Willis Alan Hizar and Roofmasters DFW, LLC v. Kenneth Heflin and Anna Heflin

Court of Appeals of Texas·Decided July 10, 2023·No. 05-21-00936-CV·Published

Opinion

Affirmed in Part, Reversed and Remanded in Part, and Opinion Filed July 10, 2023

S In The

Court of Appeals

Fifth District of Texas at Dallas No. 05-21-00936-CV

WILLIS ALAN HIZAR AND ROOFMASTERS DFW, LLC, Appellants V.

KENNETH HEFLIN AND ANNA HEFLIN, Appellees

On Appeal from the County Court at Law No. 7 Collin County, Texas

Trial Court Cause No. 007-01345-2020

OPINION

Before Justices Partida-Kipness, Nowell, and Wright1 Opinion by Justice Partida-Kipness This proceeding arises from a dispute between homeowners and a contractor

concerning removal of popcorn ceiling from a residential property. In the trial court, the homeowners, appellees Kenneth Heflin and Anna Heflin, accused appellants Willis Alan Hizar and Roofmasters DFW, LLC of failing to comply with discovery. The trial court granted the Heflins’ motion to compel production and ultimately ordered Roofmasters and Hizar’s pleadings struck for failure to comply with the trial court’s orders compelling discovery. Roofmasters and Hizar appeal the default

1 The Hon. Carolyn Wright, Justice, Assigned

judgment rendered following the issuance of death penalty sanctions and a bench trial.

BACKGROUND

Hizar is the managing member of Roofmasters DFW, LLC.2 The company’s charter was forfeited on February 28, 2020. The following day, Kenneth Heflin entered into a contract with “Hizar f/k/a Roofmasters” for the removal of the popcorn ceiling in the Heflins’ home and application of a smooth finish in its place. Anna Heflin did not sign the contract. Kenneth agreed to pay $8,600.00 for the project. That price included $6,300.00 for removal of the popcorn texture, $500.00 to prime the ceiling with Kilz, and $1,800.00 to apply a smooth surface to the ceilings. The quote included notes stating that the price for a smooth surface was listed in the quote, but the Heflins would decide “if they want a smooth finish or a light knockdown after job is started and a test area for smooth finish and light knockdown is applied in hallway.” Kenneth agreed to pay fifty percent “upon acceptance of the quote” and the balance “the day of project completion.” Kenneth paid Hizar $3,350.003 by check on Friday, March 6, 2020, and Hizar began work on the project.

2 The certificate of formation for Roofmasters lists the entity name as “RoofMasters-DFW LLC.” The parties’ contract also refers to “RoofMasters-DFW LLC.” The parties, however, refer to RoofMasters-DFW LLC as “Roofmasters DFW, LLC” or “Roofmasters” throughout their briefing here and in the trial court. We will follow the parties’ lead and refer to “RoofMasters-DFW LLC” as “Roofmasters DFW, LLC” or “Roofmasters.”

3 $3,350.00 is half of the quoted costs for popcorn texture removal and priming the ceiling.

Kenneth testified that Hizar said the project would be completed within three or four days. But after starting work, Hizar informed the Heflins that the project would take an additional four or five days because the popcorn ceiling was more difficult to remove than he anticipated. Hizar testified that the difficult removal of the popcorn ceiling kept him “from making a smooth surface from scraping it off” and required him “to do something else to make it smooth.” According to Hizar, the “something else” was putting a coat of mud over the popcorn texture. Hizar testified that he told the Heflins one coat of mud would cost an additional $1,800, and if two coats were required, the total additional cost would be $4,000 to $5,000.

The Heflins maintained, however, that they did not agree to any additional cost. Anna testified that Hizar texted the Heflins on Sunday, March 8, 2020, and asked them to meet him at the house because he had encountered a problem. According to Anna, they met with Hizar immediately and were told that it would be hard to apply a smooth surface because Hizar could not get the popcorn texture to come off. If they wanted a smooth surface, Hizar said the price would increase. But Hizar told the Heflins that he could apply a texture instead that would cost less than the original quoted price for a smooth surface. The Heflins agreed to a textured finish because that was the less expensive and quicker option.

On March 12, 2020, Kenneth paid Hizar an additional $1,400. According to Kenneth, the $1,400 payment was for materials to finish the job. Kenneth considered

the second payment to be “an additional advancement” of money toward the total contract price.

The Heflins inspected the work done by Hizar the following Saturday, March 14, 2020. They found the work incomplete and defective. Photos admitted into evidence at trial showed lines on the ceiling, inconsistent texture, and overspray texture on light fixtures, ceiling fans, and other fixtures. Anna described the work as follows:

It was not a knockdown texture. It had trowel marks, it had scrapings.

Some areas were smooth, some were textured, some were more popcorn; the joints, the overspray down on it. All of our ceiling fixtures were still covered in plastic. All of our smoke detectors were removed with tape on them. It wasn’t a complete job. He admitted it wasn’t a complete job.

Hizar testified that he completed the work the Heflins paid for, which included applying one coat of mud, knockdown texture, and two coats of paint to the ceilings. He contended the ceilings “needed another coat of mud,” but the Heflins would not pay for it, so he applied only one coat of mud and left the job:

Q: Now, when you say you completed the scope of the everything [sic]

in the work, what was done?

A: I removed the popcorn texture to the best of my ability. I primed all the ceilings with KILZ. I put one coat of mud on the whole ceilings. In the trade it’s called skim coating. So I coated the ceilings with mud.

Then I textured with knockdown texture and painted with two coats of paint, and then we cleaned our mess up and loaded the truck up and that was it.

Q: Out of the additional work that you recommended to the Heflins, what remained to be done?

A: The ceilings -- before the texture was applied, the ceilings needed another coat of mud.

Q: And why was it you left the job?

A: I was done. They didn’t want to pay the extra money to have another coat of mud, and give me more time to do what needed to be done, so I finished the job, what’s listed in the scope of work, and that was it.

On March 14, 2020, Hizar abandoned the work on the Property prior to completion of the Project. The Heflins hired JMS Drywall to complete the project and paid $3,500.00 for their work.

PROCEDURAL HISTORY

Hizar sought payment of $7,400.00 from the Heflins plus daily late fees of 6.5%. According to Hizar, he provided labor and materials “worth at least $12,150.00,” which left a balance of $7,400.00 after subtracting the Heflins’ prior payments. On April 16, 2020, counsel for the Heflins sent Hizar a demand letter in which they disputed the amount owed and sought payment from Roofmasters and Hizar for the damage caused by the defective and incomplete work and additional damage caused to the Property. On May 29, 2020, Roofmasters and Hizar filed a lien affidavit against the Property in the amount of $7,400.00. On June 19, 2020, the Heflins sued Hizar. In a September 11, 2020 order, the trial court removed the lien on the Property and awarded the Heflins attorney’s fees of $3,389.84. Thereafter, Hizar filed a counterclaim and Roofmasters filed a plea in intervention. The Heflins named Roofmasters a defendant in their first amended petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Willis Alan Hizar and Roofmasters DFW, LLC v. Kenneth Heflin and Anna Heflin, (Tex. Ct. App. 2023).

Willis Alan Hizar and Roofmasters DFW, LLC v. Kenneth Heflin and Anna Heflin (Willis Alan Hizar and Roofmasters DFW, LLC v. Kenneth Heflin and Anna Heflin) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wal-Mart Stores, Inc. v. Canchola
121 S.W.3d 735 (Texas Supreme Court, 2003)
Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Cire v. Cummings
134 S.W.3d 835 (Texas Supreme Court, 2004)
Shell Oil Co. v. HRN, Inc.
144 S.W.3d 429 (Texas Supreme Court, 2004)
Varner v. Cardenas
218 S.W.3d 68 (Texas Supreme Court, 2007)
Medical City Dallas, Ltd. v. Carlisle Corp.
251 S.W.3d 55 (Texas Supreme Court, 2008)
HRN, Inc. v. Shell Oil Co.
102 S.W.3d 205 (Court of Appeals of Texas, 2003)
Crown Life Insurance Company v. Casteel
22 S.W.3d 378 (Texas Supreme Court, 2000)
In Re Polaris Industries, Inc.
65 S.W.3d 746 (Court of Appeals of Texas, 2001)
Van Es v. Frazier
230 S.W.3d 770 (Court of Appeals of Texas, 2007)
Allan v. Nersesova
307 S.W.3d 564 (Court of Appeals of Texas, 2010)
Central Forest S/C Partners, Ltd. v. Mundo-Mundo, Inc.
184 S.W.3d 296 (Court of Appeals of Texas, 2006)
Alan Reuber Chevrolet, Inc. v. Grady Chevrolet, Ltd.
287 S.W.3d 877 (Court of Appeals of Texas, 2009)
Andras v. Memorial Hospital System
888 S.W.2d 567 (Court of Appeals of Texas, 1994)
Morey v. Page
802 S.W.2d 779 (Court of Appeals of Texas, 1990)
Davenport v. Scheble
201 S.W.3d 188 (Court of Appeals of Texas, 2006)
Kindred v. Con/Chem, Inc.
650 S.W.2d 61 (Texas Supreme Court, 1983)
Davis v. Kaufman County
195 S.W.3d 847 (Court of Appeals of Texas, 2006)
Allied Resources Corp. v. Mo-Vac Service Co.
871 S.W.2d 773 (Court of Appeals of Texas, 1994)