William Cramp & Sons Ship & Engine Building Co. v. United States

50 Ct. Cl. 179, 1915 U.S. Ct. Cl. LEXIS 107, 1915 WL 1109
CourtUnited States Court of Claims
DecidedMarch 8, 1915
DocketNo. 26398
StatusPublished
Cited by6 cases

This text of 50 Ct. Cl. 179 (William Cramp & Sons Ship & Engine Building Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William Cramp & Sons Ship & Engine Building Co. v. United States, 50 Ct. Cl. 179, 1915 U.S. Ct. Cl. LEXIS 107, 1915 WL 1109 (cc 1915).

Opinion

Booth, Judge,

reviewing the facts found to be established, delivered the opinion of the court:

This case is again before the court on motion for new trial by both claimants and defendants.

The claimant company, on October 1, 1898, entered into a contract with the defendant to construct the battleship Maine. The claimant was to furnish all the necessary material entering into the vessel except the armor and armament and to complete the same within 32 months from the date of the contract, viz, June 1, 1901. The defendants agreed to furnish the armor specified in clause 3 of the contract “ within the times and in the order required to carry on the work properly.” The claimant subsequent to the execution [181]*181of the contract proceeded upon the preliminary arrangements necessary for its proper performance ordered materials, made plans, etc., up to a time when it became a conceded and apparent fact that the defendants would be unable to comply with their engagement respecting the armor. The defendants did not furnish the necessary armor until long after it was needed by the claimant to finish the vessel within the contract period. The last armor plate was delivered by the defendants on August 12, 1902,14 months and 11 days after the date of completion fixed by the contract. The defendants also defaulted in the delivery of armament, augmenting the delay occasioned by the failure to deliver armor to the extent of 2 months and 27 days. The present suit to recover damages for the above defaults was commenced October 11, 1904, and in the petition then filed the ad damnum was stated at $148,868.32; subsequently, on May 18,1912, in an amended petition, this was increased to a total demand of $390,672.32.

The case is not susceptible of differentiation in any of its aspects from a similar case of Wm. Cramp & Sons v. United States, 6216 U. S., 494, except as to proof and measurement of damages claimed. In the former^ase, which involved the construction of the U. S. S. Alabama, the Supreme Court passed directly upon all the contentions put in defense here respecting the liability of the defendants, the rights of the claimant to avail itself of the privileges set forth in clause 3 of the contract, and the legal effects of the inserted proviso to the final release. The above case, taken in connection with an earlier suit between the same parties involving the construction of the U. S. S. Indiana, 206 U. S., 118, precludes a repeated discussion of these issues, despite the vigor and ability with which the same are urged.

The vital distinction between this and former cases of similar import revolves exclusively about the quantum of damages. There is absolutely no room for dispute as to important facts. Dates speak for themselves. The Secretary of the Navy conceded defendants’ default, extended the contract period, and remitted all claims for liquidated damages. It was physically and legally impossible for the defendants to comply with their obligations under the contract; they made no pretense of doing so. It would be idle and meaning[182]*182less to extend an investigation into tbe realm of conjecture in an attempt to ascertain wbat might have happened if the defendants had complied with their undertaking, upon which the claimant’s obligations expressly depended. There is no possible way of ascertaining whether the claimant could have executed its contract if. the defendants had not defaulted; the presumptions are all in its favor. It had executed contracts of like magnitude and possessed the facilities as well as the technical ability to do so again. The defendants are obviously in no position to assert such a contention in the face of express admissions of default, which, to say the least, prevented the experiment. Pickley v. United States, 46 C. Cls., 77.

The claimant’s progress toward complying mwith the time limit fixed by the defendants in the contract was dependable entirely upon defendants’ obligation to perform a condition precedent. The defendants defaulted and imposed upon the company an extended delay of 18 months and 27 days. The courts have frequently adjudicated cases involving similar conditions; the liability has been determined. Alabama case, supra; Weeks v. Little, 89 N. Y., 566; District of Columbia v. Camden Iron Works, 181 U. S., 453; United States v. Behan, 110 U. S., 338.

In the cases involving the Alabama and Indiana claimant company presented a specific bill of damages, involving a direct pecuniary loss. In this case it is impossible to do likewise. A short time after commencing the construction of the vessel it became notoriously apparent that the defendants would not be in a position to furnish the armor in the order and at the times needed to complete the work. The Secretary of the Navy was powerless so to do because of legislative inhibitions as to price and the unwillingness of armor makers to accede to the same. The claimant under these conditions retarded work on the vessel, employing the bulk of its force on other work in its yard, important and pressing. Up to the time the contract for armor was let by the Secretary, on November 28, 1900,. work on the Maine had been abnormally slow; subsequent to that time, however, work was greatly accelerated and rapid progress made. The shipbuilders were ready for the armor when furnished. The [183]*183vessel under normal conditions should have been launched in 18 months from the date of the contract. Instead, however, she was not launched until 34 months from the date of the contract, occupying the claimant’s building slip for a time 16 months in excess of the normal period. The claim, therefore, as well stated in claimant’s brief, becomes a property loss as distinguished from one capable of specific proof of a pecuniary outlay. In other words, as to this particular item the damage suffered was the loss to the claimant of its use of the building slip during the deferred period — a loss incapable of direct proof. Claimant company predicates its loss upon the ascertained value of their entire plant less 25 per cent, deducted because of use of yard for other purposes than shipbuilding, and proportion said value among its building slips employed in constructing vessels, claiming a return thereon of 6 per cent per annum.

In this connection it is proper to observe that in ascertaining the intrinsic value- of the slip, wharfage value must be included in making up the total value of the entire plant. Wharfage is an indispensable adjunct to the slip; without wharves the slips would be useless. The two are inseparable, and to ascertain the proportionate value of one the proportion must include the value of the other. Hence, as shown in Finding XI, wharfage is included. This identical method has been heretofore employed by the United States in similar cases and payments made thereunder.

Defendants assail this contention, attacking it because of uncertainty and remoteness, and charging the claimant with dereliction in not prosecuting its work to all possible limits, irrespective of defendants’ default» The findings establish indisputably that the claimant company could have prosecuted work on the vessel to the point of launching, for up to the normal period fixed for said event the defendants’ defaults caused no delay, and the court has computed the delay period from this date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
Tester Corp. v. United States
30 Cont. Cas. Fed. 70,544 (Court of Claims, 1982)
Harvey Ward Locke v. United States
283 F.2d 521 (Court of Claims, 1960)
James Stewart & Co. v. United States
63 F. Supp. 653 (Court of Claims, 1946)
Globe Works v. United States
53 Ct. Cl. 532 (Court of Claims, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
50 Ct. Cl. 179, 1915 U.S. Ct. Cl. LEXIS 107, 1915 WL 1109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-cramp-sons-ship-engine-building-co-v-united-states-cc-1915.