Williams v. Department of Highways

92 So. 2d 98
CourtLouisiana Court of Appeal
DecidedJanuary 2, 1957
Docket4332
StatusPublished
Cited by13 cases

This text of 92 So. 2d 98 (Williams v. Department of Highways) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams v. Department of Highways, 92 So. 2d 98 (La. Ct. App. 1957).

Opinion

92 So.2d 98 (1957)

Dr. Donald B. WILLIAMS, Plaintiff-Appellee,
v.
The DEPARTMENT OF HIGHWAYS of the State of Louisiana, Defendant-Appellant.

No. 4332.

Court of Appeal of Louisiana, First Circuit.

January 2, 1957.
Rehearing Denied February 4, 1957.

*100 W. Crosby Pegues, Jr., D. Ross Banister, Philip K. Jones, Baton Rouge, for appellant.

LeBlanc & Summers, Abbeville, for appellee.

TATE, Judge.

This suit seeks to enjoin the Department of Highways from continuing with certain construction upon plaintiff's land in connection with the improving of Louisiana Highway 339 in Lafayette Parish. The Department appeals from the injunction issued against it, and the landowner answered the appeal requesting that the injunction be broadened.

Along with 77 other landowners, plaintiff Dr. Williams had in May, 1955, executed a deed conveying to the Department a right of way "of a width not to exceed eighty (80') feet, measuring forty (40') feet in width on each side of the centerline of the existing roadway."

It is not denied that the eighty-foot right of way which the Department actually proposes to use for the new highway lies entirely east of the present right of way, and almost or entirely east of and outside the right of way described in the deed. East of the new highway, the Department also planned and started construction of a new cut, or drainage draw, approximately 40 feet in width, consuming another 40 feet off the western end of plaintiff's property; and it therefore constructed within a few days of the present suit a "right of way fence" approximately 120 feet within plaintiff's property, and approximately 150 feet from the center line of the existing roadway—bounding a strip some 110 feet deeper than the right of way deed calls for, and altogether approximately 600 feet in length.

Citing Raxsdale v. Highway Commission, La.App. 2 Cir., 1 So.2d 342, certiorari denied, appellant Department relies solely upon LSA-R.S. 48:219:

"After the department has laid out a highway over a certain tract of land and the work thereon has commenced without objection on the part of the landowner, the landowner may not prevent or retard the construction thereof by any legal process, but is limited to an action for damages."

Plaintiff landowner replies that the statute is unconstitutional; and alternatively, that he objected before operations commenced on his land.

The right of a citizen to have judicially determined the public need for his property and to receive payment for it (either personally or by deposit in the register of the court) before it is taken from him is one of his fundamental liberties and is guaranteed to him by Article 1, Section 2[1] and Section 6,[2] and by Article *101 4, Section 15,[3] of the Louisiana Constitution. LSA Article VI, Section 19.1, Louisiana Constitution authorizes the Legislature to provide for the taking of property for highway purposes by ex parte court order prior to final judgment in expropriation suits, "provided that provision be made for deposit before such taking" of the estimated value and damages. (Italics ours.)

Within the past several months, our Supreme Court has reaffirmed the constitutional right to receive compensation for private property before the public taking, holding void for this reason a police jury taking of private property for road purposes when payment was not tendered until sixteen days after the taking; and further holding that "notice and an opportunity to be heard and to defend in an orderly proceeding" are constitutional requisites to afford due process before such taking, Charles Tolmas, Inc., v. Police Jury, La., 90 So.2d 65, at page 68. See also: DeBouchel v. Louisiana Highway Commission, 172 La. 908, 135 So. 914; Bickham v. City of Shreveport, 156 La. 648, 101 So. 8.

Counsel for the Department has ably argued in brief and oral argument that the necessities of efficient highway construction and of avoiding undue expense by interruptions or relocations demand our sustaining the constitutionality of the Department's construction of the statute that a landowner's claim is relegated to damages and he is barred from enjoining construction, once a contract has been let and work has been started upon a given highway project. The sincerely claimed power of the State through the Highway Department to preclude a citizen's fundamental right to have the necessity for the public taking judicially determined and the court-ordered compensation paid or deposited before the taking, is repugnant to the cited provisions of our Constitution.

The Second Circuit Raxsdale case, cited by the Department, is not authority to the contrary, since the landowner did not appeal from the award to him of damages on his alternative demand, granted instead of an injunction; the remarks upon which appellant relies are by way of dicta, and were made without apparent consideration of the consitutional provisions and jurisprudence thereunder upon which we reply.

While, if required, the Department's construction of the statutory provision would render it unconstitutional, in our opinion; in accordance with the presumption of constitutionality of legislative enactments, a statute will be sustained when a constitutional construction can be given it, as over an unconstitutional construction urged. Meyer v. Board, 199 La. 633, 6 So.2d 713; Parker v. Board, La.App. 1 Cir., 84 So.2d 80. Insofar as it might apply to a situation where the landowner stands by without objection or protest, permitting the State to commence substantially work on his tract, the statute may probably be sustained on a theory of estoppel or implied consent. See Carroll v. Louisiana Highway Commission, 177 La. 865, 149 So. 503, where the landowner did not seek to enjoin the State from proceeding with construction until approximately two years after the preparatory work of constructing the road-bed had been completed.

But this is not the situation with which we are here faced. Dr. Williams, the landowner, signed the right of way deed in May, 1955. In due course, the contract *102 was let in January, 1956. Approximately the last week of February, 1956, Dr. Williams came by his place and saw workmen driving test pilings for a new bridge about 200 feet north of his property. From the location of this bridge, and from conversations with the workmen there, according to his testimony, he realized for the first time that the new highway would deviate substantially from the old roadway, and claim far more land for the right of way than he had conveyed. It is confirmed by the Department District Engineer that Dr. Williams saw him at once, before further work was done, complaining that the construction plans together with new cut or drainage draw would encroach greatly upon his property and deny him highway access to the west end thereof. The Engineer forwarded on Dr. Williams' complaints and proposed changes to Department headquarters in Baton Rouge.

Nevertheless, heavy equipment was moved to the area on March 6, 1956, and excavation of a deep drainage cut about 35 feet wide at the top and 20 feet wide at the bottom was commenced at once. A right of way fence was erected 120 feet inside the western edge of plaintiff's property, and a bulldozer commenced leveling the land proposed to be utilized for the new highway roadbed, by knocking down knolls and spoil piles and filling in gulleys.[4] Approximately the day the dragline commenced operations, Dr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion Number
Louisiana Attorney General Reports, 2007
State ex rel. Department of Highways v. Terral
206 So. 2d 307 (Louisiana Court of Appeal, 1968)
Gray v. State, Through Department of Highways
191 So. 2d 802 (Louisiana Court of Appeal, 1967)
Tennessee Gas Transmission Co. v. Violet Trapping Co.
176 So. 2d 425 (Supreme Court of Louisiana, 1965)
Poirier v. T. L. James & Co.
163 So. 2d 171 (Louisiana Court of Appeal, 1964)
State Ex Rel. Sabine River Authority v. Phares
159 So. 2d 144 (Supreme Court of Louisiana, 1963)
Collector of Revenue v. Mossler Acceptance Co.
139 So. 2d 263 (Louisiana Court of Appeal, 1962)
Cobb v. Louisiana Board of Institutions
111 So. 2d 126 (Supreme Court of Louisiana, 1959)
State Licensing Bd. of Con. v. State Civil Serv. Com'n
110 So. 2d 847 (Louisiana Court of Appeal, 1959)
State Ex Rel. Department of Highways v. MacAluso
106 So. 2d 455 (Supreme Court of Louisiana, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
92 So. 2d 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-department-of-highways-lactapp-1957.