Winder v. Caldwell

55 U.S. 434, 14 L. Ed. 487, 14 How. 434, 1852 U.S. LEXIS 456
CourtSupreme Court of the United States
DecidedFebruary 15, 1853
StatusPublished
Cited by51 cases

This text of 55 U.S. 434 (Winder v. Caldwell) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winder v. Caldwell, 55 U.S. 434, 14 L. Ed. 487, 14 How. 434, 1852 U.S. LEXIS 456 (1853).

Opinion

Mr. Justice GRIER

delivered the opinion of the court.

Caldwell, who was plaintiif below, entered’ into a contract With Winder, “ to furnish ajl the materials and do all the carpenter work required to a certain house to be erected in the city of Washington,” for the sum of ten thousand dollars. After the house was finished, .the contractor filed a lien against the building,..claiming this sum, together with sundry charges for extra' work. A scire facias was issued to enforce this claim, and *443 a trial hád, in the course of which, numerous bills of exception were sealed by the court at the defendant’s instance, which form the subjects for our consideration in this case.

1. The want of a declaration, though not the subject of exception below, has. been urged here as an error- But we think this objection is without foundation..

A scire facias is a judicial writ used to enforce, the execution of some matter of record on which it is usually founded; but though a judicial writ, or writ of. execution, it is so far an-ori-' ginal that the defendant may plead to it. As it discloses the facts on which it is foupded, and requires an answer from the defend-1 ant, it is in the nature of a declaration, and the plea is properly to the writ. In the present case the bill of particulars of the plaintiffs claim is filed of record under the statute whieh gives this remedy, and it is recited in the writ and thereby made part of it, so that any further pleading on his part, to set forth the nature of his demand, would De-wholly superfluous.

2. In the written contract between the parties, given in evidence on the trial, it is stipulated that “ the work is to be promptly , executed, so that no delay shall be occasioned to the builder by having to wait for the carpenter’s work;” and also.,' that in-any and every case in which the carpenter shall occasion delay to the building the sum of twenty-five dollars per day shall be deducted for each and every day so delayed, from the amount to be. paid by this contract.”

The defendant, under a notice of set-off, ■ offered to prove “ that in consequence of the plaintiff’s not being ready to put up his work according to said contract,'delay was occasioned by him' in the construction of the building of not less' than three weeks;” and also, “ that the work and materials found and provided upon and for the said building, were defective in .quality and- character, and far inferior in value to what said contract and specification called for.”

The refusal of the court to permit such evidence to go to the jury, is the subject of the first two bills of exception.

The statute which authorizes this proceeding, gives the defendant liberty “ to plead and make such defence as in personal actions for the recovery of debts.” Had the plaintiff below brought his action of assumpsit on the contract, the right to make this defence cannot now be doubted. Por, although it is true, as a general rule, that unliquidated damages cannot be the subject of set-off, yet it is well settled that a total or partial failure of' consideration, acts of nonfeasance, or misfeasance, immediately connected with the cause of' action, Or any equitable defence arising out of the same transaction, may be given in evidence in mitigation of damages, ot recouped ; not. strictly *444 by way of defalcation or set-off, .but for the purpose of defeating the plaintiff’s action in whole or in*part, and to avoid circuity of action.' Without ndticing the numerous cases on this subject, it is sufficient to say that the cases of Withers v. Green, (9 How. 214,) and Van Buren v. Digges, (11 How. 461,) decided in .this court, are conclusive of the question. The court below, therefore, erred in the rejection of the testimony offered.

3. The remaining bills of exception, involve, in fact, but one prominent and important question, and the decision of it will dispose of this case.

The right to file a “mechanic’s lien,”, as it is .usually denominated, is claimed by the.plaintiff, under the act of Congress of March 2d, 1833, entitled,-“An act to secure to mechanics and others, payment for. labor done and materials furnished, in the erection of buildings in the District of Columbia.” The first section oí- -this act,' defines the persons who shall be entitled to this peculiar security arid remedy, as follows:

“All and every dwelling-house, or other building, hereafter constructed arid erected within the city of Washington, in the town of Alexandria, or in Georgetown, in the District of Columbia, shall be subject to the payment of the'debts contracted for, or by reason of any work done, or materials found and provided. by any brickmaker, bricklayer, stonecutter, mason, lime-merchant, carpenter, painter and glazier, ironmonger,-blacksmith', plasterer and lumber-merchant, or any other person or persons employed in furnishing materials for, or in erecting and constructing such house or other building, before any other lien which originated subsequent to the commencement of such house, or other building. But if such dwelling-house or other building, or any portion thereof, shall have been constructed under contract, or contracts, entered into by the owner thereof, or his or her agent, with (any person or persons, no person who may have done work for such, contractor or contractors, or furnished materials to him, or on his order or authority, shall have or possess any lien on said house or other building, for work done, or fnaterials so furnished, unless the person or persons employed by such contractor to do work-on, or furnish materials'for, such. building, shall, within thirty days after being so employed, give notice in writing to the owrier or owners of such building, or to his or to their agent, that, he or they are so employed to work or to furnish materials, and that they claim the benefit of the lien granted by this act.” .

Does a master-builder, undertaker, or contractor, who undertakes, by contract with the owner, to erect a building, or some part or portion thereof, on certain terms, come within the letter oi spirit of this act, or within any of • the classes enumerated, as *445 entitled to this special remedy.? Such persons have an opportunity, and are capable of obtaining their own securities. They-do npt labor as mechanics, but superintend work done by others. They are not tradesmen in lumber, or other materials for building, but employ others to furnish materials. If such contractor should by accident be a carpenter, or an owner or vendor of lumber, yet he deals not with the owner in this capacity, but as an undertaker, who has covenanted for his own securities.

■ The title to this act shows its policy and intention. It is to secure, to “ mechanics and others, payment for labor done and materials found;” and the persons enumerated in the first section are, plainly, those mechanics and tradesmen whose personal labor or property have been incorporated into the building, and not the agents, supervisors, undertakers, or contractors, who employed them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lofchie v. Washington Square Ltd. Partnership
580 A.2d 665 (District of Columbia Court of Appeals, 1990)
Griffith v. Butler
571 A.2d 1161 (District of Columbia Court of Appeals, 1990)
United States v. Steese
144 F.2d 439 (Third Circuit, 1944)
Orsi v. Hall
8 Conn. Super. Ct. 92 (Connecticut Superior Court, 1940)
Hoffman v. Gleason
107 F.2d 101 (Sixth Circuit, 1940)
Smith v. O'Connor
88 F.2d 749 (D.C. Circuit, 1936)
Parker v. Tilghman v. Morgan, Inc.
183 A. 224 (Court of Appeals of Maryland, 1936)
Pure Oil Co. v. Cornish
1935 OK 1133 (Supreme Court of Oklahoma, 1935)
Manzo v. United States
66 F.2d 579 (Eighth Circuit, 1933)
Western Surety Co. v. United States
51 F.2d 470 (Ninth Circuit, 1931)
Myers v. Hurley Motor Co.
273 U.S. 18 (Supreme Court, 1927)
Baldwin Locomotive Works v. Edward Hines Lumber Co.
125 N.E. 400 (Indiana Supreme Court, 1919)
Muir v. Chatfield
255 F. 24 (Second Circuit, 1918)
Universal Transp. Co. v. National Surety Co.
252 F. 293 (S.D. New York, 1918)
Maynard v. Lange
143 P. 648 (Oregon Supreme Court, 1914)
Vandalia Railroad v. Stillwell
104 N.E. 289 (Indiana Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
55 U.S. 434, 14 L. Ed. 487, 14 How. 434, 1852 U.S. LEXIS 456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winder-v-caldwell-scotus-1853.