Williston Basin v. FERC

CourtCourt of Appeals for the Eighth Circuit
DecidedJune 27, 2000
Docket98-4079
StatusPublished

This text of Williston Basin v. FERC (Williston Basin v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williston Basin v. FERC, (8th Cir. 2000).

Opinion

United States Court of Appeals FOR THE EIGHTH CIRCUIT ___________

No. 98-4079/99-3554 ___________

Williston Basin Interstate Pipeline * Company, * * Petitioner, * * v. * * On Petition for Review of Federal Energy Regulatory * Orders of the Federal Commission, * Energy Regulatory Commission. * Respondent; * * Northern States Power Company, * * Intervenor on Appeal. * ___________

Submitted: March 15, 2000 Filed: June 27, 2000 ___________

Before RICHARD S. ARNOLD, LAY, and BEAM, Circuit Judges. ___________

RICHARD S. ARNOLD, Circuit Judge.

Williston Basin Interstate Pipeline Company petitions for review of six administrative orders issued by the Federal Energy Regulatory Commission. All six orders interpret a contract between Williston Basin and the Northern States Power Company. We hold that the Federal Energy Regulatory Commission correctly interpreted the contract, and therefore affirm the first four orders. We hold that we do not have jurisdiction to review the final two orders, but this holding has no practical significance, since we are deciding the underlying substantive question, the meaning of the contract.

I.

Williston Basin Interstate Pipeline Company is an interstate natural gas pipeline company that operates in Montana, North Dakota, South Dakota, and Wyoming. Northern States Power Company supplies residential and commercial customers in North Dakota and Minnesota with natural gas. In 1991, Northern States and Williston entered into negotiations for Williston to build a 50-mile addition to Williston's pipeline system that would allow it to transport natural gas for Northern States.

Pursuant to Section 7(c) of the Natural Gas Act, 15 U.S.C. §717f(c), Williston filed an application with the Federal Energy Regulatory Commission, requesting a certificate of public convenience and necessity to construct the pipeline and transport the natural gas. As part of the application, Williston included a proposed new tariff to cover this service. Williston generally uses what is referred to as the "FT-1" rate schedule. The proposed tariff for the Williston-Northern States deal was called Rate Schedule X-13. The Commission issued a certificate authorizing Williston to construct and operate the pipeline and related facilities to transport gas for Northern States. However, the Commission directed that some changes be made to Rate Schedule X-13. The Commission required Williston to recover the costs of the new service through an "incremental rate."1

1 Additionally, the Commission set the initial rate, contained in Rate Schedule X- 13, at $19.5778 per 1,000 cubic feet of gas.

-2- In response to the Commission's directive to use an incremental rate, Williston and Northern States submitted a Service Agreement. Article V of this Service Agreement requires Williston to recalculate ("restate") the X-13 rate on March 1, 1995, and to continue its recalculations every two years until the X-13 rate equals or falls below Williston's generally available FT-1 rate. The agreement states that these rate restatements are "pursuant to Section 4 of the Natural Gas Act." When the X-13 rate equals or falls below the FT-1 rate, Northern States will pay a rate equal to the FT-1 rate, and the X-13 rate will no longer be restated. Exhibit A and Schedule A of the Service Agreement also provide that in calculating and restating the X-13 rate, Williston will use two cost components – the return-on-equity and depreciation rates – that it uses in calculating its FT-1 Rate Schedule. The contract states that in using these FT-1 cost components, Williston will use Rate Schedule FT-1 "as such may be in effect from time to time."

A brief discussion of the Commission's role under the Natural Gas Act will be useful in explaining Williston's and Northern States' problems under this contract. Under Section 4 of the Natural Gas Act, 15 U.S.C. §717c, if a pipeline such as Williston proposes to change its existing rates, the pipeline has the burden of demonstrating to the Commission that its proposed change is just and reasonable. If the pipeline proposes a rate increase, the Commission can allow the pipeline to put its new rate into effect (making it the "effective" rate), but subject to investigation and refund. This means that if the Commission ultimately determines that the proposed rate was not just and reasonable, the Commission can order the pipeline to refund the difference between the "effective" rate and the rate the Commission ultimately decides is just and reasonable. In contrast, under Section 5 of the Natural Gas Act, 15 US.C. §717d, if the Commission decides to review a pipeline's rates that are already unconditionally in place, it has power to grant only prospective relief.

On March 1, 1995, pursuant to the contract, Williston restated its X-13 rate for the first time. The FT-1 rate used to calculate this restatement (Docket No. 92-163)

-3- was one that had been effective, subject to investigation and refund, since November 1, 1992. The Commission took note of the fact that the return-on-equity and depreciation rates underlying the restated X-13 rate were tied to those underlying the FT-1 rate, which was itself subject to refund. Therefore, the Commission made the X-13 rate also subject to refund pending the outcome of the ongoing rate case in the FT-1 docket. This is the first order that Northern States is challenging here. Williston sought rehearing of this order, arguing that because the restated X-13 rate was lower than the initial X-13 rate, the Commission lacked authority to make the restated rate subject to refund. The Commission denied the request for rehearing, reasoning that because the X-13 rate was not yet final, it was not yet certain that the restated X-13 rate would actually be a decrease. The Commission's denial of rehearing is the second order that Williston is challenging here.

Shortly thereafter, the Commission finished its investigation of the FT-1 rate (Docket No. 92-163) that had been used in calculating Williston's first restatement. The Commission issued orders that, inter alia, lowered the return-on-equity and depreciation rates for this FT-1 rate. These orders required Williston to lower this FT-1 rate retroactively for its effective period, which was November 1, 1992 through August 1, 1995.2 The Commission then directed Williston to recalculate its first restatement of the X-13 rate to reflect the lower return-on-equity and depreciation rates of the underlying FT-1, and to refund the overcharges. The Commission also ordered

2 This action did not yet finalize the FT-1 rate in Docket No. 92-163. Williston challenged this decision in the D.C. Circuit. That Court remanded the order back to the Commission for further consideration of the return-on-equity rate imposed on Williston. Williston Basin Interstate Pipeline v. FERC, 165 F.3d 54, 62-63 (D.C. Cir. 1999). Recently Williston Basin entered into a settlement agreement involving the return-on-equity rate, and this settlement agreement was approved by the Commission. As such, the cost components of the FT-1 rate involved in calculating Williston's 1995 X-13 restatement are now final. The motion of Northern States to file a supplemental appendix containing the settlement agreement is granted.

-4- Williston to follow a similar procedure in its subsequent biennial filings. This is the third order Williston challenges here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Williston Basin v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williston-basin-v-ferc-ca8-2000.