Wilkins v. P.M.B. Systems Engineering, Inc.

741 F.2d 795
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 17, 1984
DocketNo. 83-2017
StatusPublished
Cited by22 cases

This text of 741 F.2d 795 (Wilkins v. P.M.B. Systems Engineering, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilkins v. P.M.B. Systems Engineering, Inc., 741 F.2d 795 (5th Cir. 1984).

Opinion

JOHN R. BROWN, Circuit Judge:

This is an appeal of a seaman’s personal injury suit against various defendants. Two of the defendants settled with the plaintiff in return for a Mary Carter agreement providing for their reimbursement from any recovery the plaintiff might later have from the non-settling defendants. We find the trial court’s holding 553 F.Supp. 201, after trial that one of the non-settling defendants had been liable, while holding that the same defendant’s only servant aboard the vessel was not liable, to be internally inconsistent. Because under the evidence the trial court as fact-finder could reasonably have reached either of two different consistent conclusions on liability, we remand for the trial court to make findings that are, in view of the law, internally consistent. Because there may yet be no recovery by the plaintiff, we do not reach any questions of indemnity, Mary Carter or otherwise.

Facts

On August 12, 1979, Allen Lane Wilkins was working as a member of the crew of the ARTHUR BRADY, a jack-up vessel being used to construct the platform around an oil well Christmas tree in the [797]*797outer continental shelf in the Gulf of Mexico. A heavy prefabricated platform was being hoisted from the vessel to be fitted over the well. When the platform was improperly hoisted, it swung into the side of the Christmas tree, causing a perceived danger that the high-pressure well would blow out. Wilkins quickly grabbed the single tag line hanging from the platform and attempted to pull it away from the Christmas tree. In so doing, Wilkins suffered a ruptured disk, which required surgery.

The well was owned by Centex Oil, who is not a party in this case. Centex contracted with defendant P.M.B. Systems Engineering, Inc. (PMB) to provide design and project management services for a large offshore oil field operation of which the satellite well involved in this case was a small part.1

As to the particular operation in which Wilkins was injured, PMB arranged for defendant Aquatic Equipment and Engineering (Aquatic) to provide a labor crew along with a supervisor who would be capable of directing the crew, ordering material when needed and solving minor problems on the spot. Wilkins was employed by Aquatic as part of this crew. The Aquatic supervisor was Donny Criswell. PMB also arranged for defendant Otis Engineering to provide the jack-up vessel for the Aquatic crew to work on. PMB did not contract with either Aquatic or Otis, but merely negotiated the contracts between Centex and Aquatic and Centex and Otis.

However, PMB did contract directly with Bob Hendershot Consultants, Inc. (Hender-shot) to provide inspection services and supervision of the installation work done by Aquatic. PMB prepared the design plans and specifications. Hendershot’s role was to be a field representative and liaison for PMB, explaining the plans to Aquatic; monitoring the progress of the work; ensuring that the work conformed to the specifications; reporting back to PMB periodically; securing PMB approval for changes in the plans; and approving all time cards for Aquatic employees. Hen-dershot assigned defendant Richard L. Eustace, a Hendershot employee, to fill this ■role. Thus, PMB had no employees of its own on the vessel or at the construction site.

A principal issue at trial concerned the extent of control actually exercised by Eus-tace over the manner of performance of the work of the Aquatic employees, including Wilkins. Specifically, there was controversy over whether Eustace had ordered Wilkins to grab and pull the tag line, and whether Eustace was responsible for the assignment of only one person to hold the tag line.

Wilkins initially brought suit in federal court based on the Jones Act and general maritime law against Aquatic, his employer, and Otis, the owner of the vessel on which he worked and was injured. Later, Wilkins joined PMB as a defendant. Then Aquatic and Otis reached a settlement agreement with Wilkins and so informed the trial court. The trial court then severed the claims against PMB and any other defendants, and dismissed the suit against Aquatic and Otis.

[798]*798The settlement contained a Mary Carter provision.2 In exchange for $75,-000, Wilkins not only released his claims against Aquatic and Otis, but assigned to them his causes of action against any other defendants. Specifically, Wilkins was to receive the first $10,000 of any recovery against the nonsettling defendants. Aquatic and Otis would get the next $75,-000, and Wilkins would retain any amount recovered beyond $85,000.

In the severed action against PMB, PMB filed third-party actions against Aquatic, Otis, Hendershot, and Eustace. Wilkins also sued Hendershot and Eustace directly. Prior to trial, all defendants asserted cross actions against the others seeking contribution or indemnity if they were held liable to Wilkins.

After a trial consisting partly of live testimony and partly of admitted depositions, the District Court issued a memorandum opinion. The Court found that PMB was in overall control of the work on the ARTHUR BRADY that day; PMB had undertaken responsibility for the staffing of the personnel needed to do the work; and PMB had negligently injured Wilkins by assigning too few personnel to the task.

In addition, the Court found that Aquatic was the Jones Act employer and was negligent in failing to provide Wilkins a safe place to work. Otis also was found negligent, because its crane operator failed properly to hoist the fabricated deck causing it to hit the Christmas tree. The Court apportioned negligence as follows: •

PMB 50%
Aquatic 25%
Otis 25%3

The total of damages found by the trial court was $258,698, Wilkins was awarded 50 percent of that amount ($129,349) from PMB. The Court enforced the release portion of the Mary Carter settlement agreement, and therefore there was no recovery against Aquatic and Otis. However, the Court awarded the full 50% of his damages to Wilkins, refusing to enforce the Mary Carter reimbursement provision of the settlement, under which Aquatic and Otis would have taken $75,000 of Wilkins’ recovery and thus effectively paid nothing for their 50% of responsibility. The Court em[799]*799phasized the harsh scrutiny exercised by courts in their discretion to protect seamen, who are wards of admiralty, e.g., Garrett v. Moore-McCormack Co., 317 U.S. 239, 63 S.Ct. 246, 87 L.Ed. 239 (1942); Wink v. Rowan Drilling Co., 611 F.2d 98 (5th Gir. 1980). Consequently, the Court concluded that the reimbursement provision was not supported by adequate consideration and would work an injustice if enforced.4

As to defendants Hendershot and Eus-tace, the Court held as follows:

The Court further finds no liability against Hendershot or Eustace, who at the time said accidental injury occurred was a borrowed servant of PMB. A master who loaned a servant to another for a special service is not liable for the negligent act of the borrowed servant where that act resulted in injury to an employee of the one who borrowed the servant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gantt v. Seadrill Americas, Inc.
360 F. Supp. 3d 402 (E.D. Louisiana, 2018)
Hicks v. BP Exploration & Prod., Inc.
310 F. Supp. 3d 754 (E.D. Louisiana, 2018)
Menard v. LLOG Exploration Co.
259 F. Supp. 3d 475 (E.D. Louisiana, 2017)
Richard Skinner v. Schlumberger Technology Corp.
655 F. App'x 188 (Fifth Circuit, 2016)
Watco Companies, Inc. v. Campbell
371 P.3d 360 (Court of Appeals of Kansas, 2016)
Stolt Achievement v. Dredge B E Lindholm
447 F.3d 360 (Fifth Circuit, 2006)
Stolt Achievement, Ltd. v. Dredge B.E. Lindholm
447 F.3d 360 (Fifth Circuit, 2006)
Stolt Achievement, Ltd. v. Lindholm
440 F.3d 266 (Fifth Circuit, 2006)
Karim v. Finch Shipping Co.
374 F.3d 302 (Fifth Circuit, 2004)
Thibodeaux v. Ferrellgas, Inc.
717 So. 2d 668 (Louisiana Court of Appeal, 1998)
Sullivan v. Rowan Companies, Inc.
952 F.2d 141 (Fifth Circuit, 1992)
Hoops v. Watermelon City Trucking, Inc.
846 F.2d 637 (Tenth Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
741 F.2d 795, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilkins-v-pmb-systems-engineering-inc-ca5-1984.