and John McHugh, Secretary of the Army, alleging:

Count I, breach of contract against For-ney;
Count II, unjust enrichment against Forney;
Count III, performance of payment bond against Hanover;
Count IV, injunctive relief against For-ney, IIU, and Secretary McHugh; and Count V, injunctive relief against For-ney.

See Compl. ¶¶ 35-93.

Subsequently, WSI voluntarily dismissed Secretary McHugh and general contractor IIU. See Notice of Dismissal [Dkt. 8]. WSI also voluntarily dismissed Count IV, which sought an injunction to permit WSI to continue working on the project. Id. WSI also sought an injunction to prevent Forney from terminating WSI. See Compl., Count V. However, Forney terminated WSI on September 20, 2011, and WSI has waived its claim for injunction by not prosecuting it. In addition, the Court granted Forney’s motion to dismiss Count II for failure to state a claim. See Order [Dkt. 27]. Thus, the Complaint remains pending against only two parties on two separate counts: against Forney on Count I for breach of contract and against Hanover on Count III for performance of the payment bond.

Forney filed a two-count Counterclaim, alleging breach of contract and indemnification. See Countercl. [Dkt. 23]. IIU informed Forney that it held Forney responsible for damages allegedly caused by WSI, including the cost to reprocure, repair, and complete WSI’s work on the project. Ukoh Aff. ¶ 25. IIU settled its claims against Forney without a lawsuit. IIU agreed, in a written settlement agree *56 ment, to limit its recovery against Forney to “those amounts Forney recovers from WSI in this litigation, less Forney’s lost profits.” Id. ¶26; see Opp’n, Ex. 3 (Settlement Agreement).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parker v. John Moriarty & Associates
District of Columbia, 2018
Parker v. John Moriarty & Assocs. of Va., LLC
332 F. Supp. 3d 220 (D.C. Circuit, 2018)
Berlin v. Bank of America, N.A.
101 F. Supp. 3d 1 (District of Columbia, 2015)
Winston & Strawn LLP v. the Law Firm of John Arthur Eaves
47 F. Supp. 3d 68 (District of Columbia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
26 F. Supp. 3d 52, 2014 U.S. Dist. LEXIS 34702, 2014 WL 1015717, Counsel Stack Legal Research, https://law.counselstack.com/opinion/window-specialists-inc-v-forney-enterprises-inc-dcd-2014.