Willowbrook Development Corp. v. Pollution Control Board

416 N.E.2d 385, 92 Ill. App. 3d 1074, 48 Ill. Dec. 354, 1981 Ill. App. LEXIS 2043
CourtAppellate Court of Illinois
DecidedJanuary 27, 1981
Docket80-585
StatusPublished
Cited by20 cases

This text of 416 N.E.2d 385 (Willowbrook Development Corp. v. Pollution Control Board) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Willowbrook Development Corp. v. Pollution Control Board, 416 N.E.2d 385, 92 Ill. App. 3d 1074, 48 Ill. Dec. 354, 1981 Ill. App. LEXIS 2043 (Ill. Ct. App. 1981).

Opinion

Mr. JUSTICE REINHARD

delivered the opinion of the court:

This case involves an appeal pursuant to section 41 of the Environmental Protection Act (Ill. Rev. Stat. 1979, ch. llBz, par. 1041) from an order of the Illinois Pollution Control Board (Board) entered on July 3, 1980. Section 41 of the Act provides, in pertinent part, that “any person who has been denied a variance ” ° may obtain judicial review directly in the Appellate Court for the District in which the cause of action arose and not in the Circuit Court” (Ill. Rev. Stat. 1979, ch. llBz, par. 1041). The appellant, and petitioner below, Willowbrook Development Corporation (Willowbrook), had requested a variance from the Board to connect and operate a sewer extension to serve 152 units of the developer’s planned Lake Willow Way development in Willowbrook, Illinois. The Board, however, in its order, granted the requested variance for only 52 of the units at Lake Willow Way. Willowbrook is seeking a reversal of that portion of the order which failed to grant a variance for the remaining 100 units planned for Lake Willow Way.

The facts involved are set out in detail since they are dispositive of this case. Willowbrook is the developer of Lake Willow Way, which is projected to comprise 38 multifamily structures and a total of 152 coach-house units. The project is located in Du Page County, Illinois, and occupies a 17.5-acre parcel containing a 4.5-acre man-made lake. In March 1976, Willowbrook’s engineers requested a preliminary opinion and evaluation of the proposed sewer system from the Illinois Environmental Protection Agency (EPA). The EPA responded by letter dated March 23, 1976, indicating that, according to their records, the Du Page County Marionbrook Sewage Treatment Plant (Marionbrook) had adequate capacity to accept the additional flow from the planned project (then planned as an apartment complex) and, therefore, had no objection to the proposed sewer system. The EPA did point out, however, that the Board’s Rules and Regulations require that a permit be obtained prior to the installation of the sewer system.

Approximately three years later, in March 1979, Willowbrook submitted to the EPA an application for a permit to construct and operate a sanitary sewer extension for Lake Willow Way. The EPA responded by letter dated April 13,1979, that they must deny the permit since they lack the “statutory authority to permit sewer extensions when the receiving sewers or treatment plants are already overloaded,” referring to the Marionbrook treatment plant. The EPA further pointed out, however, that where the following two conditions are satisfied, they are able to issue special permits for construction only and not operation: (1) The owner of the overloaded facility has received a permit from the EPA to install additional or upgraded facilities which will have sufficient capacity to handle the load anticipated from the sewer extension under consideration, and (2) all contracts necessary for the completion of the construction of the additional facilities have been signed and ratified by the responsible authorities. Those two conditions were satisfied in approximately July 1979.

On September 17,1979, Willowbrook submitted an application to the EPA for the above-described “Construct Only Permit” and the permit was issued by the EPA on September 26, 1979. Construction began at Lake Willow Way in the first week of December 1979. The terms of both the application and the permit itself provided that the permit was for construction only and did not authorize actual operation of the facilities. The terms of each provided that operation of the facilities constructed would be contingent upon the issuance of an “Operating Permit” by the EPA. EPA Technical Policy WPG — 5 provides that “[t]he issuance of a Construct Only Permit to the applicant is a method for allowing the construction of a sanitary sewer which, due to projected sewerage facilities’ improvements, can become operational at a time consistent with completion of sewerage facilities improvements.”

On April 30, 1979, some five months prior to issuing the Construct Only Permit to Willowbrook, the EPA notified the Du Page County Department of Public Works (DCDPW) that it was placing their Marion-brook plant on “Restricted Status” because it was operating at 102 percent of its EPA rated capacity. Restricted Status is defined in EPA Technical Policy WPG — 4 as “the Agency determination * * * that a sewer has reached hydraulic capacity or that a sewage treatment plant has reached design capacity, such that additional sewer connection permits may no longer be issued without causing a violation of the Act or Regulations.” EPA Technical Policy WPG — 4 further provides that notification of Restricted Status shall be sent to the owner of the treatment facility (in this case DCDPW) and that a list of the plants subject to Restricted Status shall be published and made available upon request as well as published in the Pollution Control Board’s publication, Environmental Register, which was done by the EPA.

Subsequent to receiving the Construct Only Permit, Willowbrook had little or no contact with the EPA and was not informed that the Marionbrook plant was on Restricted Status. Willowbrook agents communicated frequently with DCDPW employees regarding the status of the improvements at the Marionbrook facility and were informed repeatedly that improvements were underway to increase plant capacity from 4 MGD (million gallons per day) to 5 MGD, which would enable them to accommodate flows from Lake Willow Way and that upon completion of the plant modifications, operating permits could be obtained from the EPA. The village of Willowbrook issued building permits in December 1979, and construction began shortly thereafter. Despite the frequent communications between Willowbrook and DCDPW, DCDPW never informed Willowbrook that the Marionbrook plant was on Restricted Status. Willowbrook first learned of the Restricted Status classification in April 1980, in conversation with an EPA employee. On April 4, 1980, Willowbrook filed a petition for variance with the Board pursuant to section 37 of the Environmental Protection Act (Ill. Rev. Stat. 1979, ch. HIM, par. 1037) seeking permission to connect a sewer extension to serve the 152 units projected for Lake Willow Way. The EPA filed a written recommendation that the petition for variance be denied. The variance hearing was held on June 20 and June 21, 1980. At the conclusion of testimony, the Board entered an opinion and order granting a variance for only 52 of the 152 units planned for Lake Willow Way.

At the Board hearing, Mr. Donald Schuster, president of Willow-brook Development Corporation, testified that the Corporation had already expended approximately $1,100,000 in land and site improvements, $2,000,000 in building construction and $150,000 in general and administrative expenses; that Willowbrook had undertaken extensive land clearing and excavation, installed sewer and water mains for the entire development, had done some paving and had eight buildings (32 units) at various stages of completion. Schuster testified that the denial of a variance for Lake Willow Way would result in the bankruptcy of himself personally and the Willowbrook Development Corporation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Environmental Protection Agency v. Pollution Control Board
721 N.E.2d 723 (Appellate Court of Illinois, 1999)
EPA v. Pollution Control Board
Appellate Court of Illinois, 1999
Petersen v. Chicago Plan Comm'n
Appellate Court of Illinois, 1998
Petersen v. CHICAGO PLAN COM'N
707 N.E.2d 150 (Appellate Court of Illinois, 1998)
Trochelman v. Village of Maywood
631 N.E.2d 334 (Appellate Court of Illinois, 1994)
Abernathy v. Board of Education of Community High School District No. 218
611 N.E.2d 1022 (Appellate Court of Illinois, 1992)
Anane v. Pettibone Corp.
560 N.E.2d 1088 (Appellate Court of Illinois, 1990)
Corkill Electric Co. Ex Rel. Illinois Petroleum Co. v. City of Chicago
554 N.E.2d 1027 (Appellate Court of Illinois, 1990)
Environmental Protection Agency v. Fitz-Mar, Inc.
533 N.E.2d 524 (Appellate Court of Illinois, 1988)
Central Illinois Light Co. v. Pollution Control Board
511 N.E.2d 269 (Appellate Court of Illinois, 1987)
Central Illinois Public Service Co. v. Pollution Control Board
491 N.E.2d 176 (Appellate Court of Illinois, 1986)
Bodine v. Bodine
489 N.E.2d 911 (Appellate Court of Illinois, 1986)
Coca-Cola Co. Foods Division v. Olmarc Packaging Co.
620 F. Supp. 966 (N.D. Illinois, 1985)
Willowbrook Motel, Partnership v. Pollution Control Board
481 N.E.2d 1032 (Appellate Court of Illinois, 1985)
Carey v. City of Rockford
480 N.E.2d 164 (Appellate Court of Illinois, 1985)
Tyska v. BOARD OF EDUCATION TWP. SCH. DIST.
453 N.E.2d 1344 (Appellate Court of Illinois, 1983)
E & E HAULING, INC. v. Pollution Control Bd.
451 N.E.2d 555 (Appellate Court of Illinois, 1983)
Dwyer v. Graham
442 N.E.2d 298 (Appellate Court of Illinois, 1982)
Gary-Wheaton Bank v. Burt
433 N.E.2d 315 (Appellate Court of Illinois, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
416 N.E.2d 385, 92 Ill. App. 3d 1074, 48 Ill. Dec. 354, 1981 Ill. App. LEXIS 2043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/willowbrook-development-corp-v-pollution-control-board-illappct-1981.