William C. Chapman v. Orange Rice Milling Company, and Edward J. Stine

747 F.2d 981, 1984 U.S. App. LEXIS 16254
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 3, 1984
Docket83-2653
StatusPublished
Cited by34 cases

This text of 747 F.2d 981 (William C. Chapman v. Orange Rice Milling Company, and Edward J. Stine) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
William C. Chapman v. Orange Rice Milling Company, and Edward J. Stine, 747 F.2d 981, 1984 U.S. App. LEXIS 16254 (5th Cir. 1984).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

A lessor of a large tract of ranch land appeals from a take-nothing judgment following a bench trial in this Texas diversity action for breach of contract. While the district court found that the lessee had breached his lease by not clearing sufficient acreage, it held the contract claim barred by the applicable four-year statute of limitations. Persuaded of a different reading of the schedule for clearing under the lease, we conclude that the breach sued for came later than found by the district court, and that the lessor’s claim was not time-barred. We reverse and remand.

I

William C. Chapman owns approximately 18,000 acres of wooded land in Red River and Bowie Counties, Texas. In June of 1967 he entered into a written ten-year lease of this tract with the president of Orange Rice Milling Company, Edward J. Stine. 1 Orange Rice Milling leased the land from July 1, 1967 to June 31, 1977 for farming and cattle ranching. As part of its consideration, Orange Rice Milling agreed that “[djuring the ten (10) year period of the lease” it would “clear and keep cleared a minimum of 7,000 acres.” According to the schedule set in the lease, “a minimum of 700 acres” would be cleared “each year during said term with a minimum of 4,000 acres cleared on or before July 1, 1970.” Orange Rice Milling cleared 4,000 acres by July of 1970 as required, and both parties believed that the remaining acreage had been substantially cleared by the early 1970’s. Orange Rice Milling vacated the property when its lease terminated in December of 1978. 2 In 1979, Chapman began leasing the land to others for farming. A March 1980 Department of Agriculture overfly map indicated that Orange Rice Milling had cleared only 5,226 acres of Chapman’s land, 1,774 acres fewer than the contractual minimum. Chapman filed suit for breach of contract on May 21, 1980.

At the conclusion of the evidence, the district court requested legal memoranda on certain issues, including “[wjhether the matter of limitations applies in this case or not, and if so, how it applies.” The district court then issued its findings of fact and conclusions of law, holding that Orange Rice Milling breached its lease by failing to clear 1,744 acres, damaging Chapman in the amount of $244,160. It went on to hold, however, that the defendant had *983 “raised the affirmative defense of limitation during the course of the trial,” and that the action was barred by Texas’ four-year statute of limitations for suits on written contracts. Tex.Rev.Civ.Stat.Ann. art. 5527 (Vernon Supp.1984). The court entered a take-nothing judgment against Chapman.

II

-1-

In holding Chapman’s contract claim barred by Texas’ applicable statute of limitations, the district court read the lease schedule to require that Orange Rice Milling complete its 7,000 acre clearing obligation by July of 1975. 3 Reasoning that 4,000 acres were, as both parties agreed, cleared by July of 1970 as required, and that the lease also required a minimum of 700 acres to be cleared “each year thereafter,” the contractual obligation mathematically had to be completely performed, and any breach established, by July 1, 1975. The district court held that as Chapman should have known of the termination of the defendant’s clearing efforts and of any clearing deficiencies at that time, 4 his claim for breach of contract accrued, and the limitations period began to run, in July of 1975, some five and one-half years before suit was filed in May of 1980.

-2-

Although this lease was ambiguous in its schedule for land clearing and extrinsic evidence of the parties’ intent was admissible, no such evidence was offered. The district judge, in finding that the breach occurred in 1975, construed the lease within its four corners. Such an interpretative exercise presents a question of law, not fact, and our review is not limited by the clearly erroneous standard. Paragon Resources, Inc. v. National Fuel Gas Distribution Corp., 695 F.2d 991, 995 (5th Cir.1983). Our judicial task is said to be “restricted to the interpretation of the contract as the parties made it for themselves.” Lion Oil Co. v. Gulf Oil Corp., 181 F.2d 731, 733 (5th Cir.1950). In so doing, we must abide by tenets of contract construction and seek to ascertain the true intentions of the parties by examining “the entire writing in an effort to harmonize and give effect to all the provisions of the contract so that none will be rendered meaningless.” Coker v. Coker, 650 S.W.2d 391, 393 (Tex.1983) (emphasis in original). See also Blaylock v. American Guarantee Bank Liability Insurance Co., 632 S.W.2d 719, 722 (Tex.1982); R & P Enterprises v. LaGuarta, Gavrel & Kirk, Inc., 596 S.W.2d 517, 519 (Tex.1980). We must hon- or the presumption that parties to a contract intend every clause to have some effect, and attempt to reconcile ambiguous provisions unless they are “irreconcilable,” Ogden v. Dickinson State Bank, 662 S.W.2d 330, 332 (Tex.1983), or “necessarily repugnant.” Western Oil Fields, Inc. v. Pennzoil United, Inc., 421 F.2d 387, 389 (5th Cir.1970).

-3-

We do not read the lease to require that as of July 1, 1970, a minimum of 700 *984 acres would “thereafter” be cleared each year. The lease required Orange Rice Milling to clear at least 7,000 acres “during the ten (10) year period of this lease.” It then scheduled such clearing in increments of “a minimum of 700 acres each year during said term.” (emphasis added). There is no “thereafter” in the contractual language. The trial court’s insertion of this implicit deadline added an unintended term to the parties’ contract. Construing the lease to require that all clearing be complete by July of 1975, at the end of eight years, does not give meaning to the provision that 7,000 acres be cleared “during the ten (10) year period of [the] lease.” Nor can the requirement that a minimum of 700 acres be cleared each year be read, in harmony with other lease provisions, as a requirement that land be cleared in each year of the lease. Obviously, if 4,000 acres were to be cleared in the first three years of the lease, clearing 700 acres each year thereafter would require that some 8,900 acres be cleared, rather than the contracted for ceiling of 7,000 acres.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Linn Energy, LLC
576 B.R. 532 (S.D. Texas, 2017)
RA MACKIE & CO., LP v. PetroCorp Inc.
244 F. Supp. 2d 279 (S.D. New York, 2003)
Sullivan v. Mancuso
Fifth Circuit, 2000
In Re El Paso Refinery, L.P.
244 B.R. 613 (W.D. Texas, 2000)
Vaughn v. GULF COPPER
54 F. Supp. 2d 688 (E.D. Texas, 1999)
MCI Telecommunications Corp. v. Texas Utilities Electric Co.
993 S.W.2d 663 (Court of Appeals of Texas, 1996)
Pollock v. F.D.I.C.
Fifth Circuit, 1994
Fender v. Zapata Partnership, Ltd.
12 F.3d 480 (Fifth Circuit, 1994)
Parrett v. American Ship Building Co.
990 F.2d 854 (Sixth Circuit, 1993)
Parrett v. American Ship Building Company
990 F.2d 854 (Sixth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
747 F.2d 981, 1984 U.S. App. LEXIS 16254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/william-c-chapman-v-orange-rice-milling-company-and-edward-j-stine-ca5-1984.